Title: APG Military Construction Program
1APG Military ConstructionProgram
- SAME Chesapeake Post
- CPT BJ Kraemer
2Agenda
- BRAC
- APG Military Construction Overview
- C4ISR Phase 1 Update
- C4ISR Phase 2 Program
- Overview
- Update
- USACE Team APG Update
3BRAC
- Base Realignment and Closure Act
- BRAC 2005 requires US Army Corps of Engineers to
realign BRAC impacted organizations and missions
to Aberdeen Proving Ground (APG) by September
2011.
4APG BRAC Program Overview
- Background
- Philadelphia District (NAP) supporting entire
C4ISR program - Baltimore District (NAB) supporting all other
BRAC guidance at APG - BRAC mandated moves MUST all be completed (fully
mission capable) by September 2011 for Army to be
in compliance with Congressionally mandated law.
5 Army Test Evaluation Command Headquarters
Location Aberdeen Scope BRAC construction of
a headquarters administrative facility at
Aberdeen Proving Ground, MD to support the
relocation of Headquarters US ATEC and AEC from
activities currently located in Alexandria,
Va. Delivery Method Design-Build Phase
Construction AE WDG Architecture DB Contractor
Foulger Pratt Awarded March 13, 2009 BOD Jun
11 Status Project awarded, waiting on
contracting to Issue notice to proceed.
6 Non-Medical Chem Bio Facility (JPEO)
Location Edgewood Scope Construct a joint
administrative facility with general
administrative, special space, conference/meeting/
training rooms, storage, and technical shop for
Chemical Biological Defense Activities. Delivery
Method Design-Build Phase Proposals received 14
Nov 08 AE Ewing Cole DB Contractor
Bradley-Nason Construction Awarded February 27,
2009 BOD Jun 11 Status Project was awarded
and the Corps and contractor are moving forward
with preliminary meetings.
7ARL Vehicle Technology Facility
Location Aberdeen Scope Construct research,
development, test, and evaluation (RDTE)
laboratories and facilities, and associated
general administrative and special purpose space.
These buildings will be an addition to the
Rodman Building. Delivery Method
Design-Bid-Build Phase Design AE Jacobs
Engineering Construction Contract Award 19 Jun
09 BOD 10 Jun 11 Status AE producing 100
submission.
8MRICD Chem. Bio Defense Lab
- Location Edgewood
- Scope Construct a 526,000 SF multistory
chemical containment medical research facility
for USAMRICD. The facility will enable the
development, testing, and evaluation of medical
treatments and material to prevent and treat
causalities exposed to chemical warfare agents. - Delivery Method Design-Bid-Build
- AE IDP Joint Venture
- Award
- Early Site work Contract April 09
- Construction Contract Jun 09
- BOD Feb 13
- Status 95 Design complete
9 BRAC Infrastructure Gate 715
Location Aberdeen and Edgewood Scope Design
and construction of Gate 715 Improvements
including earthwork, utilities, additional entry
lanes, VCC, Canopy and embedded traffic control
devices Delivery Method Design-Bid-Build Phase
Construction AE Jacobs Contractor
Facchina Construction Contract Award 18.2M, FY
07 Notice to Proceed 6 Feb 08 BOD May 09
Status 80 Complete
10C4ISR Phase 2 C2/CNT East
Location Aberdeen Scope 650,000 SF of new
high-tech, electronics-communications RD
facility Delivery Method DBB AE Ewing Cole
C2/CNT East CWE 150-200M Advertise 26 Jan
09 Bid Opening 7 Apr 09 Award 21 Apr 09 Status
Advertised. Building turnover 31 Dec 10, site
work complete Aug 11. Early Site Package awarded
3 Feb 09 for 2M and Magazine Road awarded 27 Feb
09 for 0.4M to clear C2/CNT East footprint.
11Consolidated North
Location Aberdeen Scope 140,000 SF of new
integration, fabrication and research and
development facility Delivery Method DBB AE
Jacobs Consolidated North CWE 40-60M Advertise
11 Jun 09 Bid Opening 24 Jul 09 Award 7 Aug
09 Status 95 Design due 30 Apr 09. Building
turnover 31 Dec 10.
12Building 5100
Location Aberdeen Scope 109,000 SF of
adaptive re-use space for integration,
fabrication and research and development facility
Delivery Method DBB AE Jacobs Bldg 5100 CWE
15-30M Advertise 18 Jun 09 Bid Opening 31 Jul
09 Award 14 Aug 09 Status 95 Design due 7 May
09. OCS footprint clears 30 Sep 09. Building
turnover 31 Dec 10.
13JSEC (Joint Satellite Engineering Center)
Location Aberdeen Scope 98,000 SF of
satellite engineering and research and
development facility Delivery Method DBB AE
USACE JSEC CWE 30-50M Advertise 2 Jul 09 Bid
Opening 14 Aug 09 Award 28 Aug 09 Status 95
Design due 21 May 09. Building turnover 31 Dec 10.
14Integration Facility
Location Aberdeen Scope 85,000 SF of new
integration and fabrication facility Delivery
Method DBB AE Jacobs Integration Facility CWE
5-15M Advertise 15 Dec 09 Bid Opening 15 Feb
10 Award 15 Apr 10 Status 35 Design received
25 Mar 09. OCS footprint clears 30 Sep 10.
Building turnover 30 Jun 11.
15C4ISR Phase 2 Site/Utilities
Location Aberdeen Scope Electrical
Distribution Substation, Water Sewer and
Roadway/Intersection Improvements within the
Phase 2 footprint Delivery Method DBB AE
Jacobs Site/Utilities CWE 15-30M Status
Multiple solicitation packages. Electrical
Substation Distribution 95 Design due 1 Jun
09. Water Sewer 95 Design due 24 Apr 09.
Roadway improvements within Phase 2 project area
95 design due 25 May 09.