Title: ILC Beam Delivery System Layout and Lattice Design
1ILC Beam Delivery System Layout and Lattice
Design
-
Deepa Angal-Kalinin - ASTeC,
Cockcroft Institute -
Cockcroft Institute SAC 23-24th November 2006
2Lattice Design and Simulation Team_at_CI
- Manchester
- Rob Appleby
- Dragan Toprek
- Adina Toader
- Ph.D. Student
- Anthony Scarfe
- ASTeC
- Frank Jackson
- James Jones
- Stephan Tzenov
- Deepa Angal-Kalinin
3Background
- Before the technology decision for the linear
collider (August 2004) studies were mainly
focussed on TESLA design - Problems related to head-on extraction
- Poor collimation performance
- Local chromaticity final focus system was
designed but was not integrated with rest of the
BDS - Alternative solutions to head-on small vertical
or small horizontal crossing angle
collaborations with LAL(Orsay), CEA(Saclay) - The team developed understanding of BDS design
and requirements, implemented the required
simulation codes in order to contribute to the
evolving designs, established good collaborations
- After the technology decision
- Small crossing angle solution and extraction
line design required urgently - NLC collimation and final focus design was
adapted to ILC, performance poor than NLC
4Interaction region - Crossing angle choice
Very small 0 2 mrad Large 14
25 mrad
Incoming and outgoing beams
Shared magnets gt coupled design
Separate magnets
- Challenges in both the schemes
- Large aperture shared magnets or compact magnets
- No/ marginal/complete reliance on crab crossing
- Axial/Non-axial field in the solenoid
- Preserve pre-IP beam or emphasis post-IP beam
- Reflected backgrounds or pre-IP constraints
- Physics prefers head-on with minimum
background
52mrad crossing angle extraction line design
- CI team took a lead role in developing the 2
mrad extraction line design (part of
SLAC-BNL-UK-France Task Force) - Due to higher cost of this line and challenges
in magnet design, this crossing angle solution is
now an alternative to the baseline with 14 mrad - CI team is working with LAL to optimise the
extraction line to minimise the beam losses and
magnet apertures - The optimised doublet (Appleby, Bambade, Toprek)
at 500 GeV CM show significantly less losses in
the IR region - Re-designing the rest of the line minimum line
to start with (Appleby)
- Comparison of number of hits in VXD for the 2
mrad and 20 mrad (with DID) showed that the pair
background increases for 20 mrad with DID - gt 14 mrad anti-DID solution, now adapted for
the RDR
6Contributions to the ILC collimation optics
- Tools to estimate the collimation depths for
different crossing angle geometries
- Better collimation efficiency
Halo Tracking to FD entrance
Original Performance
Collimation depth
Optimisations still continuing
F. Jackson
New Performance
7Contributions to the test facilities ATF2
Beam sizes before and after tuning
1mrad QD0 Rotation
- Tuning procedures and tolerances for the ATF2
- Several generic options for tuning of final-focus
beam at IP Traditional, Rotation Matrix, dumb - Would like to test these algorithms at ATF2,
which will present an ideal opportunity to
provide some limited analysis of the viability of
these methods. - Aim to increase our contributions with the help
of Ph.D. student Anthony Scarfe - Expertise in tuning area, used to define the
correction method in the long undulator section - The techniques developed are applicable to any
accelerator
Relative luminosity vs tuning knob
J. Jones
8Contributions to the test facilities ESA
vert beam size 83?m for collimator wakefield tests
- Optics design for several experiments at ESA,
SLAC (January06 and April06 beam tests) - Require small beam sizes in x and y planes for
collimator wakefield and BPM experiments - Optics modelling challenges high dispersion and
SR in A-line - Careful emittance and Twiss measurements followed
by beam tuning - Achieved goals of ?y?100?m and ?x200?m in
separate lattice configurations
horz beam size 240?m for BPM studies
F. Jackson
9ILC BDS Layout Changes
First ILC Workshop, KEK, November 2004 Working
hypothesis
10ILC BDS Layout Changes
to Vancouver, July 2006
11ILC BDS Layout Changes
- At Vancouver (July 2006), first cost
estimates indicated significantly higher costs
for 2 mrad line gt base line configuration
changed to 14/14 from 20/2.
