Target%20Station%20and%20Target%20Damage%20Session%20-Introduction- - PowerPoint PPT Presentation

About This Presentation
Title:

Target%20Station%20and%20Target%20Damage%20Session%20-Introduction-

Description:

11:20 Target damage simulations (15 min) - Andriy Ushakov. 11:35 ... Neglect collimation. Target 450m downstream of undulator. Total photon beam power: 145 kW ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 22
Provided by: ipppD
Category:

less

Transcript and Presenter's Notes

Title: Target%20Station%20and%20Target%20Damage%20Session%20-Introduction-


1
Target Station and Target Damage
Session-Introduction-
  • I. Bailey
  • University of Liverpool /
  • Cockcroft Institute
  • RAL September 27th 2006

2
Session Outline
  • 1100 Introduction (20 min) - Ian Bailey
  • 1120 Target damage simulations (15 min) - Andriy
    Ushakov
  • 1135 Discussion (45 min) - All
  • 1220 Alternative target design status (5 min) -
    Ian Bailey
  • 1225 New results for crystallized W target from
    KEK (10 min) - Masao Kuriki
  • 1235 Discussion (10 min)- All

3
Undulator-Based Positron Source for ILC
  • The ILC requires of order 1014 positrons / s to
    meet its luminosity requirements.
  • A factor 60 greater than the conventional SLC
    positron source.
  • Undulator source should have lower stresses in
    the production target(s) and less activation of
    the target station(s) compared with a
    conventional source.
  • Collimating the circularly-polarised SR from the
    undulator leads to production of
    longitudinally-polarised positrons.

4
ILC Positron Source Layout
EUND - undulator TAPA - target station A TAPB -
target station B
Baseline layout of ILC with undulator at 150GeV
position in main linac.
Not to scale in any dimension!
5
Undulator Photon Beam (BCD)
  • Assume K1, 1cm period, 100m long undulator.
  • Assume nominal ILC e- bunch structure.
  • Neglect collimation.
  • Target 450m downstream of undulator.
  • Total photon beam power 145 kW
  • Average photon energy 13MeV
  • Beam spot rms 1.5 mm (0.75mm in BCD)

Simulations using SPECTRA
10MeV photons
6
Undulator Photon Beam (2)
Target designed for 300kW average photon beam
power.
? Proportional to undulator length
7
Target Project Overview
The University of Liverpool heads a
EUROTeV-funded task to carry out design studies
of the conversion target and photon collimator
for the polarised positron source.
Capture Optics
Positron beam pipe/ NC rf cavity
Target wheel
Photon beam pipe
Motor
Vacuum feedthrough
LLNL - draft design
  • Working in collaboration with SLAC and LLNL.
  • Developing water-cooled rotating wheel design.
  • 0.4 radiation length titanium alloy rim.
  • Radius approximately 1 m.
  • Rotates at approximately 1000 rpm.

8
Target Station Systems and Groups
  • LLNL
  • Target design
  • Computational studies
  • SLAC
  • Integration
  • Radiation studies
  • Liverpool / DL / RAL
  • Target design / prototyping
  • DESY
  • Target performance modelling
  • Cornell /BINP / KEK
  • Alternative target
  • ANL
  • Source modelling
  • Approx 400 m downstream of undulator
  • Key sub systems
  • Target wheel
  • Drive system
  • Cooling system
  • Vacuum system (10-8Torr)
  • Remote-handling system
  • Diagnostic and control systems
  • Target support systems
  • Photon collimator
  • Photon beam dump
  • Capture optics
  • NC rf cavity

9
Target Wheel Design
Numbers refer to LLNL study of earlier solid-disc
design.
  • Constraints
  • Wheel rim speed determined by thermal load and
    cooling rate
  • Wheel diameter determined by radiation damage and
  • Materials fixed by thermal and mechanical
    properties and pair-production cross-section

10
Power Deposition Cooling
Approximately 10 of photon beam power is
deposited in target wheel (30kW)
Water fed into wheel via rotating water union on
drive shaft.
11
Target Wheel Design
  • Recent drawings from DL design team
  • 5 spokes (following LLNL vibrational studies)
  • Thicker inner region to allow for stability,
    easier manufacture and balancing
  • Scaled to 1m diameter
  • LLNL may also extend driveshaft through vacuum
    chamber on both sides to allow separation of
    water union and drive system and prevent
    deflection of wheel in AMD field.

12
Radiation Effect Issues
  • Material Damage
  • Need further analysis to gain confidence in
    numbers from earlier work.
  • Currently investigating options for this work.
    Damage to nearby components (motors, seals, etc)
    needs to be checked.
  • Material Activation
  • Analysis needs to be done on this for handling
    issues as well. Planning to have this done by
    whoever does the damage assessment. Needs to
    include looking at cooling fluid (water, liquid
    nitrogen). Possibly will need to include
    filtration on nitrogen loop to remove carbon
    decay products (soot).

