Title: RSS Construction in Bosnia-Herzegovina
1RSS Construction in Bosnia-Herzegovina
David A. Kaulfers, P.E. Assistant State Materials
Engineer Virginia Department of Transportation
2Where is Bosnia
3Where is Bosnia???
4West Virginia????
5US Sector
6Why are we in Bosnia?
- In December 1995 the Dayton Peace Accord signed
and shortly thereafter the US crossed the Sava
and was supposed to be out in one year - To provide stability in an area of the world that
historically has been contentious - The mission is not yet complete
7Why am I talking about Bosnia?
- In November 2000, my Army Reserve Unit was
involuntarily activated for peacekeeping duties
in Bosnia from March to September - My job was the Construction Management Officer
for all Soldier Construction Projects
8Army Engineer Team
- HQ Staff 3ID Engineers from Ft Stewart
- Engineer Company C/448th ENG GaARNG
- Earthmoving Platoon 92 Engineer Bn from Ft.
Stewart - Construction Management 416th Engineer Command,
USAR
9Army Engineers Job
Maintain Freedom of Movement for Stabilization
Forces in the US Sector
10My Job
Construction Management Officer Perform
Reconnaissance, Scope Out, Design, Plan, Procure
Construction Materials and Provide Construction
Oversight for all Soldier Constructed Projects
in the US Sector
11Route Georgia Landslide
12Corrective Considerations
- Hesco-Bastion Retaining Wall
- Concrete Gravity Retaining Wall
- Timber Crib Retaining Wall
- Reinforced Soil Slope
NO BORINGS!!!!
13Design Approach
- KEEP IT SIMPLE
- Used RSS for Design and estimated conservative
soil properties - Specified materials that were easy to work with
and obtain - Use Power Point for Design
14Route Georgia Slope Correction Limits of Repair
100
Reflector
Reflector
Culvert
4.0 m
110
Limits of Repair
14
Approximate Limits of Failure
120
130
140
46
150
15Route Georgia Slope CorrectionLimits of
Excavation Not to Scale
Theoretical Slope Break
3.2m
Existing Ground Surface
3.2m
1.0 Vertical
Limits of Excavation
0.5 Horizontal
4.8 m
1.0 Vertical
1.0 Horizontal
16Route Georgia Slope CorrectionReinforcement
Not to Scale
Theoretical Slope Break
3.2m
0.15m
0.30m
Existing Ground Surface
3.2m
1.0 Vertical
0.5 Horizontal
0.05m
4.8 m
NOTES Geotextile Fabric Amoco 6086 (US
Equivalent 2044) Spacing is 0.30m, 11 total
Layers Backfill Material, 30-60mm Aggregate, cap
w/ 0-30 Seams have min overlap of 0.2m and
perpendicular to face of slope
1.0 Vertical
1.0 Horizontal
17Route Georgia Slope CorrectionFace Formwork
Welded Wire FabricWWF, Not To Scale
0.42 m
0.30 m
45 degrees
1.70 m
1.0 Vertical
Notes Face formwork consists of welded wire
fabric, 6m long by 2.15m wide, folded along the
long axis at a 45 degree angle.
1.0 Horizontal
18Route Georgia Slope CorrectionGeotextile Facing
DetailNot To Scale
1.0m overlap
0.42 m
0.30 m
4.8m to 3.2m, depending on elevation
1.0 Vertical
Notes Place geotextile and drape at least 1.5m
extra Over WWF formwork. Place aggregate up
against Fabric/formwork. Once aggregate is
placed, drape Geotextile back over for at least
1.0m overlap
1.0 Horizontal
19Route Georgia Slope CorrectionScope of Work
- Remove Existing Guard rail and save
- Paint on ground limits of excavation
- Excavate out failed material and beyond
- Place geotextile in 0.3m layers between 30-60mm
Aggregate
- Cap slope with 0-30mm Aggregate
- Replace Guard rail
- Excavate drainage ditch above slope to divert
future runoff
20Route Georgia Slope CorrectionSpecifications
- Material shall be removed as shown on limits of
excavation - The Geotextile shall be placed, pulled tight and
formed against the welded wire fabric - No equipment shall be on the geotextile
- Aggregate shall be back dumped onto the fabric
- The aggregate shall be compacted with the D4
dozer - All dimensions and slope angles must be
maintained within 10
21Construction Planning
22ConstructionSlope Excavation
23ConstructionSlope Excavation
24ConstructionPlacing Geotextile WWF
25ConstructionPlacing Geotextile WWF
26ConstructionCompaction Equipment
27Finished ProductSlope Face
28Finished ProductRoad
29Project Facts
- Materials Cost, 8,000
- 220 cubic meters of Aggregate
- 4700 square meters of Geotextile
- 2600 Man-Hours
- 13 Days
- Teamwork Success
30Lessons Learned
- Keep it simple
- Communicate
- Show evidence of Prior Success
- Rehearse prior to construction