Protocol for Environmental Management Mining and Extractive Industries - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

Protocol for Environmental Management Mining and Extractive Industries

Description:

Heavy metals (eg, lead antimony) PAHs. Radioactive isotopes. Assessment criteria. Annual average ... Class 3 indicators hydrogen cyanide, arsenic, antimony) ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 38
Provided by: lynde3
Category:

less

Transcript and Presenter's Notes

Title: Protocol for Environmental Management Mining and Extractive Industries


1
Protocol for Environmental Management (Mining and
Extractive Industries)
2
PEM Mining and Extractive Industries
  • Incorporated document to SEPP (AQM)
  • Gazetted February 2008
  • Is a statutory document same power as SEPP
  • Industry must still comply with requirements of
    SEPP
  • PEM just provides further interpretation and
    guidance
  • Establishes a procedure for conducting an air
    quality assessment as part of an EES process, EPA
    Works Approval Application, Planning Permit
    Application or DPI Work Authority application

3
SEPP (AQM)
  • Sets out the statutory framework for managing
    emissions to the air environment
  • Emissions are managed in such a way to ensure
    that
  • Air quality objectives in SEPP (AAQ) are met
  • Continuous improvement in Victorias air quality
    occurs
  • All indicators in SEPP (AQM) must be managed by
    application of best practice
  • Class 3 indicators by application of controls to
    maximum extent achievable (MEA)

4
Best Practice and MEA
  • In determining what constitutes best practice and
    MEA consideration must be given to the wastes
    hierarchy
  • Avoidance
  • Reuse
  • Recycling
  • Recovery of energy
  • Treatment
  • Containment
  • disposal

5
Best practice and MEA
  • Best Practice - Best combination of eco-efficient
    techniques, methods, processes or technology used
    in an industry sector or activity that
    demonstrably minimises the environmental impact
    of a generator of emissions in that industry
    sector or activity
  • MEA - A degree of reduction in the emission of
    wastes from a particular source that uses the
    most effective, practicable means to minimise the
    risk to human health from those emissions and is
    at least equivalent to or greater than that which
    can be achieved through application of best
    practice

6
Best Practice and MEA
  • Best practice
  • Industry wide
  • Determined for industries of similar size,
    location and operations
  • MEA
  • Goes beyond best practice to take into
    consideration what site-specific action can be
    taken
  • This may include for example
  • Ceasing operation for several hours under certain
    met conditions
  • Increased water sprays or use of chemical dust
    suppressants
  • Use of blast mats

7
How to determine best practice or MEA?
  • Most recent documented definition for the
    industry sector from national and international
    sources
  • Most recent documented definition for the
    industry sector in Victoria (if any)
  • Performance standards or benchmarks for the
    industry in terms of management of emissions,
    wastes, energy and resources and their impacts
  • Any constraints that may apply to each situation
    (eg., availability, affordability or
    practicability)
  • Comparison of different approaches currently used
    in the industry

8
Assessment requirements
  • Risk based
  • Dependent on scale or size of operation
  • Location of the site
  • Irrespective of the level of assessment emissions
    must be controlled by application of best
    practice or MEA
  • Level 1 most rigorous applies when
    developments are close to residential areas or in
    urban areas and have the potential to give rise
    to significant off-site impacts

9
Assessment requirements
  • Level 2 required when development is in rural
    area with residences in close proximity or where
    a small operation is located in an urban area.
  • Level 3 required when development is in a rural
    location with no residences in close proximity
  • For mines and quarries with less that 50,000
    tonnes per year extraction, no modelling is
    required
  • Best practice (relevant to the site) applied to
    control of emissions on site

10
Extraction
  • For quarries the amount of soil and rock that is
    moved or extracted per year
  • For above ground mines the amount of soil, rock
    or ore moved on site
  • For underground mines that amount of soil, rock
    and ore moved above ground and brought to the
    surface of the mine. Any emissions from
    ventilation shafts of the mine must also be taken
    into account in the estimates of emissions where
    the shaft is part of the premises.

11
Criteria for Assessment
12
Indicators to be assessed
  • PM10
  • PM2.5
  • Respirable crystalline silica
  • Asbestos
  • Arsenic
  • Hydrogen Cyanide
  • Heavy metals (eg, lead antimony)
  • PAHs
  • Radioactive isotopes

13
Assessment criteria
14
Assessment criteria
  • Prior to Assessment
  • Level 1 real-time continuous monitoring 24-hour
    average PM10 and PM2.5 for a 12 month period,
    analysis of RCS, deposited dust and heavy metals
  • Level 2 - continuous monitoring 24-hour average
    PM10 and PM2.5 for a 12 month period, analysis of
    RCS, deposited dust and heavy metals
  • Level 3 no monitoring required prior to
    assessment
  • EPA has data for Melbourne, Geelong, Wangaratta,
    Latrobe Valley, Bendigo, Ballarat, Mildura,
    Shepparton, Warrnambool that is available on
    request.

