Patrick Kearon The Bristol Port Company - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Patrick Kearon The Bristol Port Company

Description:

Archaeology. Traffic and transport. Noise and vibration ... Archaeology. Assessment of archaeological remains in the vicinity of the development site: ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 19
Provided by: auth215
Category:

less

Transcript and Presenter's Notes

Title: Patrick Kearon The Bristol Port Company


1
Patrick KearonThe Bristol Port Company
2
Background
  • Global warming we all need to reduce CO2 output
    from our activities
  • UK Target 20 reduction in 1990 CO2 levels by
    2010
  • South West Target 11-15 of electricity from
    renewable sources
  • Dependence on finite fossil fuels increasing
    energy costs
  • UK is Europes windiest country - average mean
    wind speeds gt7m/s (18mph)

3
The Answer
Imperative for The Bristol Port Company to
develop a local renewable energy source to supply
port demand
4
Outline of Proposals
  • Erect 3 wind turbines (up to 3 MW), including
    associated bases and cables
  • Construct control building access ways
  • Combined 9 MW up to 75 of ports electricity
    demand
  • Development site is 8.5 hectares of reclaimed
    land in Avonmouth Dock
  • Adjacent to Severn Estuary

5
Site Location
6
Site Selection - Alternatives
  • 9 potential locations short-listed and tested
    against 3 key factors
  • Wind generating potential
  • Aviation safety (Filton Airfeld)
  • Possible impacts on birds using the estuary
  • This location in Avonmouth Docks was identified
    as optimum site
  • Turbine location finely adjusted to not interfere
    with air safety bird migration routes

7
The Preferred Site
8
Typical Wind Turbine Dimensions
9
Environmental Issues
  • Geology/Ground Conditions
  • Hydrology/Hydrogeology
  • Ecology
  • Landscape and visual impacts
  • Archaeology
  • Traffic and transport
  • Noise and vibration
  • Telecommunications
  • Air traffic

10
Landscape and Visual Impacts
  • Evaluate effect on local landscape
  • Turbines located in low-lying, heavily
    industrialised landscape, with many tall
    structures buildings
  • Landform, structures woodlands restrict
    visibility
  • Turbines will be visible from
  • Avonmouth Village (partial, restricted views,
    change inevitable in places)
  • Pill (noticeable, but not intrusive)
  • Higher elevations e.g. Lawrence Weston
    Shirehampton (more visible, but distant
    panoramic, not intrusive)

11
Photomontage of Landscape
12
Ecology and Birds
  • No valuable habitats on site, but next to Severn
    Estuary SPA, SSSI and Ramsar site
  • Ecological surveys to inform assessment of
    impacts on wildlife, including
  • Extended Phase 1 habitat survey
  • Bird surveys (e.g. High tide/low tide counts,
    night time, migration and breeding surveys)
  • Key potential impacts on birds are Disturbance
    Collisions
  • With mitigation no adverse impact during
    construction
  • 5 years monitoring (review in 2 years)

13
Bird Movements
14
Archaeology
  • Assessment of archaeological remains in the
    vicinity of the development site
  • Terrestrial archaeology
  • Maritime archaeology and historic activity
  • Borehole assessment
  • No known sites or monuments affected by the
    development
  • Construction of turbines includes 30 metre piles
    into made ground
  • Mitigation/Monitoring archaeological recording

15
Historic Mapping
16
Balance of Effects
  • No major adverse environmental impacts
  • Potential disturbance of SPA birds and changed
    views from areas of Avonmouth Village
  • All other negative impacts avoided or reduced by
    mitigation and design measures
  • 17-26 of south wests renewable energy target
  • Provision of up to 75 of Ports electricity
  • Significant reduction in green house gasses
    (18,319 tonnes CO2 /plus SO2 NOx)

17
Construction Operation
  • Construction end 2006
  • Construction programme about 36 weeks
  • In operation this time in 2007
  • Operational life of 25 years
  • Turbines then either replaced, refurbished or
    removed site reinstated

18
The Way Forward
  • BPC agreement with Ecotricity who will construct,
    own and operate the turbines
  • BPC provided with energy for life of turbines
  • Overspill electricity is publicly available -
    see (http//www.ecotricity.co.uk)
  • We all need to do more to tackle global warming
    problem
  • Wind turbines can contribute to the renewable
    energy solution
Write a Comment
User Comments (0)
About PowerShow.com