RSS Construction in Bosnia-Herzegovina - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

RSS Construction in Bosnia-Herzegovina

Description:

In December 1995 the Dayton Peace Accord signed and shortly ... Hesco-Bastion Retaining Wall. Concrete Gravity Retaining Wall. Timber Crib Retaining Wall ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 31
Provided by: Vdot7
Category:

less

Transcript and Presenter's Notes

Title: RSS Construction in Bosnia-Herzegovina


1
RSS Construction in Bosnia-Herzegovina
David A. Kaulfers, P.E. Assistant State Materials
Engineer Virginia Department of Transportation
2
Where is Bosnia
3
Where is Bosnia???
4
West Virginia????
5
US Sector
6
Why are we in Bosnia?
  • In December 1995 the Dayton Peace Accord signed
    and shortly thereafter the US crossed the Sava
    and was supposed to be out in one year
  • To provide stability in an area of the world that
    historically has been contentious
  • The mission is not yet complete

7
Why am I talking about Bosnia?
  • In November 2000, my Army Reserve Unit was
    involuntarily activated for peacekeeping duties
    in Bosnia from March to September
  • My job was the Construction Management Officer
    for all Soldier Construction Projects

8
Army Engineer Team
  • HQ Staff 3ID Engineers from Ft Stewart
  • Engineer Company C/448th ENG GaARNG
  • Earthmoving Platoon 92 Engineer Bn from Ft.
    Stewart
  • Construction Management 416th Engineer Command,
    USAR

9
Army Engineers Job
Maintain Freedom of Movement for Stabilization
Forces in the US Sector
10
My Job
Construction Management Officer Perform
Reconnaissance, Scope Out, Design, Plan, Procure
Construction Materials and Provide Construction
Oversight for all Soldier Constructed Projects
in the US Sector
11
Route Georgia Landslide
12
Corrective Considerations
  • Hesco-Bastion Retaining Wall
  • Concrete Gravity Retaining Wall
  • Timber Crib Retaining Wall
  • Reinforced Soil Slope

NO BORINGS!!!!
13
Design Approach
  • KEEP IT SIMPLE
  • Used RSS for Design and estimated conservative
    soil properties
  • Specified materials that were easy to work with
    and obtain
  • Use Power Point for Design

14
Route Georgia Slope Correction Limits of Repair
100
Reflector
Reflector
Culvert
4.0 m
110
Limits of Repair
14
Approximate Limits of Failure
120
130
140
46
150
15
Route Georgia Slope CorrectionLimits of
Excavation Not to Scale
Theoretical Slope Break
3.2m
Existing Ground Surface
3.2m
1.0 Vertical
Limits of Excavation
0.5 Horizontal
4.8 m
1.0 Vertical
1.0 Horizontal
16
Route Georgia Slope CorrectionReinforcement
Not to Scale
Theoretical Slope Break
3.2m
0.15m
0.30m
Existing Ground Surface
3.2m
1.0 Vertical
0.5 Horizontal
0.05m
4.8 m
NOTES Geotextile Fabric Amoco 6086 (US
Equivalent 2044) Spacing is 0.30m, 11 total
Layers Backfill Material, 30-60mm Aggregate, cap
w/ 0-30 Seams have min overlap of 0.2m and
perpendicular to face of slope
1.0 Vertical
1.0 Horizontal
17
Route Georgia Slope CorrectionFace Formwork
Welded Wire FabricWWF, Not To Scale
0.42 m
0.30 m
45 degrees
1.70 m
1.0 Vertical
Notes Face formwork consists of welded wire
fabric, 6m long by 2.15m wide, folded along the
long axis at a 45 degree angle.
1.0 Horizontal
18
Route Georgia Slope CorrectionGeotextile Facing
DetailNot To Scale
1.0m overlap
0.42 m
0.30 m
4.8m to 3.2m, depending on elevation
1.0 Vertical
Notes Place geotextile and drape at least 1.5m
extra Over WWF formwork. Place aggregate up
against Fabric/formwork. Once aggregate is
placed, drape Geotextile back over for at least
1.0m overlap
1.0 Horizontal
19
Route Georgia Slope CorrectionScope of Work
  • Remove Existing Guard rail and save
  • Paint on ground limits of excavation
  • Excavate out failed material and beyond
  • Place geotextile in 0.3m layers between 30-60mm
    Aggregate
  • Cap slope with 0-30mm Aggregate
  • Replace Guard rail
  • Excavate drainage ditch above slope to divert
    future runoff

20
Route Georgia Slope CorrectionSpecifications
  • Material shall be removed as shown on limits of
    excavation
  • The Geotextile shall be placed, pulled tight and
    formed against the welded wire fabric
  • No equipment shall be on the geotextile
  • Aggregate shall be back dumped onto the fabric
  • The aggregate shall be compacted with the D4
    dozer
  • All dimensions and slope angles must be
    maintained within 10

21
Construction Planning
22
ConstructionSlope Excavation
23
ConstructionSlope Excavation
24
ConstructionPlacing Geotextile WWF
25
ConstructionPlacing Geotextile WWF
26
ConstructionCompaction Equipment
27
Finished ProductSlope Face
28
Finished ProductRoad
29
Project Facts
  • Materials Cost, 8,000
  • 220 cubic meters of Aggregate
  • 4700 square meters of Geotextile
  • 2600 Man-Hours
  • 13 Days
  • Teamwork Success

30
Lessons Learned
  • Keep it simple
  • Communicate
  • Show evidence of Prior Success
  • Rehearse prior to construction
Write a Comment
User Comments (0)
About PowerShow.com