Provisional list from Tom Piggott, LLNL
13
Neutron Production
See Target Hall Design and Activation session
From TESLA study, expect 100mSv/h activation in
target region. EU exposure limit for radiation
workers is 20mSv/year
V. Bharadwaj - Positron Source Workshop,
Daresbury 2005
14
Mechanical Design Issues
  • Thermal Modeling
  • Complete modeling to check earlier results with
    varying beam parameters as well as varying wheel
    diameter and speed.
  • Structural Modeling
  • Complete structural modeling for various cases
    analyzed thermally. Continue with vibration
    analysis, check internal modes, probably change
    to an odd number of spokes to avoid possible
    problems.
  • Repetitive Loading
  • Check for effects of repetitive loading from
    beam, fatigue, creep, etc. Confer with
    metallurgist at LLNL.
  • Shaft Orientation/Deflection
  • Evaluate moving to shaft supported on both ends.
    Possible vacuum seal issues, but simplifies
    motor and water union mounting. Evaluate
    movement of wheel under load conditions. Some of
    this already done with vibration modeling.
  • Wheel Size
  • Evaluate thermal/structural/radiation damage
    limitations on wheel diameter. Also include
    looking at limitations imposed by other system
    components (capture optics, etc).
  • Target Station Handling
  • Evaluate remote handling possibilities. Also
    look at packaging of target station to allow easy
    removal, and possible motion of target to move
    beam to extend target life.
  • Vacuum Design
  • Requirements for vacuum in target station is
    determined by amount of differential pumping
    possible between the downstream accelerating
    cavity and the target station itself. Vacuum
    simulations /calculations required to determine
    achievable vacuums given outgassing from target
    seal leakage.
  • Cooling System Design
  • Layout and specification for target wheel
    cooling as well as AMD cooling system (and photon
    collimator?)
  • Piping/Electrical Layout
  • Instrumentation and controls
  • Layout and specification of needed
    instrumentation and controls.

Provisional list from Tom Piggott, LLNL
15
AMD Related Issues
Provisional list from Tom Piggott, LLNL
  • AMD Design
  • Further evaluation of pulsed/continuous design.
    Look in more detail at cooling and stress issues.
  • Magnet Loading on Wheel
  • Try to bring simulations and experimental data
    closer. Look at required motor power, additional
    heat input.

16
Integration Issues
Provisional list from Tom Piggott, LLNL
  • Integrated Simulations
  • Changes to undulator and collimator designs alter
    thermal load requirements of target. Effect of
    evolution in target / AMD design needs to be
    related to yield and polarization of finally
    captured positrons.

17
Eddy Current Simulations
See AMD Session
  • Initial Maxwell 3D simulations by W. Stein and
    D. Mayhall at LLNL indicate
  • 2MW eddy current power loss for 1m radius solid
    Ti disc in 6T field of AMD.
  • lt20kW power loss for current 1m radius Ti rim
    design.
  • However - Simulations do not yet agree with SLAC
    rotating disc experiment.
  • 8 diameter Cu disc rotating in field of
    permanent magnet.
  • Possibility of OPERA-3D simulations at RAL.

18
Other Issues
Provisional list from Tom Piggott, LLNL
  • Other Target Technologies
  • Stay aware of developments regarding alternative
    target materials, radiatively-cooled targets,
    liquid metal targets, etc.
  • Other Positron Source Technologies
  • Stay aware of developments regarding conventional
    and Compton scattering sources.

19
UK Plans
  • Prototyping to demonstrate
  • Stability of rotating target
  • Reliability of drive mechanism and vacuum seals.
  • Rotation of target in B field of capture optics.
  • Reliability of water-cooling system for required
    thermal load (average / peak?)
  • Engineering techniques for manufacture of
    water-cooling channels.
  • Liverpool, DL, and RAL plan to further develop
    the LLNL design and build prototypes of the
    target systems to determine the reliability.
  • Bid submitted to PPARC as part of LC-ABD.
  • Further EU funding? Coordination needed with
    other positron souce projects (CLIC) through
    ELAN, EUROTeV, etc.

20
UK Proposed Milestones
  • Goal 3. Construct and test a prototype to
    establish the mechanical stability of the target.
  • 3.1 Jul 07 - Infrastructure in place at Daresbury
    Laboratory.
  • 3.2 Aug 07 - Design of target test rig and
    instrumentation complete.
  • 3.3 Oct 07 - Construction of target test rig
    complete.
  • 3.4 Oct 07 -Construction of first prototype
    complete.
  • 3.5 Apr 08 -Testing of first prototype complete.
  • 3.6 Jun 08 - Data from first prototype analysed.
  • Goal 4. Construct and test a prototype to
    demonstrate operation of target in strong
    magnetic field.
  • 4.1 Nov 07 - Magnet design complete.
  • 4.2 Mar 08 - Magnet construction complete.
  • 4.3 Sep 08 - Construction of second prototype
    complete.
  • 4.4 Mar 09 - Testing of second prototype
    complete.
  • 4.5 May 09 - Data from second prototype analysed.
  • Goal 5. Construct and test a prototype to
    establish performance of the target cooling
    system.
  • 5.1 Feb 08 - Possible technologies for simulating
    thermal load identified.
  • 5.2 Jun 08 - Design of thermal load source and
    interface complete.
  • 5.3 Mar 09 - Installation of thermal load in test
    rig complete.
  • 5.4 Jun 09 - Construction of third prototype
    complete.
  • 5.5 Jan 10 - Testing of third prototype complete.

21
Discussion
  • Whats missing from the RD list?
  • Are all topics covered?
  • Is the proposed prototyping programme sufficient
    / necessary?
  • Do we have enough faith in radiation damage
    simulations to opt for smaller target wheel?
  • Scope for further collaboration / cooperation
  • Alternative targets discussed later in session
Write a Comment
User Comments (0)
About PowerShow.com