Title: Elasticplastic FEM Simulation and Analysis of the Entire Construction Process of Culvert
1Elastic-plastic FEM Simulation and Analysis of
the Entire Construction Process of Culvert
The 1st China-Japan Seminar for Graduate Students
in Civil Engineering
- By LI Jun-wei
-
- E-mail 0310020154_at_smail.tongji.edu
.cn - or lijunwei76_at_163.com
- Department of Geotechnical
Engineering - Tongji University, Shanghai,
China, 200092 - Nov.6, 2004
2Outline
- 1. Research Background
- 2. The Theory of Elastic-plastic FEM
Simulation of the Entire Construction Process of
Culvert - The Mode of Elastic-plastic Finite Element Method
- The types of elements used in FEM simulation
- The basic theory of FEM simulation
- Loading process simulation by step by step
construction - 3. Case Study
- Simplification of case
3Outline
- 4. Analysis on the simulation results
- Results analysis on the simulation of
foundation excavation - Results analysis on the stress contour of
excavation step by step. - Results analysis on the displacement field
contour of excavation step by step. - Simulation results analysis on the
foundation-pits filling - The settlement and vertical stress contour
analysis after the backfilling completion. - Discussion on the simulation results.
- 5. Conclusion
41. Research Background
- Much research work on
- ? Foundation-pit excavation.
- ? Mechanics characteristics of the culvert
structure under earth pressure or live loadings. - ? Interaction between the culvert and the
soil. - ? The designing methods and procedures.
-
5- But, as for the construction of the culvert,
including ?foundation-pit excavation, ?casting
structure concrete and ?the backfilling the
foundation-pit and covering fill layers, this
continuous construction process is always been
ignored. - Although some research work had involved the
backfilling computation, yet, after the
excavation completion, the primary stress field
was assumed as the self-weight stress field. This
kind of solution is not reasonable. The main
reason is that their stress history and stress
path are distinct from each other. - So, present research on the entire construction
process of culvert is needed very much in
practical construction, design and analysis.
62. The Theory of Elastic-plastic FEM Simulation
of the Entire Construction Process of Culvert
- 2.1 The Model of Elastic-plastic Finite Element
Method - In this research work, elastic-plastic
hardening constitutive finite element (FE) model
and Drucker-Prager yield criteria are used. The
yield function of it could be expressed the
following -
- 2.2 The types of elements used in FEM
simulation - Beam elements, quadrilateral isoparametric
elements and Goodman contact elements etc.
72.3 The basic theory of FEM simulation
- The method of generating initial stress
field in this research is according to the
following steps - 1) According to the formula of initial
stress, compute the initial Gauss stress in
different depth. Thus a hypothesis initial stress
field was formed -
- Formula of initial stress
-
- 2) Compute the equivalent nodal stress
vector -
- 3)Carry out the FEM computation. At this
time, the loading is only q , which is divided
into several increments and added to the
structure system. It is noted that at the
beginning of the increment, the stress is zero. -
- Using above, a modified initial stress
field and initial elastic-plastic distribution
were obtained, which could be presented the
entire characteristics of the stress field and
confirm with the yield criterion.
8The Method of Simulating Release Loading
- The Modified Manas Method is used in this
research work. Owing to the influence of the
volume force (such as self-weight, seepage force,
etc.) on the releasing loading caused by
excavation is taken into consideration. It can be
expressed - Where, N - the displacement interpolation
function - B - the strain matrix
- - the equivalent nodal force
caused by excavation - - all elements that will be
excavated - - area load (the
excavation loading) acting on the - - the excavated boundary
surface.
9- 2.4 Loading process simulation by step by step
construction - In the simulation, the influence of
the gravity of backfilling soil only applies on
the soil that has been filled before this
construction, but it has no influence on the
future filling soil. -
- Using the method of increasingly
adding the number of elements in computation
domain to simulate backfilling the foundation-pit
is an important construction process. By applying
the self-weight loading of the newly backfilling
elements and construction grinding force in every
backfilling layer, the displacement increment and
stress increment of every newly added element are
obtained By this way, the backfilling
construction process is really simulated in
practice.
