Title: Innovations in Erosion Protection
1Innovations in Erosion Protection
Norton Fitzwarren Dam
Murray Seaton
Date 23 January 2008
2Dam Description
- Earth flood alleviation dam 450 m long, 5m high
- Floods smaller than 100 year return period with
20 allowance for climate change pass through
culvert - Some flow from floods large than 100 year plus
20 event overtops crest - The whole crest and downstream shoulder acts as
spillway - Category A dam designed to pass the Probable
Maximum Flood (PMF) of 272 m3/s
3(No Transcript)
4Section through Downstream Shoulder
5Spillway Erosion Protection Armorflex
- Pre-cast concrete blocks. Polyester cables
passing through the blocks enable them to be
supplied as mats - Installed on a geotextile on the crest, top of
downstream shoulder and along the downstream toe
of the embankment - When topsoiled and grassed forms a reinforced
grass waterway. Erosion protection of blocks
enhanced by root anchorage and soil wedging
between blocks - Can withstand flow velocities up to 8 m/s
- Design guidance CIRIA Report 116 Design of
reinforced grass waterways - Approx material cost 12/m2
6Spillway Erosion Protection Armorflex
7Spillway Erosion Protection Armorflex
8Spillway Erosion Protection Stepped Blocks
- Pre-cast concrete blocks.
- Installed on a underlayer comprising granular
material and geotextiles. - The granular material provides an even foundation
for the blocks and, in combination with drainage
vents in the blocks and toe, helps prevent the
build up of pressure beneath the blocks. - The geotextile protects the subsoil from erosion
due to flow in the granular material and prevents
soil particles from the subsoil being washed out
by seepage.
9Spillway Erosion Protection Stepped Blocks
- Installed on the downstream shoulder where the
hydraulic jump forms - Design guidance CIRIA Special Publication 142
Design of stepped block spillways - Block sizes designed and blocks manufactured at
pre-casting plant - Approx material cost 70/m2. Installation
costs are also higher than for the Armorflex
system.
10Spillway Erosion Protection Stepped Blocks
11Spillway Erosion Protection Stepped Blocks
12Spillway Erosion Protection Stepped Blocks
13Stepped Blocks A Brief History
- Initially developed at the Moscow Institute of
Civil Engineering in the 1960s and 1970s - CIRIA study arose due to
- Interest in low-cost methods of upgrading the
capacity of spillways on existing dams - Limitations in the performance of plain, parallel
sided concrete blocks and other low cost erosion
protection systems - Stepped block spillway built at North West
Waters Brushes Clough Reservoir and checked
against the guidance in the CIRIA report
14Stepped Blocks Advantages
- Hydrodynamically stable because
- The upstream edge of the block is shielded from
the flow - The flow pattern causes a low-pressure zone
downstream of each step connected by drainage
vents to the underlayer and limits development of
seepage flow - The top surface of the block experiences a
downthrust - The stepped profile dissipates energy, reducing
velocity and consequently reducing the energy to
be dissipated in the tailwater at the toe
15Spillway Erosion Protection Stepped Blocks
16Stepped Blocks Advantages
- They can withstand high unit flow intensities
- They can be designed to withstand the forces
generated by hydraulic jumps - Flexibility of system allows differential
settlement
17Conclusion
- Stepped blocks are a useful erosion protection
option for spillways on erodible slopes, both for
new structures and existing structures requiring
increased flow capacity - The ability to design the stepped blocks to
withstand the forces generated by hydraulic jumps
makes them particularly useful