ILC Beam Delivery System Layout and Lattice Design - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

ILC Beam Delivery System Layout and Lattice Design

Description:

Poor collimation performance ... NLC collimation and final focus design was adapted to ILC, performance poor than ... estimate the collimation depths for ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 21
Provided by: lanc2
Category:

less

Transcript and Presenter's Notes

Title: ILC Beam Delivery System Layout and Lattice Design


1
ILC Beam Delivery System Layout and Lattice
Design

  • Deepa Angal-Kalinin
  • ASTeC,
    Cockcroft Institute


Cockcroft Institute SAC 23-24th November 2006
2
Lattice Design and Simulation Team_at_CI
  • Manchester
  • Rob Appleby
  • Dragan Toprek
  • Adina Toader
  • Ph.D. Student
  • Anthony Scarfe
  • ASTeC
  • Frank Jackson
  • James Jones
  • Stephan Tzenov
  • Deepa Angal-Kalinin

3
Background
  • Before the technology decision for the linear
    collider (August 2004) studies were mainly
    focussed on TESLA design
  • Problems related to head-on extraction
  • Poor collimation performance
  • Local chromaticity final focus system was
    designed but was not integrated with rest of the
    BDS
  • Alternative solutions to head-on small vertical
    or small horizontal crossing angle
    collaborations with LAL(Orsay), CEA(Saclay)
  • The team developed understanding of BDS design
    and requirements, implemented the required
    simulation codes in order to contribute to the
    evolving designs, established good collaborations
  • After the technology decision
  • Small crossing angle solution and extraction
    line design required urgently
  • NLC collimation and final focus design was
    adapted to ILC, performance poor than NLC

4
Interaction region - Crossing angle choice
Very small 0 2 mrad Large 14
25 mrad
Incoming and outgoing beams
Shared magnets gt coupled design
Separate magnets
  • Challenges in both the schemes
  • Large aperture shared magnets or compact magnets
  • No/ marginal/complete reliance on crab crossing
  • Axial/Non-axial field in the solenoid
  • Preserve pre-IP beam or emphasis post-IP beam
  • Reflected backgrounds or pre-IP constraints
  • Physics prefers head-on with minimum
    background

5
2mrad crossing angle extraction line design
  • CI team took a lead role in developing the 2
    mrad extraction line design (part of
    SLAC-BNL-UK-France Task Force)
  • Due to higher cost of this line and challenges
    in magnet design, this crossing angle solution is
    now an alternative to the baseline with 14 mrad
  • CI team is working with LAL to optimise the
    extraction line to minimise the beam losses and
    magnet apertures
  • The optimised doublet (Appleby, Bambade, Toprek)
    at 500 GeV CM show significantly less losses in
    the IR region
  • Re-designing the rest of the line minimum line
    to start with (Appleby)
  • Comparison of number of hits in VXD for the 2
    mrad and 20 mrad (with DID) showed that the pair
    background increases for 20 mrad with DID
  • gt 14 mrad anti-DID solution, now adapted for
    the RDR

6
Contributions to the ILC collimation optics
  • Tools to estimate the collimation depths for
    different crossing angle geometries
  • Better collimation efficiency

Halo Tracking to FD entrance
Original Performance
Collimation depth
Optimisations still continuing
F. Jackson
New Performance
7
Contributions to the test facilities ATF2
Beam sizes before and after tuning
1mrad QD0 Rotation
  • Tuning procedures and tolerances for the ATF2
  • Several generic options for tuning of final-focus
    beam at IP Traditional, Rotation Matrix, dumb
  • Would like to test these algorithms at ATF2,
    which will present an ideal opportunity to
    provide some limited analysis of the viability of
    these methods.
  • Aim to increase our contributions with the help
    of Ph.D. student Anthony Scarfe
  • Expertise in tuning area, used to define the
    correction method in the long undulator section
  • The techniques developed are applicable to any
    accelerator

Relative luminosity vs tuning knob
J. Jones
8
Contributions to the test facilities ESA
vert beam size 83?m for collimator wakefield tests
  • Optics design for several experiments at ESA,
    SLAC (January06 and April06 beam tests)
  • Require small beam sizes in x and y planes for
    collimator wakefield and BPM experiments
  • Optics modelling challenges high dispersion and
    SR in A-line
  • Careful emittance and Twiss measurements followed
    by beam tuning
  • Achieved goals of ?y?100?m and ?x200?m in
    separate lattice configurations

horz beam size 240?m for BPM studies
F. Jackson
9
ILC BDS Layout Changes
First ILC Workshop, KEK, November 2004 Working
hypothesis
10
ILC BDS Layout Changes
to Vancouver, July 2006
  • Snowmass, August 2005

11
ILC BDS Layout Changes
  • At Vancouver (July 2006), first cost
    estimates indicated significantly higher costs
    for 2 mrad line gt base line configuration
    changed to 14/14 from 20/2.