103. Case Study
- A horseshoe-shaped culvert (see right
Fig.1) was designed for the soil dam with the
length 110m, entry elevation 463.00m, outlet
elevation 461.17m. -
- The foundation is the original state
silty clay. The slope degree of open-excavation
is 11.5, and the width of the bottom of it is
12m. The fill is the silty clay. The elevation on
the top dam is 489.86m. The maximum height above
the culvert is 20.46m.
Fig.1 the section of culvert. / cm
113.1 Simplification of case
- Structural characteristicTake the unit
length to solve - the problem as a plane strain problem.
- Structural symmetry The computation is
carried on by taking the half of the culvert
along with the vertical symmetrical axis. -
- The computation domain is taken by 2 to 3
times diameter of culvert. -
- The constraint condition the vertical
displacements of nodes on the symmetry and
lateral side are freedom and their horizontal
displacements are constraint and the
displacements of the nodes on the bottom of the
side are fixed horizontally and vertically.
124. Analysis on the simulation results
- The mesh used to simulate foundation-pit
excavation in FE computation is given in Fig.2. -
134.1 Results analysis on the simulation of
foundation excavation
- A) Results analysis on the stress contour of
excavation step by step
?Seen from the Fig.3 and Fig.4, we can
conclude that the contour of are nearly
parallel with the ground surface away from the
free face. At the end of excavation, stress
concentration occurs.
14A) Results analysis on the stress contour of
excavation step by step
- ?With the free face increasing, near
the free face, the stress contour tends to
parallel with the free face. - Theoretically, with the formation of
free face increasingly, excavation makes the soil
unload, as result, near the free face, the soil
column pressure acting on the soil decreases. So,
in the Fig.4 and Fig.5 the contour of stress
shows this law. When excavation is finished, in
the vertical direction, the soil pressure
decreases by 1018 compared with the soil
column stress. So, if use the self-weight stress
field as the primary stress field before filling
the foundation-pit, then, the results will be not
accurate and not agreement with the practice.
15B) Results analysis on the displacement feild
contour of excavation step by step
Elevation of foundation-pit /m
With the formation of the foundation-pit
slope step by step, shear deformation of the soil
towards free face occurs and increase. From Fig.7
,Fig.8 ,Fig.9 and Fig.10, we can drawn the
conclusions
? The horizontal displacements of the soil
increase with the excavation depth increasing
near the free face. But the maximum horizontal
displacement does not occur on the free face, it
occurs at a certain depth under the foot of the
slope. At the same time, the maximum horizontal
displacement shifts towards the central of the
excavation.
16Elevation of foundation-pit /m
Elevation of foundation-pit /m
Distance from the central axis of the foundation
d/m
Distance from the central axis of the foundation
d/m
Fig.9 At ?h13m the contour of vertical
displacement /cm
Fig.10 The contour of vertical displacement after
excavation completion. /cm
- ? Because the soil is at the state of
unloading at this period, resilience will occur,
and the displacement in y-direction at a certain
point will increase with the depth of excavation
increasing. In different construciton period, the
displacement in y-direction show that the
maximum resilience occurs in the place of central
symmetry axis, and the resilience decreases with
the distance from the symmetry axis increasing.
On the slope surface, the displacement in
y-direction tends to increse with the depth of
excavation increasing. At the place away from the
excavation area, a small settlement occurs, which
will expand with the the depth of excavation
increasing. This law is agreement with the
theoretical analysis results.
174.2 Simulation results analysis on the
foundation-pits filling
- After the completion of foundation-pit
excavation, firstly, the culvert structure is
constructed, at this time, assuming the force
acting on the foundation by the culvert bodys
weight is loaded only by once in the FE
computation. After this FE computation, the
obtained stress field and displacement field is
treated as the primary state of filling
foundation-pit. Then, the backfilling begins
layer by layer and the roller applies the
grinding force to make the fill compact. The FEM
simulates the entire process., the results shown
in the Fig.11 and Fig.12.
18A) The settlement and vertical stress contour
analysis after the backfill completion
- 1)The Settlement and Vertical stress contour
analysis after the backfill completion.
