Title: Monitoring Progress
1Monitoring Progress
2Constraints in a project
Time
Cost
Quality
3Monitoring Progress
- Monitoring Effort
- Monitoring Cost
- Monitoring Quality
- Milestone Slip Chart
- Earned Value Analysis
4Monitoring Effort
- In IS projects,
-
- Major resource ? staff time
- To gather information on the effort
- Timesheets can be used.
5Monitoring Effort
Effort-monitoring timesheet
Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending Name Project Week ending
Code  Mon Tue Wed Thu Fri Sat Sun Total To go
A/01 CODE PROGRAM CV004 6,5 5,0 7,5 Â Â Â Â 19,0 NIL
A/02 TEST PROGRAM CV004 Â Â Â 7,5 3,0 Â Â 10,5 NIL
A/07 CODE PROGRAM EN025 Â Â Â Â 4,0 Â Â 4,0 15,0
          Â
          Â
          Â
M/03 TEAM MEETING Â Â Â Â Â Â Â 1,0 Â
M/02 COMPLETE TIMESHEET Â Â Â Â 0,5 Â Â 0,5 Â
6Monitoring Effort
Effort to go
- We can not turn back time, so efforts should be
focused on the future and the work to be done. - (Original Estimate)-(Effort Expended to
date)Estimate to go
7Monitoring Effort
Some Additional Features for Timesheet
- Comments about problems, delays
- Predicted end-date
- Non-productive but project related activities
(e.g. meetings)
8Monitoring Effort
Bar chart showing project progress
9Monitoring Cost
- Labour costs
- Project-specific training
- Specially arranged accomodation
- Lodging and subsistence costs
- Travel costs
- Consumables
- Insurance
10Monitoring Cost
- Monitoring costs can be done using the weekly
submitted timesheets. - Timesheets are then used as the basis for an
invoice. - Problem Time lag between work done and costs
appearing on the account.
11Monitoring Quality
12Monitoring Quality
Decision points
- Having checks at milestones
- When phases change
- When there are new standards
- When there are new techniques or methods
- Checking the work of inexperienced staff
13Monitoring Quality
Testing the finished product
- Testing individual components
- Testing components linked to each other
- Testing complete system
- Testing made by the customer for acceptance
14Monitoring Quality
Methods for monitoring quality
- Self-checking
- Team leader reviews
- Peer reviews
- Walkthroughs
- External review
- Fagan Inspections
15Monitoring Quality
- Self-checking
- best suited for experienced team members
- Team leader reviews
- useful when work is linked to coaching
- disadvantage one person checks all and team
leader may not be as skilled as the author - Peer reviews
- one person checks others work
- danger rivalry
16Monitoring Quality
- Walkthroughs
- a review by a group of people
- requires good organization and clear objectives
- focusing on the identification of problems
- avoid finding solutions
- meetings should be time-limited (max.1-2 hours)
- External review
- disadvantages
- person checking may not be familiar
- cost
17Monitoring Quality
- Fagan Inspections
- formalised form of walkthrough
- author of the work reports that the work is
complete and ready to be checked - Defect detection is the main activity of software
detection - Defects are identified, classified and logged
18Monitoring Quality (Fagan Insp.)
- Planning
- moderator organises date, duration,... of the
meeting - Overview
- objectives of the inspections, roles are defined
- Preparation
- individual inspections by participants
- Meeting
- participants gather and inspect the work
- Rework
- author takes the list of defects
- Follow-up
- a reviewer chacks the rework
19Documenting Quality Control
20Monitoring Quality
Systems of Classification
- Four-stage system
- Minor non-conformance
- More serious non-conform.
- Major non-conformance
- Very severe non-conform.
- Three-stage system
- Severe Defect
- Less Severe Defect
- Minor Defect
21Milestone Slip Chart
22Earned Value Analysis
- Measures how much has been spent and how much has
been achieved - Problem cumbersome and uneasy terminology
23Earned Value Analysis
- Actual cost of work performed (ACWP)
- Actual spend (expenditure to date)
- Budgeted cost of work scheduled (BCWS)
- Planned spend (what plan says)
- Budgeted cost of work performed (BCWP)
- Earned value (completed work)
24Earned Value Analysis Example
- Five Programs
- Each one requires 2 weeks to write and costs
2,000 - Total 10,000
25Earned Value Analysis
actual spend 3,000 planned spend
4,000 earned value 2,000
Progress Check
26Earned Value Analysis
- Cost variance Earned Value Actual Spend
- Cost Performance Index Earned Value / Actual
Spend - (CPI)
- Schedule variance Earned Value Planned Spend
- Schedule Performance Index Earned Value /
Planned Sp. (SPI)
27Earned Value Analysis
- Predicted budget outturn Original budget / CPI
- Predicted timescale Original timescale / SPI
28 29