ILC GDE
14mrad
14mrad
12
ILC BDS Layout Changes
  • Valencia, November 2006

1 IR two complementary push-pull detectors
discussed with detector concepts and WWS
ILC GDE
14 mrad
CCR will be submitted this week by the BDS area
leaders
13
Present activities and Objectives
  • Contributing to several critical decisions on the
    ILC Interaction Region(s)
  • The BDS lattice design for the new baseline
    configuration
  • Risks vs performance
  • Push-pull task force
  • Optimisations and tuning studies
  • Layout details CFS (shafts/caverns, IR halls)
  • Surface assembly for the detectors
  • Muon walls
  • Contributing to the RDR costing and writing
  • Optimisations for 2 mrad and modified head-on
    extraction line designs cost effective, with
    input from magnet designers
  • studying the minimum layout design for these
    options without downstream diagnostics

14
Future Plan Beam Line Integration
  • Continue lattice optimisations for better
    performance, include realistic beam and machine
    errors
  • ATF2 skew/emittance LW, final focus, tuning, tail
    folding tests
  • Large crossing angle issues
  • Beam Line Integration Major involvement of
    CCLRCs engineering expertise
  • Lattice design and simulations
  • Collimation design
  • Vacuum design
  • Other CI major activities viz crab system and
    beam dumps integrate naturally with this proposal
  • Depends on the outcome of LC-ABD2
    funding request

Background wake fields main concern
15
Future Plan Collimation Design
  • BDS and extraction lines include 20 different
    types of collimators
  • Most critical ones are with the adjustable gaps
    ltmm and long tapers
  • CI is a leading contributor (with CCLRC,
    Birmingham and SLAC) on critical collimator
    issues wakefields, survivability
  • ESA and simulations (C. Beards talk)
  • Future programme builds on this and will
    prototype ILC collimators for
  • optimal mitigation of wakefields and component
    damage (and its detection)
  • overall engineering design tolerances,
    alignment, movable jaws, cooling, machine
    protection.
  • Depends on the outcome of LC-ABD2 funding request

16
Future Plan Vacuum Design
  • BDS has complex vacuum design
  • Spoilers with fraction of millimetres openings to
    beam pipe radius of 200mm in the extraction lines
  • Synchrotron radiation at 250-500 GeV is
    significant
  • No experimental photon/electron desorption data
    exists at such energies
  • The interaction region geometry is most complex
  • Backgrounds in the detector are critical
  • Push-pull detectors will need special engineering
    solutions
  • Real vacuum chamber design (material and detailed
    designs) to estimate the wakes
  • Manufacturing and alignment tolerances -
    stringent
  • MPS issues
  • Depends on the outcome of LC-ABD2 funding request

17
ILC BDS Collimation, crab system, beam dumps
  • Layout lattice design has a close link with the
    other tasks lead by the CI

  • Collimation Carl Beard
  • Crab
    system Peter McIntosh
  • Beam
    dumps Rob Appleby

Next two talks
ILC GDE
18
The ILC beam dumps
  • ILC beam dumps and collimators are challenging -
    high power (18MW _at_1TeV CM) and short energy
    deposition showers
  • No experience with such beam dumps. Designs have
    been scaled from low power beam dumps
  • More simulation and prototypes required
  • Using CCLRCs expertise in high power targets
    (ISIS, T2K), a programme lead by CI (Appleby) and
    CCLRC (Densham) has been initiated.
  • Definition of UK beam dumps programme, consisting
    of physics (CI) and engineering (CCLRC)
  • UK contribution to dumps and collimator costing
  • Physics simulation studies

19
Future plans Beam Dumps
  • The CI (Appleby) will lead physics simulation of
    dumps and collimators throughout the ILC
  • Energy depositions
  • Shielding and activation of water dump baseline
    and collimators
  • Costing and engineering expertise (CCLRCCI)
  • Study of only viable alternative to main dump
    the Noble gas dumps (Will seek new funding).
    Crucial if unknown show-stopper for water dump
    and alternative needed.
  • Site dependent
  • Depends on the outcome of LC-ABD2 funding request

20
Summary
  • The CI team
  • has developed a skill base for optics and
    simulations
  • has made significant contributions to the ILC
    baseline and is contributing to the Reference
    Design Report
  • is very well integrated with the global design
    effort
  • intends to take a bigger role during the
    technical design phase with CCLRCs engineering
    expertise
  • Most of the proposed work depends upon the
    outcome of LC-ABD2 funding proposal submitted to
    PPARC
Write a Comment
User Comments (0)
About PowerShow.com