Town of Amherstburg Public Works Department - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Town of Amherstburg Public Works Department

Description:

Thomas Road Reopening 320,000.00. Fryer Street Reconstruction ... Bridge over River Canard. at Con. 2 North (No. 3008) 265,250.00 $ 304,400.00. 6 ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 16
Provided by: corrieg
Category:

less

Transcript and Presenter's Notes

Title: Town of Amherstburg Public Works Department


1
Town of AmherstburgPublic Works Department
  • 2008 Capital Budget

2
Miscellaneous Equipment
  • 80 kW Generator 75,000.00
  • Truck with Plow 120,000.00
  • Top dresser 18,000.00
  • Slit seeder 9,500.00
  • Tractor with Loader 35,000.00
  • 257,500.00

3
Roads Division Initiatives
  • Thomas Road Reopening 320,000.00
  • Fryer Street Reconstruction from Simcoe to
    Pickering 315,000.00
  • Murray Street Road and Sewer Reconstruction from
    Sandwich Street to Dalhousie Street 518,000.00
  • Dalhousie Street Reconstruction 500,000.00
  • 1,653,000.00

4
Roads Division Initiatives
  • Traffic Signal Upgrades 95,000.00
  • Street Lights on County Road 20(From County Road
    10 North Sideroad) 35,000.00
  • 130,000.00

5
Roads Division - Bridges
  • Bridge over Long Marsh Drain at Middle Sideroad
    (No. 2004) 39,150.00
  • Bridge over River Canard at Con. 2 North (No.
    3008) 265,250.00
  • 304,400.00

6
Parks Division Initiatives
  • Scodeller Park
  • Playground Equipment Site Work 33,000.00
  • Ranta Marina - Restore Brick Walkway 20,000.00
  • Ranta Park Shoreline Repairs
    Reshaping 25,000.00
  • Kingsbridge Park Playground and access
    works 100,000.00
  • Toddy Jones - Barrier Free playground
    equipment 75,000.00
  • 253,000.00

7
Sewer Separation Initiatives
  • Dalhousie Street Area - Sewer Separation Phase 3
  • Roads, storm and sanitary 720,000.00
  • Laird Avenue Area - Sewer Separation Phase 4
  • Roads, storm and sanitary 460,000.00
  • Wolfe and Murray Sewer Separation
  • Storm and sanitary 265,000.00
  • Fryer Street Trunk Sewer 150,000.00
  • Dalhousie Street Inflow Reduction 45,000.00
  • 1,640,000.00

8
Amherstburg Wastewater Treatment Plant
  • Wastewater Plant Design Equipment Selection
    for Expansion and Secondary Treatment
    7,357,000.00
  • (Construction Cost is 18,640,000 to be tendered
    in 2009)
  • Water / Wastewater Rate Review -
    Engineering 40,000.00
  • 7,397,000.00

9
Wastewater Lagoon Systems
  • McGregor Wastewater Lagoon System
  • Install effluent disinfection system as per
    existing Certificate of Approval requirements
    and pursuant to completion of EA 500,000.00
  • Cleaning of sediment from Lagoon Cell No.
    1 225,000.00
  • Edgewater Wastewater Lagoon System
  • Miscellaneous equipment and lagoon
    upgrades 48,000.00
  • 773,000.00

10
Water Initiatives
  • Annual Inspections and miscellaneous repairs
    145,000.00
  • Water Legislation compliance and requirements
    (DWQMS) 60,000.00
  • Water Conservation Implementation Program
    (2008) 96,000.00
  • 301,000.00

11
Water Initiatives
  • Water Meter Replacement Program 90,000.00
  • William Street and Walker Road System Looping
    145,000.00
  • Fryer Street Watermain Looping 80,000.00
  • Sandwich Street Watermain Replacement 785,000.00
  • Life Cycle Replacements - Replacement of aging
    water system components
  • Dalhousie Street watermain replacement 680,000.00
  • Main Street North watermain replacement
    41,000.00
  • Wolfe Street watermain replacement 88,000.00
  • Murray Street watermain replacement 26,000.00
  • 1,935,000.00

12
Amherstburg Water Treatment Plant
  • Backwash and carbon dust collection system
    upgrades 121,000.00
  • Sand blast and coat Clarifier 504,000.00
  • Clarifier Cover to protect open clarifier
    185,000.00
  • Miscellaneous upgrades to plant and
    equipment 173,000.00
  • 983,000.00

13
Water Tower and External Supply
  • New Water Tower Design Construction
    1,725,000.00
  • (Construction Cost is 1,500,000 to be tendered
    in 2008)
  • Water Master Plan and EA for New Water
    Tower 60,000.00
  • Water Distribution feed to Essex Study 45,000.00
  • 1,830,000.00

14
2008 Summary of Capital Projects
  • Miscellaneous Equipment 257,500.00
  • Roads Division 2,087,400.00
  • Parks Division 253,000.00
  • Wastewater Division 8,170,000.00
  • (including road and water components of
    reconstruction projects)
  • Water Division 5,049,000.00
  • Total 2008 Capital 15,816,900.00

15
Town of AmherstburgPublic Works Department
  • 2008 Capital Budget