Title: Case Studies and First National meeting
1Case Studies andFirst National meeting
- REACT
- Lisbon meeting 1-2 April 2004
2Installation of Wind turbines through the use of
fixed ten years PPAs and feed-in tariffs.
3Installation of Wind turbines through the use of
fixed ten years PPAs and feed-in tariffs.
- Law 2244/94 has set the rules for fixed ten years
Power Purchase Agreements between the Public
Power Corporation and the RES electricity
producers - The law has also set fixed feed-in tariffs for
RES electricity, defined as a percentage of the
consumer tariff (70 of the middle voltage
consumer tariff for the interconnected system and
90 in the non-interconnected islands). - It has helped considerably the increase in
installed capacity of wind turbines in
combination with an investment subsidy scheme
under the Operational Programme for Energy
(1996-2000) and the favourable wind conditions in
Greece.
4Installation of Wind turbines through the use of
fixed ten years PPAs and feed-in tariffs.
- The legislation changed in 1999 due to the
liberalisation of the electricity market. Law
2773/99 has set the rules for the liberalised
market and kept all the favourable conditions for
RES electricity (PPAs and feed in tariffs),
adding the advantage of priority dispatching - The increase of the installed capacity of wind
turbines from 26MW in 1995 to 420MW at the end of
2003 shows that the market has received a
significant boost, part of which is due to the
PPAs and feed-in tariffs applied.
5Installation of Wind turbines through the use of
fixed ten years PPAs and feed-in tariffs.
- Evaluation Main elements of success and
problems - The main success element of the combination of
PPAs and feed in tariffs was the establishment of
a stable investment environment.
6Installation of Wind turbines through the use of
fixed ten years PPAs and feed-in tariffs.
- Objectives for further development
- The main problem in the market is the delay in
the deployment of new projects due to the very
slow procedures for licensing of RES projects.
The target that is set by the Greek state is
1300MW installed capacity of wind turbines by
2010. - Conclusions
- The main lesson learned form the use of PPAs and
feed in tariffs in combination is the fact that
it is important to establish a long term stable
environment for investment in RES projects.
7Domestic Solar Water Heaters
- Greece has managed to reach the first place
in installed area of solar water heaters until
2001. An important role in this development was
played by the tax exception scheme for domestic
solar water heaters.
8Domestic Solar Water Heaters
- The scheme was introduced in the 1980s. The
way it worked was rather straight forward and
probably this simplicity has contributed to its
success - Results
- Volume growth in installed surface was from
1.7 million sq. meters in 1990 to 3 million
square meters of collectors in 2001. This means
that 25 of all Greek households own a hot water
solar system. The estimated energy production is
4.32 PJ of heat.
9Domestic Solar Water Heaters
- Evaluation Main elements of success and problems
- The main element of success in this promotion
scheme was its simplicity, combined with the
reliable technology and installation since there
werent any bad examples, and of course the large
solar potential. - An important side effect of the market
development was the emergence of a local network
of solar water heater manufacturers. At the
moment the local companies produce annually about
250000 m2 almost half of which is exported.
10Domestic Solar Water Heaters
- At the moment the market of domestic solar water
heaters in Greece is self sustainable, at least
until now. The measure of tax exemption was
abolished in 2003, and the effect of this will be
visible this year. It is expected however that
the effect will be negative. - Conclusions
- The tax exemption scheme corresponded to an
indirect subsidy of the initial investment for
solar water heaters. The simplicity of the scheme
was important for its success, as well as the
lack of negative stories due to equipment failure
or installation problems.
11Local tax on the wind electricity production
- After the initial development of a number of
wind turbine sites, some local reaction appeared
against the development of new sites. In order to
give motives to the local communities, law
2773/99 for the electricity market liberalisation
introduced the concept of a tax for the local
authorities in the areas where the wind parks
were installed
12Local tax on the wind electricity production
- The concept of the tax is rather clear. A total
of 2 of the annual revenue from electricity
sales will be given to the local authorities as a
compensation tax. Although this was not met
with a lot of enthusiasm by the investors, it
seems that it is a measure that has helped to
increase the acceptability of wind turbine
installations. - Evaluation Main elements of success and problems
- The main element for success is the participation
of local municipalities to the earnings that come
from wind energy installations.
13Local tax on the wind electricity production
- Conclusions
- It seems that the local opposition to wind
turbines installations could be reduced once the
local players have a direct benefit from the
installation.
14Operational Programme for Competitiveness
- The Operational Programme for Competitiveness
(2000-2006) is a direct subsidy scheme funded
through the European Structural Funds - The approach of the programme is to offer direct
financial incentives in order to improve the
competitiveness of the economy as a whole. For
the energy sector in particular the approach is
to offer an initial investment subsidy ranging
from 35 up to 50 depending on the technology
that is to be implemented. So a 50 subsidy is
offered for the installation of photovoltaic
while a 35 subsidy is offered for wind energy
plants and other RES technologies.
15Operational Programme for Competitiveness
- The first calls for energy project proposals were
launched in 2001 with a total budget of 0.51
billion of which 0.17 billion were EU Community
Support Framework grants. The programme received
310 proposals from the private sector for
renewables, cogeneration and energy efficiency.
The total investments that will be funded by the
programme will be 1 billion, with a subsidy of
0.35 billion.
16Operational Programme for Competitiveness
- Evaluation Main elements of success and problems
- The main element of success of the programme is
of course the direct subsidies that are offered,
which makes installations in high potential
regions very attractive. This is helped by the
existence of a stable investment environment in
RES electricity generation and results in the
majority of the projects being electricity
generation projects and not so many renewable
heat projects.
17Operational Programme for Competitiveness
- Conclusions
- The investment subsidies are obviously a very
attractive option for the investors, especially
when combine with high RES potential, but the
continuation of market development needs measures
that can secure the investment environment, like
the PPAs and feed-in tariffs that are applied at
the moment only for RES electricity.
18First National meeting
- Participants
- I. Stefanakis, N. Stavridis, Renewable Energy
Division, Public Power Corporation - M. Safos, Greenpeace
- G. Spyrou, Hellenic Association of RES
Electricity Producers - G. Mentzos, RES Section, Energy Division,
Ministry for Development
19First National meeting
- The presentations of the participants were
focused on the problems and - Main points
- Hellenic Association of RES Electricity Producers
- Non existing land planning, land-use, cadastre
this leads to time consuming and bearaucratic
procedures and uncertainty - Problems with the grid
- Reduction of initial investment subsidies
- Small hydro problems with the use of water for
irrigation
20First National meeting
- Main points
- Public Power Corporation
- RES is not among the immediate priorities of the
PPC. - PPC is responsible for the upgrade of the grid
and there is a lot of pressure on this direction.
- There is a contribution for RES that is included
in all the electricity bills and is collected by
the PPC and then forwarded to the Hellenic
Transmission System Operator.
21First National meeting
- Main points
- GREENPEACE
- Incentives should be enhanced instead of reduced
(i.e. solar water heaters VAT reduction etc) - Main focus on solar systems
- Geothermal energy should also be exploited and
promoted.
22First National meeting
- Main points
- Ministry for Development
- Problem electricity market liberalization is
really far behind. So the PPC is almost the only
actor. - Licenses time consuming procedures has lead
to a market for licenses!