Title: TC MTS


1
TC MTS41Sophia Antipolis, Oct 11-13 2005
STF276 Status
  • Anthony Wiles, STF Leader

2
Resources Used up to 30th September
  • Paid effort 386 days
  • 18 days remaining (total 38618404)
  • Which leaves 432-40428 days not assigned
  • 20 days will be allocated to Alexandre Berge (
    equal amount as voluntary effort)
  • 8 days will be assigned to final maintenance
  • Suggest that maximum amount of travel budget is
    converted to time ( 3 days)
  • Total unnassigned time 11 days
  • Voluntary expert effort 124 days
  • 21 days remaining
  • Total voluntary effort 145 days which is
    145-11034 days more than originally promised to
    the EC

3
Dissemination
  • Scott Moseley attended IPv6 Ready Technical
    meeting at UNH in US (draft travel report is on
    the server).
  • Planning/preparation of MTS/3GPP workshop to be
    held 11th October
  • Planning/preparation of STF276 participation in
    IPv6 Plugtest is well advanced (17-21 October)

4
Conformance Tests
  • Final draft TSSTP ready for approval (version
    1) according to EC schedule (14.10.2005)
  • Final total is 404 TPs
  • Interim draft ATS available for review according
    to EC schedule
  • 273 TPs identified as being testable. This final
    total is lower than the figure anticipated last
    month.
  • 273 Test Cases written (i.e., all TCs are now
    written)
  • Number of fully validated TCs 88
  • Number of partially validated TCs 106 (i.e.,
    executed but TTCN-3 corrections yet to be done)
  • Number of TCs yet to be validated 79

5
Conformance Tests To do
  • Only the validation will remain after end of
    October
  • Probably 79 test cases in total
  • This will be completed by Alexandre Berge,
    hopefully by the end of December
  • Final output of the STF
  • 404 TPs
  • 273 fully validated conformance test cases
  • Core TTCN-3 Library
  • Quality issues for the Steering group
  • TPs are not syntax checked
  • Why is TP summary field empty?
  • Have naming and documentation conventions been
    followed?

6
Interop Tests
  • All IOP TPs are written (approx 130)
  • Interim draft IOP TPs available for review
    according to EC schedule (actually this is the
    final draft of the TPs but no explicit TP
    deliverable required by the EC. The deliverable
    in February is combined TPsTDs)
  • So far 43 TDs have been written.
  • 17 TDs have been identified as untestable.
  • (Total left to write 130-43-1770)
  • Final figure will depend on whether there are
    more untestable TPs (likely)
  • Remaining TDs in progress
  • No IOP TDs validated (except those done in
    prototyping phase).

7
Interop Tests To do
  • XF will complete approx 35 of the remaining 70
    IOP TDs with his outstanding resource (5 paid
    10 days voluntary)
  • LV will complete the final 35 TDs before end of
    project
  • AB will do some IOP validation (depends on what
    time he has left after conformance validation)
  • Final Output of the STF
  • 130 IOP TPs
  • Approx 100 TDs
  • Quality issues for the Steering Group
  • Not much validation

8
Other Work
  • SCOP and Upper Tester complete
  • but not tested as we are still waiting on
    implementation of SCOP encoder in test tool
  • dependant on Testing Tech for that
  • Not critical but cannot validate all conformance
    tests without it
  • Only small number use the UT configuration

9
Open Issues
  • No technical issues
  • But we need assistance with dissemination
  • quotes from stakeholders
  • press releases
  • other possibilities?