ILC GDE
14mrad
14mrad
12ILC BDS Layout Changes
1 IR two complementary push-pull detectors
discussed with detector concepts and WWS
ILC GDE
14 mrad
CCR will be submitted this week by the BDS area
leaders
13Present activities and Objectives
- Contributing to several critical decisions on the
ILC Interaction Region(s) - The BDS lattice design for the new baseline
configuration - Risks vs performance
- Push-pull task force
- Optimisations and tuning studies
- Layout details CFS (shafts/caverns, IR halls)
- Surface assembly for the detectors
- Muon walls
- Contributing to the RDR costing and writing
- Optimisations for 2 mrad and modified head-on
extraction line designs cost effective, with
input from magnet designers - studying the minimum layout design for these
options without downstream diagnostics
14Future Plan Beam Line Integration
- Continue lattice optimisations for better
performance, include realistic beam and machine
errors - ATF2 skew/emittance LW, final focus, tuning, tail
folding tests - Large crossing angle issues
- Beam Line Integration Major involvement of
CCLRCs engineering expertise - Lattice design and simulations
- Collimation design
- Vacuum design
- Other CI major activities viz crab system and
beam dumps integrate naturally with this proposal - Depends on the outcome of LC-ABD2
funding request
Background wake fields main concern
15Future Plan Collimation Design
- BDS and extraction lines include 20 different
types of collimators - Most critical ones are with the adjustable gaps
ltmm and long tapers - CI is a leading contributor (with CCLRC,
Birmingham and SLAC) on critical collimator
issues wakefields, survivability - ESA and simulations (C. Beards talk)
- Future programme builds on this and will
prototype ILC collimators for - optimal mitigation of wakefields and component
damage (and its detection) - overall engineering design tolerances,
alignment, movable jaws, cooling, machine
protection. - Depends on the outcome of LC-ABD2 funding request
16Future Plan Vacuum Design
- BDS has complex vacuum design
- Spoilers with fraction of millimetres openings to
beam pipe radius of 200mm in the extraction lines - Synchrotron radiation at 250-500 GeV is
significant - No experimental photon/electron desorption data
exists at such energies - The interaction region geometry is most complex
- Backgrounds in the detector are critical
- Push-pull detectors will need special engineering
solutions - Real vacuum chamber design (material and detailed
designs) to estimate the wakes - Manufacturing and alignment tolerances -
stringent - MPS issues
- Depends on the outcome of LC-ABD2 funding request
17ILC BDS Collimation, crab system, beam dumps
- Layout lattice design has a close link with the
other tasks lead by the CI -
Collimation Carl Beard - Crab
system Peter McIntosh - Beam
dumps Rob Appleby
Next two talks
ILC GDE
18The ILC beam dumps
- ILC beam dumps and collimators are challenging -
high power (18MW _at_1TeV CM) and short energy
deposition showers - No experience with such beam dumps. Designs have
been scaled from low power beam dumps - More simulation and prototypes required
- Using CCLRCs expertise in high power targets
(ISIS, T2K), a programme lead by CI (Appleby) and
CCLRC (Densham) has been initiated. - Definition of UK beam dumps programme, consisting
of physics (CI) and engineering (CCLRC) - UK contribution to dumps and collimator costing
- Physics simulation studies
19Future plans Beam Dumps
- The CI (Appleby) will lead physics simulation of
dumps and collimators throughout the ILC - Energy depositions
- Shielding and activation of water dump baseline
and collimators - Costing and engineering expertise (CCLRCCI)
- Study of only viable alternative to main dump
the Noble gas dumps (Will seek new funding).
Crucial if unknown show-stopper for water dump
and alternative needed. - Site dependent
- Depends on the outcome of LC-ABD2 funding request
20Summary
- The CI team
- has developed a skill base for optics and
simulations - has made significant contributions to the ILC
baseline and is contributing to the Reference
Design Report - is very well integrated with the global design
effort - intends to take a bigger role during the
technical design phase with CCLRCs engineering
expertise - Most of the proposed work depends upon the
outcome of LC-ABD2 funding proposal submitted to
PPARC