Elevation of foundation-pit /m
Distance from the central axis of the foundation
d/m
Fig.11 Contour of vertical stress after
backfilling completion. /kPa
19- Due to the larger stiffness and little
deformation of the culvert compared with the
soil, during the backfilling, the culvert
structure has the behavior of holding back the
settlement of the fill. So, near the tunnel wall
of the culver, the settlement is smaller than the
settlement away from the tunnel wall. In the
Fig.11, the settlement on the top of the culvert
is smaller than the settlements on the two sides
of it. So, in the contour of vertical stress
field, the stress concentration occurs on the top
of it, however, beside two side-walls, the stress
is smaller. - Additionally, owing to the uplifting
effect of the culvert structure on the settlemt
of around soil, the vertitcal stress on the
lining structure increases. As result of it, the
relatively tangential displacement between
side-wall and the fill and frictional contact
force occures . The manifestation of the
frictional contact is to holdback the settlement
of the fill on the two side of tunnel wall.
Therefore, the vertical earth pressure on the two
sides of the tunnel wall is smaller than the
earth column pressure. Besedes these, because of
the increment of friction contact and the
increment of vertical stress on the top of the
culvert, the compression stress on the bottom of
culvert base and settlement deformation compared
with its side increases with it as well.
202)Discussion on the simulation results
Conventional method
Fig.13 Settlement comparison between
step-by-step loading and one-step
loading
Using this method
212) Discussion on Conventional Method
- In the conventional FE computation, the fill
was assumed to backfill directly to the top of
the dam instead of using backfilling layer by
layer, and the loading was applied the structure
entirely for only one time. So, the structure
would bear every part of the loading. And the
displace-ment of every point is the result of the
self-weight of the entire fill. within the
compression layer (h-z), the stress presents the
trapezoid shape distribution ABCD. Assumed
the soil is elastic medium, the unit weight of
soil is , the deformation modulus for unit
volume is ,and the coefficient of bulk
compressibility is constant, thus, the settlement
of A point is
222)Discussion on the simulation results in this
work
- In fact, the force applied the culvert increased
step by step. When the real construction reaches
a certain A point, the self-weight of newly
backfilled elements and the construction grinding
force is only applied to the soil that has been
constructed fill, however, the up layer soil will
not undertake any loading At the FE simulation
process, the meshes will be created only with the
respect of the soil that bad been backfilled,
which can embody the real construction process.
This is the characteristics of the procedure in
this paper. When the backfilling construction was
complete, above this surface, there is no any
loading, so there is no settlement. Therefore,
the settlement of A point is zero. When the
height of the fill reach another height above the
A point, then, the settlement will occur at the A
point. When the fill reached the top of the
designed elevation, the stress caused settlement
of A point in the compression layer presents
rectangular distribution, see ABED in the Fig.13.
so, the settlement of A is
232)Discussion on the simulation results in this
work
- In fact, backfilling the culvert
foundation is not an one dimensional problem.
Owing to stress distribution is not always
echelon shape, and the material has the
non-linear characteristic, the maximum settlement
is always located between h/3 and h/2. The
relationship between the settlement of the fill
above the top of the culvert and the height of
fill is shown in the Fig.14. - Additionally, due to the interaction
between the culvert and the fill, the maximum
settlement is not located at the top of the
culvert. From the Fig.14, it could be drawn a
conclusion that the simulation results is
agreement with the theoretical analysis results.
24(No Transcript)
255. CONCLUSION
- From the FE simulation results of the
example of the Huihe Reservoir reinforcement
engineering construction process, some concluding
remarks can be drawn - (1) The programmed procedure can reflect the
continuity of the loading or unloading applied
and the deformation of the soil. And the general
changing laws were obtained using these
simulation methods. The methods embody the
interacting relationship between the
structure-soil-foundation and the harmony
relationship of deformation. The simulation
results are agreement with the theoretical
analysis. - (2) With the depth of the excavation
increasing, the vertical resilience of soil and
lateral displacement on the slope increase. The
results show that the resilience at the central
axis of basement is maximal and the maximum
lateral displacement occur near the foot of the
slope of the foundation-pit. But the maximum
would drift towards the central of the
foundation-pit. The stress field decrease about
10 to 18 compared with the self weight stress
field.
265. CONCLUSION
- (3) As the backfilling soil is finished,
due to the uplifting effect of the culvert, the
state of the soil around the crown becomes small
displacement and large stress domains. The
maximum settlement is not located the top of the
culver, but at the 1/3 to 1/2 height of the fill.
27Our Beautiful Campus
28-
- Thank You !
- Hope you have a pleasant
- time in Tongji University
-
-