Project Network Diagrams overview - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Project Network Diagrams overview

Description:

Diagrams that represent activities, events (milestones), precedence relations, and durations ... that are unrelated by precedences, and do not share resources, ... – PowerPoint PPT presentation

Number of Views:173
Avg rating:3.0/5.0
Slides: 23
Provided by: coe84
Category:

less

Transcript and Presenter's Notes

Title: Project Network Diagrams overview


1
Project Network Diagrams (overview)
  • Comm 589
  • Mats Gerschman

2
Learning objectives
  • To understand what a Network diagram represents
    in project management
  • To understand what is meant by predecessor and
    successor activities
  • Understand how to calculate slack
  • Understand how to find the critical path and why
    this is important

3
Definition Project Network Diagram
  • The activities and the activity durations to
  • pictorially represent the sequences in
  • which the project work can be done.

4
Network representations of projects
  • Diagrams that represent activities, events
    (milestones), precedence relations, and durations
  • A network (or graph) consists of
  • Nodes (points)
  • Arcs (lines, links)
  • Numbers associated with the nodes and/or arcs
  • Two styles of project networks
  • PERT
  • CPM

5
PERT and CPM
  • PERT Program Evaluation and Review Technique
  • Activity on arcs
  • Nodes represent events (start, end of activities)
  • May need dummy activities to represent some
    precedences
  • CPM Critical Path Method
  • Activity on nodes
  • Arcs represent the precedences
  • Extra nodes (activities) for milestones (incl.
    the start and end of whole project)
  • Both represent the logical structure of the
    project
  • In particular, line lengths do not represent time
    or durations

6
CPM Network Diagram an example
  • Setting up a new nursing home facility
  • Define activities
  • Activity A run pilot service in new facility
  • Activity B build facility
  • Activity C install equipment and furnishing
  • Activity D recruit staff
  • Activity E train staff
  • Activity F pass safety inspection
  • Identify precedences
  • Activity A predecessors are C, E, F
  • Activity B no predecessor
  • Activity C predecessor is B
  • Activity D no predecessor
  • Activity E predecessor is D
  • Activity F predecessor is B

7
Precedence relations
  • 3) Diagram the precedence requirements

8
Project scheduling
  • Gantt Chart
  • A bar chart showing activity progress vs time
    used for both scheduling and control

9
Critical path method (CPM)
  • Main ideas
  • Whole project should be completed ASAP (but while
    keeping an eye on costs)
  • Ex) penalties for late completion
  • For this, activities,
  • that are unrelated by precedences, and do not
    share resources, may be undertaken simultaneously
  • Identify critical activities, ie, those for which
    any delay will delay the whole project
  • Allocate resources among activities to find the
    right time/cost tradeoffs.

10
Critical path method cont.
  • Schedule the start and end times of each
    activity, so as
  • To secure the corresponding resources
  • To be able to monitor that project is on track
  • Schedule expenditures and resources

11
Logical steps
  • Forward pass for each activity, find its
  • earliest start time ES
  • earliest finish time EF
  • Backward pass for each activity, find its
  • latest finish time LF
  • latest start time LS
  • For each activity, find its slack time
  • S LS ES
  • Identify the critical activities, where S 0,
    and the critical path(s)

12
Activity durations
C, 3
B, 24.3
A, 5.5
F,15.3
D,2.1
E,5
13
Forward pass?determine the earliest project
completion time
  • set time to start project, say 0
  • determine the earliest start times ES
  • an activity can start as soon as all its
    predecessors are completed, but no sooner
  • and the earliest finish times
  • EF ES activity duration

24.3, 27.3
0, 24.3
45.1
0
39.6, 45.1
24.3, 39.6
0,2.1
2.1, 7.1
14
Backward pass?determine the latest start times
  • set time to finish project,
  • Normally, the earliest project completion time
    (found in the forward pass)
  • determine the latest finish times LF
  • an activity can finish before all its
    successors are started, but no later
  • and the latest start times
  • LS LF - activity duration

36.6, 39.6
0, 24.3
39.6, 45.1
24.3, 39.6
45.1
0
32.5, 34.6
34.6, 39.6
15
Slack times S LS ES
  • 4. Critical activities S 0
  • and Critical path (or paths)

12.3
0
0
0
0
0
32.5
32.5
16
CPM Assumptions/Limitations
  • Project activities can be identified as entities.
    (There is a clear beginning and ending point for
    each activity.)
  • Project activity sequence relationships can be
    specified and networked.
  • Project control should focus on the critical path
  • Project timing can be estimated

17
Example in EPM where activities are days
Forward pass
Assume that activity starts in morning and ends
in evening
18
Backward pass
EF
ES
LS
LF
19
Critical path (Slack0)
Slack LS - ES
20
Slack and duration
21
Summary
  • Finding dependencies of activities is very
    important in project management
  • Creating a network diagram will assist in the
    planning of the the projects utilization of
    resources
  • Focus must be on the critical path
  • Gantt charts are most commonly used for planning,
    but they have limitations.

22
Home work for Jan.24 and Jan.26
  • Next class (Jan.24) homework The Campus wedding
    displayed on OH or Powerpoint and handed in.
  • By Jan.26
  • In MS Project
  • WBS broken down to lowest level activities for
    Deployment
  • Time estimates depicted in Gantt chart with
    interdependencies displayed
  • Estimated resource requirements (note For the
    consulting company)
  • Group1 Mingming, Mehmet, Bailey
  • Group 2 Mei, Ryan, (Kevin)
  • Group 3 Yurik, Ian
Write a Comment
User Comments (0)
About PowerShow.com