Construction Projects In Default - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Construction Projects In Default

Description:

Retained Expert to Listen and Evaluate Evidence Giving Rise to Potential ... Expert ... Experts Analysis of Cost. How has the project been funded so far? ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 16
Provided by: compa163
Category:

less

Transcript and Presenter's Notes

Title: Construction Projects In Default


1
Construction Projects In Default
  • ABA Annual Real Property, Estate Planning
    Symposia
  • Waldorf-Astoria Hotel
  • New York, New York
  • 2-4 April 2003
  • Robert C. McCue, President, P.E.
  • Shelly Gowen, Vice President
  • MDCSystems

2
Surety
  • Why is Surety and Suretys Expert Attending this
    Meeting?
  • There is no formal termination of default.
  • There is no letter from owner
    threatening default.

3
Good Faith Effort
  • Our Contractor has Informed us that there are
    Project Rumors that the Contractor will be
    Defaulted.
  • We have also heard that the Owner may Abandon the
    Project Due to Lack of Funding.

4
Stand Behind Our Contractor
  • Contractor has been a Good Client of the Surety
    for Over 20 Years.
  • Never has received a Default Termination before.
  • Never has received a Threat of Termination Before.

5
Accuracy of Evidence
  • Retained Expert to Listen and Evaluate Evidence
    Giving Rise to Potential Termination of Our
    Contractor.
  • We need to Realistically Determine Whether
    Project can be Completed Given the Funding
    Issues.
  • Identify Alternatives if Possible for Completing
    the Project.

6
Expert
  • Given the project status, surety has hired a
    forensic project management group to determine
    what is the status of construction.
  • Evaluate the performance of our contractor.
  • Make a construction and engineering
    recommendation as to whether the project can be
    completed.

7
Experts Analysis of Scope
  • Is Original Scope of the Project Practical?
  • If yes, what is it going to take to manage the
    project?
  • If no, is it possible to reduce scope and
    complete a different project than originally
    intended?
  • Will funding stay in place if scope is reduce?

8
Experts Analysis of Schedule
  • What was the planned schedule?
  • Analysis of as-built schedule.
  • Is it possible given the as-built conditions to
    complete project on time?
  • Can schedule be modified to a scaled back
    project?
  • What will it take in scheduling resources to
    bring project or reduced project to completion.

9
Experts Analysis of Cost
  • How has the project been funded so far?
  • What is the percent complete of the project?
  • What are the funding issues as of this date?
  • Do funding entities want to complete original
    project?
  • Do funding entities want to complete a modified
    project?
  • Are the costs for the construction reasonable?

10
Completion Depends On.
  • Willingness of funding parties to participate at
    a specific level.
  • Willingness of contractor and architect-engineer
    to continue working.
  • Willingness of the owner/developer to pay
    contractor and architect-engineer.
  • Willingness of the owner/developer not to make
    more changes but scale back the project.

11
Surety Initial Analysis
  • Contractor is not on the road to bankruptcy,
    however owner/ developer may be.
  • Contractor has not abandon the job.
  • Contractor continues to perform despite waiting
    inordinate amount of time for change orders and
    responses to claims.
  • Contractor is not using any unauthorized
    subcontractors.

12
Surety Initial Analysis
  • Project is delayed Not because of the
    contractor!
  • Massive design changes by owner
  • Delay in receiving RFIs and shop drawing
    approval
  • Owner supplied equipment is delivered late
  • Site not ready

13
Surety Initial Analysis
  • Some subcontractors not paid due to delay in
    receiving progress payments from owner.
  • No insurmountable design or technical problems
    just late.
  • No reported violations of the law.
  • No failure to secure insurance.
  • No substantive safety violations.

14
Surety SolutionsExperts Recommendation
  • Scale back the project.
  • Focus on construction of earliest revenue
    portions of the project only.
  • Retail Shop Space
  • Restaurants
  • Common area
  • Construct condominiums in groups.

15
Contact Us!
  • MDCSystems
  • 1-888-MDC-9977
  • www.mdcsystems.com
  • Mccue_at_mdcsystems.com
  • Gowen_at_mdcsystems.com
Write a Comment
User Comments (0)
About PowerShow.com