National Programme for Information Technology NPfIT - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

National Programme for Information Technology NPfIT

Description:

National Programme for Information Technology (NPfIT) WMS SHA Update for ... allocation method (capitation to SHA) means we will need to purchase more ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 14
Provided by: colinb8
Category:

less

Transcript and Presenter's Notes

Title: National Programme for Information Technology NPfIT


1
National Programme for Information Technology
(NPfIT)
  • WMS SHA Update for
  • Local Health Communities
  • April 2005

2
Agenda
  • DIP and Contractual update
  • Early PASs
  • P1R2
  • PACS
  • Choose and Book
  • SUS
  • Infrastructure
  • Communications
  • Programme Management

3
DIP and Contractual Update
  • DIP has been signed (v8.2)
  • Still a funding gap
  • Current WMS risk is c3m over contract life
  • Contractual only for early projects (inc. Worcs
    CMH)
  • Other 2005 projects indicative final dates to
    be agreed by end of May
  • Planning for 2006 (P1R2) in October/November
  • CSCA achieved Bundle Key Milestone (BKM) with
    caveats
  • CCN signed around CSC delays, Authority delays
    and extra functionality

4
WMSHA Early PASs
  • 3 WMS PASs planned to go live on Tactical
    Instances
  • Late delays with first two (Worcs
    Coventry/Community MH)
  • Common issues
  • availability of stable EUT environments
  • lack of process and clarity of fixes to
    showstopper bugs discovered in local testing
  • Three week delay (so far) has led to greater
    consequential delay because of level of
    uncertainty, but clarity is now emerging
  • UHCW suffers same issues, but later deployment so
    unclear about final effect

5
WMSHA Early PAS risks
  • Availability of tactical and strategic instances,
    migration approach SHA IT leads suggest
    employing a project manager
  • Logon times
  • Positive comments from early deployments
  • NPfIT commitment to redesign for P1R2
  • Spine dependence and reliability
  • Significant improvements few visible problems
    nationally
  • N3
  • Progress with early adopters recently following
    escalation
  • End User Training environments
  • Cluster have purchased 150 available by mid
    June
  • allocation method (capitation to SHA) means we
    will need to purchase more
  • Possibly 11 extra, possibly costing 550k (over 5
    years)

6
P1R2 and Clinical Systems
  • P1R2 delayed to December 05
  • Northern Clusters working group to look at NPfIT
    plan to de-risk clinicals by loosening coupling
    of spine and local NCRS
  • 2 announcements about GP systems
  • CSC/EMIS relationship
  • Any GP can have any GP system offered by any LSP
  • No clarity yet about the practical implications
    of either, nor about fit with GP Lorenzo

7
PACS
  • Pearse Butler (Cluster SRO) required assurances
    from SHAs
  • All trusts will implement PACS by March 2007
  • Capital funding will be available
  • Recurrent revenue will not be a barrier
  • Kevon Orford wrote to Trust/PCT CEOs
  • Assurance has been given by WMS
  • UHCW situation is a significant caveat
  • Talks continue with NPfIT
  • Proposals suggested for a way forward
  • Contingency to be developed (GE within NPfIT)
  • Trust to watch early adopters to end July
    possibly include St. Cross as an early adopter
  • Approach to be agreed by end April

8
Choose and Book
  • Dec 05 now one of top 3 national delivery targets
  • DH scrutinising SHA/LHC plans and visiting all
    SHAs
  • SHA concern that LHC rollout plans are not robust
  • SHA ABC taskforce visiting all PCTs
  • Directory of Service should be complete by end
    June
  • 30 GPs should be registered by end June
  • PCTs to have commissioning rules in place by end
    June
  • GP practice N3 rollout continues but later than
    planned

9
Secondary Uses Service
  • Rollout delayed, and timescale unclear now
    expect phased rollout from June
  • Training plan being developed nationally
  • Outstanding issues re effective information
    support for Payment by Results
  • Next User group meeting 6/5 (April cancelled)

10
Infrastructure
  • Registration Authorities progressing
  • All WMS organisations have nominated RA Managers
  • SHA team registering these staff now, and
    providing support
  • HR not universally keen
  • Worcestershire CEOs to nominate appropriate HR
    leads
  • Role based access control (RBAC) proving complex
    and time-consuming
  • workshop held
  • more NHS input sought
  • will improve (but not necessarily quickly)
  • Some problems with RA equipment supply
  • Need to manage to ensure PAS project GPs both
    done

11
Infrastructure
  • N3
  • Timely delivery of connections still unacceptable
  • However, BT nominally achieved target of 6000
    connections, but not all signed off by NHS.
  • Still significant outstanding issues re
  • Group connections (incorporating COINs and VPNs)
  • Support for PACS
  • Keith Boardman, with John Thornbury support,
    escalating issues with NPfIT/Cluster
  • Service Desks
  • Processes for interaction between Local/NPfIT/CSC
    service desks are being clarified
  • Some training (ITIL) available
  • Service Desk Managers forum set up to work
    through issues and share good practice

12
Communications
  • National work Porter Novelli
  • Information/campaign for NHS staff from June/July
  • Public campaign from Autumn linking to
    deployment projects

13
Programme Management Governance and Programme
Management Review
  • Reviews at Cluster, WMSHA all issued in draft,
    discussed at Boards
  • WMS workshop on implementation of recommendations
  • Will lead to increased standardisation and rigour
    in
  • Risk and issue management, escaltion
  • Change Management
  • Planning
  • Monitoring and Reporting
  • Decision making clarity of authority at each
    level
  • Detailed, resourced action plans to be debated at
    April SHA IT Programme Board
Write a Comment
User Comments (0)
About PowerShow.com