Prime Focus Imaging Spectrograph Status - PowerPoint PPT Presentation

About This Presentation
Title:

Prime Focus Imaging Spectrograph Status

Description:

Updated pupil placement and fold mirror position for maximum NIR ... 'aplanatic' configuration. reduced MAD on asphere. focus singlet triplet. Oct 10, 2002 ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 38
Provided by: KennethN6
Learn more at: http://www.sal.wisc.edu
Category:

less

Transcript and Presenter's Notes

Title: Prime Focus Imaging Spectrograph Status


1
Prime Focus Imaging SpectrographStatus
  • Engineering Status
  • Optics
  • Mechanical
  • Control System
  • Management
  • Budget
  • Schedule

2
Optics
  • Design Updates
  • Slit Throughput
  • VPH Grating Complement
  • Optomechanical
  • Concerns
  • Procurement plan

3
Optics Design
  • Updated camera and collimator to final indices
  • 20 image quality degradation
  • decrease manufacturing margin?
  • relieve spec?
  • Completed thermal design. Focus in camera
  • Updated pupil placement and fold mirror position
    for maximum NIR collimated beam
  • Fused silica -gt fused quartz in common collimator
    beam (for NIR)
  • Camera configuration update

Details
Details
Details
4
Slit Throughput
  • PDR max resolution 6250 overstated. Used
    median seeing 0.9 arcsec, not telescope image
  • Model using seeing degraded to 37 deg ZD, actual
    SAC, actual PFIS model
  • In median seeing, a 1.25 arcsec slit will give
    70 throughput
  • Resolution at a given grating angle reduced to
    70.
  • Found can increase maximum articulation of camera
    to 100 deg, increases max resolution 20 R
    5500 at 50 deg tilt, 1.25 arcsec slit

5
Spectral Resolution vs. Throughput
6
VPH Grating Complement
  • VPH procurement in next 6 months, tradeoff
    required UV efficiency vs high resolution
    efficiency
  • Suggest efficiency in UV for highest and lowest
    density gratings efficiency at high resolution
    for other three
  • Note that SALT can easily add VPH gratings-
    magazine designed for swapout

7
VPH tradeoff
8
Optomechanical
  • Largest PDR risk optics, especially
    optomechanical, underbudgeted
  • Award subcontract for optomechanical to J. Alan
    Schier
  • optomechanics for Keck ESI, DEIMOS
  • comfortable with fluid coupling, salt, solgel
  • Tasks
  • mounting tolerancing
  • design, fabricate lens holders
  • assemble lens groups

9
Current concerns
  • Coating strategy
  • baseline solgel on interior surfaces hard
    elsewhere
  • cost poorly defined
  • Stress birefringence in collimator potentially
    degrading polarimetric efficiency
  • blanks NaCl possible problem lack of data
  • 4 CaF2 blank costs may be increased
  • investigating VPH and etalon effects

Details
10
Optics procurement
  • before CDR
  • third etalon (before years end to get good
    price)
  • fold flat/ coating
  • camera/ collimator blanks
  • grating blanks
  • just after CDR
  • camera/ collimator figuring
  • waveplates, beamsplitter
  • VPH gratings

11
Structure/ Mechanisms
  • Structure
  • guide mount interface designed
  • collimator assembly
  • Mechanisms designed
  • waveplate
  • slitmask
  • grating. 6 grating complement
  • camera articulation.
  • Will do full articulation in lt 20 sec (enable
    PFIS imaging mode as slitmask setup)
  • Articulate to 100 deg

Details
12
Control System
  • Hardware
  • generic mechanism test bed operational use for
    LabView learning curve, answering operational
    questions for mechanism designs
  • wiring architecture box placement cable harness
  • Software
  • actually operating hardware
  • prototype client / server, scripting developed
  • consistent with telescope architecture

Details
13
Management
  • Budget re-projection
  • Schedule

14
Cost-to-Completion Deltas
  • Base Dollars

15
Chief Deltas
  • Q1-2 (94K)
  • CDR electrical engineering underestimate 15K
  • SAAO Cryotiger, etc 25K
  • US slowed inflation 50K
  • Q2-2 (139K)
  • Drafting subcontract underestimate 97K - 50K -
    20K 27K. Control mech design schedule risk.
  • Optomechanical subcontract 220K - 50K - 20K
    150K. Control optics technical/ schedule risk
    biggest PDR budget deficiency

16
Prognosis
  • Contingency use (58) somewhat above expected
    (50) at this point, but still on track.
    Remaining deltas will be much better known at
    CDR
  • Capital purchases. Preliminary RFQs on largest
  • likely increases CaF2 blanks coatings
  • likely savings mechanisms/controls lens
    fabrication slitmask mill
  • Schedule. Remaining contingency would cover 8
    months slip.
  • When do we start spending contingency? At current
    rate, Q1 04 at rate which would spend cap, Q4
    03 (well after CDR)

17
Schedule
  • Milestone CDR 17 Mar, 2002
  • slipped 2 months from PDR mechanical design
    critical path
  • recover drafting/ engineering subcontract help
  • Optical
  • optomechanical subcontract kickoff
  • procure blanks, issue pre-CDR RFQs
  • Mechanical 4 most complex mechanisms completed
  • Control System in progress
  • hardware wiring diagram
  • Labview design well under way
  • Detail fabrication/ testing schedule in work this
    month

Details
18
Done!
19
Optics Details
20
NIR Beam
21
Optics Configuration
22
Camera
  • triplet modification
  • CaF2 -gt silica
  • aplanatic configuration
  • reduced MAD on asphere
  • focus singlet triplet

23
Birefringence Budget
  • Unusual SALT configuration puts large glass path
    (17 cm!) between waveplate and beamsplitter
  • Stress birefringence at 45 to polarimetric axis
    causes depolarization d (p w)2 (w biref in
    waves). d lt 2 gt w lt 1/20 wave, biref/cm lt
    2-10nm/cm
  • Have birefringence budget for
  • Fused silica, quartz 1 -5 nm/cm
  • CaF2 1-2 available at extra cost
  • NaCl unknown. sample now being measured
  • Folding flat LLNL coating
  • VPH grating
  • Etalon

24
Mechanical Details
25
Completed Designs
gratings
slitmask
collimator assembly
camera articulation
waveplates
26
Camera Articulation
camera tube
gearbox/ motor
pinion
pneumatic detent, 0.5 deg spacing
bearing
27
Camera Support
28
Grating Mechanism
pneumatic insertor
linear stage selector
6 gratings
grating rotator
29
Collimator Assembly
main collimator group
slitmask magazine
guider feet
waveplates
30
Waveplate Mechanism
halfwave plate
quarterwave plate
blank
31
Slitmask Mechanism - 1
linear stage selector
magazine
pneumatic insertor
mask in position
32
Slitmask Mechanism - 2
pneumatic extractor
33
Control System Details
34
Generic Mechanism
  • Test Hardware
  • candidate motor, encoders, hall sensors,
    pneumatic
  • motor drivers
  • signal conditioner
  • PXI motor card, I/O card

35
LabView
  • Hierarchical VIs
  • Commandable from scripts

36
Management Details
37
Detail CDR Schedule