Title: IENG%20471%20Facilities%20Planning%20Dr.%20Frank%20Joseph%20Matejcik
1IENG 471 Facilities Planning Dr. Frank Joseph
Matejcik
11/03 Chapter 10.8 Fixed Path Material Handling
Equipment (Conveyors)
- South Dakota School of Mines and Technology,
Rapid City -
2Section Intro
- Widely used
- Types
- powered belt and roller conveyors
- towline and trolley-type conveyors
- AGVs
- Computer Dispathed Lift Trucks
3Towline or Trolley Conveyors
- Called conveyor analysisanalysis of
closed-loop, irreversible, or recirculating
conveyors with discretely spaced containers.
4Towline or Trolley ConveyorsOperating Problems
- 1. At a loading station, no empty carriers were
available when a loading operation was to be
performed. - 2. At an unloading station, no loaded carriers
were available when an unloading operation was to
be performed.
5Kwos Principles for closed-loop irreversible
Conveyors
- 1. Uniformity principle Materials should be
uniformly distributed over the conveyor. - 2. Capacity principle The carrying capacity of
the conveyor must be greater than or equal to the
system throughput requirements.
6Kwos Principles for closed-loop irreversible
Conveyors
- 3. Speed principle The speed of the conveyor (in
terms of the number of carriers per unit time)
must be within the permissible range, defined by
loading and unloading station requirements and
the technological capability of the conveyor. - Also, Kwo found sufficient conditions for
steady-state operations
7Muth defintions
- s is number of stations
- k is number of carriers
- The amount of material loaded on carrier n as it
passes station i is given by fi(n) for i 1, 2,
s - The amount of material carried by carrier n
afterit passes station i is given by Hi(n) for i
1, 2, s
8Muth formulas
- p is the period. We assume f is periodic
- F is a convenience term.
9Muth results
- 1. k/p cannot be an integer for steady-state
operations. - 2. Letting r k mod p, r/p must be a proper
fraction for general sequences F1(n) to be
accommodated. - 3. It is desirable for p to be a prime number, as
conveyor compatibility results for all admissible
values of k
10Approach to find Hi (n)
11Approach to find Hi (n)
12Example 10.30
13Example 10.30
14Example 10.30
15Example 10.30
16Example 10.30
17Example 10.30
18Example 10.30
19Example 10.30
20Example 10.301
- As a design choice we may try to alter the value
of k. - The results may not be obvious increasing k does
not always decrease the value of B. - Also, as a design choice we may be able to change
the value of s.
21Example 10.30 Alternative k s
22Example 10.30 Alternative k s
23Examples 10.31 10.32 comments
- Example 10.31 shows that reordering of the fi(n)
sequences can reduce the value of B. This is a
possible design decision. - Example 10.32 exchanging positions even when s
3 can reduce B.
24Horsepower Requirements
- HP horsepower requirement
- S speed of conveyor (fpm)
- L load to be carried (lbs)
- TL total length of conveyor (ft)
- RC spacing between center lines of rollers
- WBR width between rails (belt width 2.5)
- a angle of incline
- LLt live load in incline (lbs)
- BV base value
- FF Friction Factor (roller.05, slide bed0.3)
- LF Length Factor
25Horsepower Requirements
This formula is applied in a direct manner for
many of the calculations. Tables and comments
supply many of the unusual values. Bulk conveyors
are more simple. Just use tables and do a
summary calculation.
26Belt Conveyors
- BV approx. (2/3) WBR
- FF 0.05 roller, 0.30 bed supported
27Roller Conveyors
- FF 0.10 to 0.05 based on drive type
- BV 4.60 0.445(WBR)
28Bulk Belt Conveyors
- Speed given belt width is limited
29Bulk Belt Conveyors
- Table 10.14 gives max. angle of incline
- Table 10.15 gives Delivered Capacity
- Table 10.16 HP of empty conveyor
- Table 10.17 HP of horizontal delivery
- Table 10.18 HP for lifting material
- Overall HP 1.2(Sum 3 tables above)
30Flow Path Design Models
- Conventional Flows
- Tandem Flows
- Deciding between the two is beyond the scope of
the text.
31Conventional FlowAnalytical Model
- Decide direction of flow
- generally unidirectional or bidirectional
- This model unidirectional
- Kaspi Tanchoco node arc network
- Nodes pickup station, delivery station, and
aisle intersections - Arcs flow paths between nodes
32Analytical Model Variables
33Analytical Model Objective
34Analytical Model Constraints
35Analytical Model Constraints
36Analytical Model
- Too large a model (too many variables) for
practical situations - branch bound method can give feasible solutions
in reasonable times
37Branch and Bound Approach
Tandem Flow Systems