15
Modelling
  • Modelling conducted for new or modified sources
  • Modelling is conducted on emissions after the
    application of best practice and MEA
  • Residual emissions
  • Must use a regulatory model (currently Ausplume)
  • If a proponent wants to use an alternative model,
    a modelling proposal must be approved by the
    Authority
  • Follow the modelling requirements set out in
    Schedule C of the SEPP-AQM

16
Modelling
  • Ambient Background Concentrations Site
    Specific, Site Representative, Generic airshed
    values (70thiles) None
  • Meteorological data - Site Specific and Site
    Representative
  • Emissions Input Data Site specific factors or
    literature based factors (NPI or AP42)
  • Regulatory Model AUSPLUME
  • PM10 and PM2.5 must be modelled as a gas

17
Background data
  • Level 1 Real time continuous 24-hour PM10 and
    PM2.5 for a 12-month period, analysis of
    crystalline silica (PM2.5 fraction), deposited
    dust and heavy metal content (PM10) (where
    applicable)
  • Level 2 - Continuous 24-hour PM10 and PM2.5 for
    a 12-month period, analysis of crystalline silica
    (PM2.5 fraction), deposited dust and heavy metal
    content (PM10) (where applicable)
  • Level 3 No monitoring data required

18
Modelling
  • Modelling is undertaken over a twelve month
    period
  • Should be undertaken for both construction and
    operational phases of the development
  • The simulation(s) are for worst case emissions
    under normal operating conditions
  • For example maximum earth moving activities,
    activities close to sensitive receptors
  • Include background concentrations (address where
    datasets are biased by events)

19
Sensitive Locations
  • Sensitive locations include
  • residences,
  • schools,
  • kindergartens,
  • aged care facilities,
  • hospitals,
  • childcare centres and
  • recreational areas.
  • In assessing recreational areas the potential for
    exposure needs to be taken into account through a
    qualitative risk assessment process eg., whether
    activities are occurring on site when people are
    using the recreational area.

20
Presentation of modelling results
  • Time series plots at sensitive receptors,
    including total, mining/extractive contribution
    background presented separately

21
Presentation of modelling results
  • Contour Plots showing maximum concentrations from
    industry only, including residential areas and
    sensitive receptors

22
Level 1 modelling
  • 24-hour PM10 and PM2.5 predictions for a
    12-month period, including daily time varying
    background files
  • Crystalline silica,arsenic and other indicators
    with long term health effects must include annual
    average background concentrations
  • Nitrogen dioxide and carbon monoxide include
    70thile concentrations (single upper average
    value)
  • For other indicators considered, justification
    must be provided for not using a background
    concentration

23
Level 2 Modelling
  • 24-hour PM10 and PM2.5 predictions for a
    12-month period, including daily time varying
    background files (EPA). A screening assessment
    may be applied using 70thiles
  • Crystalline silica,arsenic and other indicators
    with long term health effects must include annual
    average background concentrations
  • Nitrogen dioxide and carbon monoxide do not need
    to be considered
  • For other indicators considered, justification
    must be provided for not using a background
    concentration

24
Level 3 Modelling
  • PM10, PM2.5, and RCS
  • No background data is required for modelling
    purposes

25
Risk management strategies
  • When modelling predicts that assessment criteria
    may be exceeded
  • Identify conditions (meteorological and
    operational) that lead to elevated levels
  • Identify options for reducing exposure
  • Identify further operational controls (i.e.
    stopping operation when winds from a direction
    are above a certain level)
  • Relocating residents for periods when operations
    are expected to produce high levels of emissions
  • Implement monitoring as part of a reactive
    management strategy
  • Conduct a Health Risk Assessment - where all
    options are exhausted

26
Health Risk Assessment
  • In situations where the assessment criteria are
    exceeded and additional management strategies are
    not an option or are not economically viable, a
    health risk assessment can be conducted and
    submitted as part of the assessment.
  • It is expected that a detailed quantitative
    health risk assessment will only be required in
    rare circumstances.
  • A quantitative risk assessment should only be
    undertaken when all options for reducing
    emissions by changes in site management practices
    have been exhausted or are not economically
    viable. It should not be the first option taken.

27
Health Risk Assessment
  • In conducting the health risk assessment the
    following steps must be followed
  • Review of the current information regarding the
    health effects associated with exposure to the
    indicator
  • Collection of information on the local population
    including identification of susceptible groups
    within the affected population (eg percentage of
    children with asthma or people aged over 65
    years)
  • Potential for exposure of the local population to
    levels of the indicators (obtained from air
    quality modelling) and,
  • Calculation of the risk posed by this exposure

28
Monitoring for approved developments
  • Confirmation monitoring for limited time period
    (eg 12 months)
  • Level 1 Real time continuous PM10 and PM2.5
    monitoring, nuisance dust monitoring at sensitive
    receptors and crystalline silica and metal
    monitoring (conducted using low-volume samplers
    for a period of 1 week per month)
  • Level 2 1 in 6 day 24-hour PM10 and PM2..5
    monitoring, nuisance dust monitoring at sensitive
    receptors and limited crystalline silica and
    metal monitoring (conducted using low-volume
    samplers for a period of 1 week per month)
  • Level 3 Nuisance dust monitoring at sensitive
    receptors
  • Nuisance dust monitoring to be assessed using DPI
    criteria of 4 g/m2/month on a monthly basis (not
    an annual average) no more than 2 g/m2/month
    above background.

