Title: DoD DMSMS Teaming SubGroup


1
DoD DMSMS Teaming Sub-Group
Training Session
DISTRIBUTION STATEMENT Request Approval from
DMEA, Document date 15January2003
2
Agenda
  • Introduction
  • DMSMS 101
  • DoD DMSMS Teaming Database
  • Points of Contact
  • Questions

3
Teaming Vision
  • VISION
  • Provide a cross-service forum for communication
    on common obsolescence issues.
  • GOAL
  • Educate Program Managers, minimize the cost
    impacts of obsolescence, and disseminate
    information through the government industry data
    exchange program (GIDEP) and other DoD and
    services agencies.
  • OBJECTIVE
  • Reduce the Total Ownership Cost impacts of
    obsolescence.

4
Teaming Database Overview
SUPPLIER(S) SOLUTIONS REVIEW/ INPUT
Air Force PROGRAMS
Teaming Database (Naval Undersea Warfare Center
(NUWC) Keyport, Washington)
COMMON PROGRAM DMSMS
PROGRAMS WORKING TOWARD A COMMON SOLUTION
ARMY PROGRAMS
PART NUMBERS WAITING TO BE CASES
NAVY PROGRAMS
5
Members
Ron Shimazu DoD DMSMS Teaming Group Chairman (916
) 231-1508
DoD DMSMS Teaming Group Deputy David
Robinson (614) 692-7493
Teaming Database
AIR FORCE
ARMY
NAVY
  • M1A1 TANK
  • M1A2 TANK
  • MLRS
  • PATRIOT MISSILE
  • AEGIS
  • SPS-40, 48, 49
  • SPS-55, 64, 67
  • STANDARD Missile
  • NAVAIR
  • PAC-3
  • SEAWOLF
  • SQS-56
  • SQQ-32
  • VLS
  • AWACS
  • B-1B
  • B-2
  • B-52
  • C-17
  • F-16
  • JTIDS
  • JSTARS

Support Organizations
  • DSCC
  • DMEA
  • GIDEP
  • Suppliers
  • Industry

6
Benefits of Teaming
  • Promote Communications Among Programs
  • Avoid High Cost of Redesign
  • Share the Workload
  • Whenever possible Share Solution Cost
  • Example 2 programs have the same microcircuit.
    This microcircuit cost 40,000 to reverse
    engineer. Both programs share the cost of
  • Non recurring engineering (NRE)
  • Qualification cost.
  • Share in production cost
  • Reduce Time and Effort to Obtain a Solution

7
WHO SHOULD PARTICIPATE IN THE DOD DMSMS TEAMING
GROUP ?
8
Government Participation
  • Facilitates Government Networking among other
    Programs, Industry and Suppliers
  • Provides potential for Government programs to
    share solution costs.
  • Educate Program Offices in current trends,
    solutions, and tools in obsolescence management.

Active Participation by Government Program
Offices is the Key to Success !!
9
Industry Participation
  • Facilitates Information Sharing among other
    Programs, Industry and Suppliers
  • Provides potential for reducing time and costs
    associated with DMSMS solutions.
  • Provides a forum for sharing current trends,
    solutions, and tools in obsolescence management.

10
Supplier Participation
  • Facilitates Networking among other Programs,
    Industry and Suppliers
  • Facilitates Information Sharing among other
    Programs, Industry and Suppliers
  • Provides a forum for identifying potential
    solutions.

11
DMSMS 101
12
DMSMS Definition
  • DMSMS Diminishing Manufacturing Sources and
    Material Shortages
  • DMSMS Is defined as the loss or impending loss
    of manufacturers or suppliers of items or
    shortages of raw materials.

13
Component Life Cycle
Active Device manufacturers are designing product
life to be compatible with life cycles of the
commercial off the shelf (COTS) equipment
14
Types of Component Solutions
  • TYPES OF SOLUTIONS
  • BRIDGE BUY Purchase of sufficient quantity to
    continue program support while implementing a new
    solution.
  • LIFE OF TYPE BUY Purchase a supply of DMSMS
    items to support total demands for the life of
    impacted systems or equipment.
  • AFTER MARKET SUPPLIER This is a source that may
    provide
  • Finished goods, continued manufacturing of the
    original manufacturers product, mil wafer
    storage and commercial wafer.
  • ALTERNATIVE PART - A form fit function
    replacement that requires documentation to be
    updated.
  • Excess Stock - Residual stock from minimum buys,
    or contractual changes. (Implementing this
    solutions does not mitigate the original
    obsolescence problem.)

15
Types of Component Solutions
  • CONTINUING SOURCE - Group of programs together
    defining a requirement that changes the
    manufacturers decision to obsolete a given
    product from production.
  • DEVELOP A NEW SOURCE Develop a new source for
    the same product.
  • SUBSTITUTE PART Require minor redesign to
    accommodate the part and change appropriate
    documentation.
  • RECLAMATION Removing components from a system
    that is no longer being utilized and performing
    tests to ensure that the component will continue
    to meet its design tolerances.

16
Types of Component Solutions
  • EMULATION Emulation is the process of
    developing F3 replacements for obsolete
    microcircuits using state of the art material
    design and processing techniques.
  • REVERSE ENGINEERING - Is the process of
    developing F3 replacements for obsolete products
    using state of the art material design and
    processing techniques.
  • REDESIGN This solution is chosen when it is
    more economical to redesign than to identify
    solutions for a large number of DMSMS products
    that exist on a circuit card.
  • VHDL - Very High-Scale integrated Circuit (VHSIC)
    Hardware Description Language

17
How does a Program Manager reduce costs
associated with these solution options ??
18
(No Transcript)
19
Teaming Database
  • Teaming database is used for
  • Determining commonality among programs, tracking
    solutions and project cost using industry average
    cost metrics.
  • Collecting program part numbers that have been
    predicted to be obsolete.
  • Maintains history of solutions by program.
  • Provides case tracking and resolution metrics for
    management support.
  • Helps provide a source for DMSMS solutions.

20
Teaming Database is NOT
  • A procurement health database.
  • A cost modeling decision tool
  • For analyzing programs bill of materials.

21
Types of Participants
  •  
  • Full Participant is a program representative
    that inputs their programs parts obsolescence
    cases into the teaming database have full view of
    the open cases.
  •  
  • Limited Participant is a party that just desires
    to review the database solutions and not provide
    their programs parts obsolescence cases into the
    teaming database. This participant will only
    have access to unique part number typed into the
    database one at a time.
  • Suppliers are the original equipment
    manufacturers (OEMs) or after market supplier
    that provide the components or commercial off the
    shelf (COTS) equipment have full view of the open
    cases to help provide solutions.
  •  

22
Sample Input to Teaming Database
23
Sample Report
24
DoD DMSMS Teaming Sub-Group Points of Contact
  • DoD DMSMS Teaming Group - Chairman
  • Ron Shimazu DMEA (916) 231-1508
  • shimazu_at_dmea.osd.mil
  • DoD DMSMS Teaming Group - Deputy
  • Dave Robinson DSCC (614) 692-7493
  • david.robinson_at_dscc.dla.mil
  • Focal Points
  • James Neely Air Force
  • David McIlhaney Navy
  • LtCol Lee (TBD) Army
  • Vance Anderson DMEA
  • Charlie Besore DLA
  • Bill Pumford GIDEP
  • John Laskin/Eric Brandriff Industry
  • Lee Mathieson/Jack Stradley Suppliers
  • Web info at www.dmsteam.arinc.com and
    www.gidep.org

25
Questions ??
DoD DMSMS Teaming Sub-Group More info at
www.gidep.org