Title: Target Operation and Status Report
1Target Operation and Status Report
- Chris Booth for Target Team
- 13th January 2009
- Outline
- Current target performance
- Investigation of demonstrator failure
- New mechanical design
- Control monitoring issues
- Particle production vs. beam loss
2- Current ISIS Target
- Target operation in ISIS for beam-line studies
gt190K pulses by end December. - Actuation control have operated flawlessly no
target drops. - Software (DAQ monitoring) run well, allows
remote monitoring. - System operated by non-experts.
- Target behaviour stable and reproducible.
- 29th November target accidentally parked in
beam - Interlock added to prevent parking with frame
lowered - 20th December target stopped actuating
- Apparent mechanical failure.
- No dust visible on inspection plate.
- Removed 10th January for examination. Awaiting
news. - (Any connection with previous incident?)
3- Possible Demonstrator failure causes
- Misalignment of bearings and shaft. ()
- Partial demagnetisation of permanent magnets
causing non-axial forces. () - Distortion of coils causing non-axial forces.
- Dynamic distortion of shaft.
- Poorer quality DLC coatings on shaft and/or
bearings. - () Already eliminated at last CM.
- Above are addressed in the following slides.
Several experts from RAL, Sheffield Materials and
outside companies (as well as MICE) have been
consulted and provided valuable expertise.
4- Stator Field Measurements Modelling
- Field measured (for DC current) by Craig
MacWaters Paul Smith. FEA modelling by Paul.
See following slides. - Small azimuthal variation seen.
- Equivalent to coil offsets 0.2 mm.
- This is also the precision of the position
reproducibility. - Upper limit on coil misplacements is therefore
0.2 mm. - Further FEA in progress to determine how this
maps onto transverse force on the shuttle
magnets.
5Stator field measurements
- B Field measured for every 0.2mm axially over a
distance of 120mm. Repeated at 30 deg
increments.
6FEA Modelling
Repeated for AC Data Similar Match
7- Dynamic distortion of shaft
- Distortion of shaft ?
- Stephanie Yang/Wing Lau modelled behaviour under
acceleration. - 30 Hz mode found (c.f. 30 ms acceleration period
in operation. - High speed camera data also shows wagging
motion at similar frequency. - (No evidence from camera that Sheffield
shock-absorbing mounting is significant.)
8- Dynamic distortion of shaft
- Distortion of shaft ?
- Stephanie Yang/Wing Lau modelled behaviour under
acceleration. - 30 Hz mode found (c.f. 30 ms acceleration period
in operation. - High speed camera data also shows wagging
motion at similar frequency. - (No evidence from camera that Sheffield
shock-absorbing mounting is significant.)
9- Surface coating problems
- Poor Diamond-Like Carbon (DLC) coatings ?
- Sheffield RAL team visited coating company
(TecVac), who had examined failed parts. - Likelihood of adhesive failure due to presence of
cleaning or polishing materials, or oxidation due
to wire erosion of bearings. - Sharp edges give electropotential leading to
uneven coatings. - Surface quality pre-coating was also probably
inadequate. (Recommend 0.1 to 0.02 Ra compared
with current 1.6 Ra.) - Adequate surface finish difficult to achieve with
present machined cruciform shaft.
10- New Mechanical Design
- Jason Tarrant producing revised mechanical
design. - Discussed at weekly target phone meetings.
- Details in Target Parallel this afternoon only
summary here. - Huge amount of work summarised in one slide!
- More rigid stator assembly.
- New flanges with bearings machined in situ.
- Improved alignment, reduced tolerances.
- Radically different shaft design to improve
rigidity, ease of construction, surface finish. - Tubular lower section (not cruciform)
- same mass/length as at present
- Flat on upper cylindrical section, with
anti-rotation piece on bearing. - Shorter shaft by reducing flange revised bearing
positions.
11Revised stator body
12Upper Bearing Design
Single piece main body
- Alternative bearing design
Clearance for vane (potential risk if adding vane
later otherwise simpler bearing)
Wire cut from single piece for accurate wedge fit
Full bearing merges into section for anti-rotation
Wedge dowel for full x,y,z location of clamp
M/C with block in place to prevent tool wander
Anti rotation Feature (rounded or flat bearing
face options)
13- Conclusions of Target Workshop last week
- Timescale very tight.
- Drawing up documents for review.
- Key materials (Ti tube) should be ordered now.
- Baseline target is continued 6 mm tube
- Other geometries/materials may have particle
production advantages - Must not delay installation of next target
- Baseline coating is DLC
- Other coatings (HIPIMS, WS2, WS2 over DLC) may
have advantages. - Investigation will be left for subsequent
targets. - Informally, ISIS representatives are happy with
design. - Must have two drives ready for Demonstrator and
installation in ISIS during April shutdown.
14- Control Electronics Upgrade
- Present system stable, reliable but expert
system, unfriendly to normal users! - PIC processors at computational and I/O limits.
- Complete redesign planned with improved
interfaces, PC configuration control,
flexibility, enhanced feedback, - FPGA-based system using USBDAQ board proposed.
- James Leaver (IC, FPGA experience) and Paul Smith
(present target control designer) working
together. - 5 crates of electronics may come down to single
FPGA plus few daughter cards (for A to D etc)! - Requested input from MICE community over desired
functionality. - Major project expected to take 12 months.
- See talk this afternoon!
15USBDAQ
4Mb PROM
1M Gate Spartan 3 FPGA
USB Mini-B
Cypress SX2 USB Interface
Single Ended User IO
1.2V Regulator
Differential / Single Ended User IO
2.5/3.3V Regulator
16- DAQ Monitoring
- Change to new DAQ card has led to driver
problems. - Currently converting digital position to
analogue! Unsatisfactory. - DAQ code (James Leaver) dumps data to
individual pulse files. - Target depth, beam intensity, bam losses
(various), frame status recorded - Wish to include beam position, external delay
- Various monitoring codes (inc. EPICS based see
Pierricks talk this afternoon). - Hardware control upgrades will imply DAQ,
monitoring control software redesigns. - Again, input feedback requested from the
community. - For more details, see talk this afternoon!
17- Beam-loss Particle Production
- Adam Dobbs ORBIT simulation of target ISIS
- Different target geometries orientations.
- Present orientation losses mainly near target
- 90? rotation losses near injection (see plots)
- Other angles, geometries considered.
- Marco Apollonio G4Beamline simulation of
collection - Pion acceptance into Q1 largely unaffected by
target shape or orientation. - Aluminium, Carbon, Beryllium also considered.
- Detailed study required to optimise collected
pion to beam loss ratio. - But must also consider mechanical and thermal
properties! Aluminium could melt! - For more details, see talk in beam-line session.
18Present orientation 90? rotated