29
Monitoring for Reactive Management
  • For Level 1 and 2 facilities as part of site EMP
  • A real-time tool to react to short term particle
    peaks which may impact on the overall daily
    concentration
  • EPA can assist with short term trigger levels and
    advise on appropriate instrumentation
  • Typically sited at the sensitive receptor that is
    predicted to be worst affected or boundary
    closest to that location
  • Instrumentation not the same as that required for
    compliance monitoring
  • Range of equipment available that is relatively
    inexpensive and portable that would be suitable

30
CASANZ Issues
  • If ambient background levels exceed the
    assessment criteria can different criteria be
    established? This is particularly relevant for
    fine particles and silica (especially for dust
    storms,strong wind periods, bushfires, fuel
    reduction burns, etc)?
  • The assessment criteria are based on the
    protection of health. Alternative criteria cannot
    be used. However, in the presentation of results
    the background data needs to be presented
    separately to the modelled predictions from the
    mine or quarry so that existing air quality can
    be clearly identified.

31
CASANZ Issues
  • Is the Table 2 averaging period for RCS also to
    be interpreted as a Policy (AQM) intervention
    level (as for PM10 and PM2.5?) Can it be used as
    a modelling design criterion? This question also
    applicable for other Class 3 indicators
    hydrogen cyanide, arsenic, antimony).
  • The assessment criteria in the PEM should not be
    considered as intervention levels. The assessment
    criteria apply for mining and extractive
    industries only when assessed in accordance with
    the procedures set out in the PEM. They are used
    for both design purposes and monitoring
    assessments.

32
CASANZ issues
  • Background levels (PM10, PM2.5 RCS, and deposited
    dust) are required for the air quality assessment
    if there is no site-specific data available. The
    Draft PEM Level 1 and 2 assessments require 1
    year of data be obtained prior to the preparation
    of the assessment. Given the significant costs
    and time to accumulate this data, is a shorter
    period of 4 to 6 months sufficient provided that
    the sampling is across the drier seasons?
  • The purpose of collecting this data is to ensure
    that background data is available for the
    modelling. For Level 1 assessments daily varying
    background data is required for the model so data
    must be collected daily for a 12 month period.
  • EPA has datasets available and the proponent
    should check with EPA on the availability and
    suitability of existing data.
  • Note collecting background data only during dry
    windy months may not pick up other existing
    sources such as combustion sources (eg planned
    burning and wood heater emissions that contribute
    to existing air quality)

33
CASANZ issues
  • Will a preferred dispersion model be specified
    for large area intermittent source modelling
    associated with mining e.g. for excavation,
    blasting, and haulage activities? For example
    AUSPLUME, CALPUFF or TAPM?
  • The current regulatory model is AUSPLUME, if the
    proponent wishes to use a non-regulatory model
    they have to provide a modelling proposal that is
    acceptable by the Authority.

34
CASANZ issues
  • Will a prescribed methodology for undertaking
    health risk assessment (if required) be
    recommended in the PEM Mining and Extractive
    Industry?
  • Further guidance has been provided in the PEM but
    it is not prescriptive. A PEM for Risk Assessment
    is currently being developed that will provide
    detailed guidance to what EPA requires in a risk
    assessment to demonstrate compliance with SEPP
    (AQM). In the interim contact EPA for further
    guidance.

35
CASANZ issues
  • Will a preferred hierarchy of dust monitoring
    methods be included for the 3 proposed PEM
    controlled levels? The preferred monitoring
    method should also propose optional monitoring
    frequency with references to a standard
    (Australian Standard or International).
  • No, if confirmation monitoring is required it has
    to be undertaken by at least one co-located
    reference method (AS , USEPA).
  • Reactive management monitoring is undertaken
    using a continuous method (does not have to be a
    reference or equivalence method) as it is a
    trigger for review of site management if particle
    levels are increasing. It provides a reactive
    management approach to avoid a problem in real
    time.

36
CASANZ issues
  • If the monitoring method chosen is not preferred
    highest then it should be specified what
    cross-correlation is required. For example
    monitoring equipment options may be TEOM,
    Hi-Vol, Partisol, Microvol, OSIRIS, Dust Track
    Grimm, Dust Scan, Beta Attenuation Monitor,
    Nephelometer, Direction Deposition, deposition
    and other alternatives?
  • Confirmation monitoring if required has to be
    undertaken by at least one co-located reference
    method (AS , USEPA).
  • EPA is compiling a list of currently available
    instrumentation for both confirmation and
    reactive monitoring. Proponents should check with
    equipment suppliers to ensure that they have the
    assessed all available equipment suitable for
    either type of monitoring.

37
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com