Title: Project Status and Reviews
1Project Status and Reviews
- Michael Hebert
- UC Irvine
- Feb 6, 2005
- MECO Collaboration Meeting
2MREFC Program Status
- In October Congress approved 15M for RSVP in the
FY05 NSF budget - These funds will only be released if we have
successfully baselined the experiment. The goal
is to achieve that in late April, i.e. before the
May National Science Board meeting. - It now appears that passing this baseline review
is a political necessity. To quote Jon Kotcher,
there really is only one message we do
whatever we must do to get this project baselined
in the next few weeks - nothing else matters. If
we don't make this, we indeed may have nothing.
People should be heavily sensitized to this fact,
and the situation these projects are in
politically. Personnel must focus solely on this
goal, putting aside arguments and considerations
not directly related to a successful outcome
here, if this is going to succeed. That's the
long and the short of it. Do with it what you
will, but the fate of RSVP is in the balance of
the next few weeks. - The FY06 NSF request will be known on Monday as
part of the Presidents Budget Request to Congress
3MREFC Total Budget
- RSVP Management has set the following cost
targets (burdened FY05) - KOPIO - 55M
- MECO magnet - 56M
- MECO - 24M
- AGS - 40M
- Project Office - 20M
- The total is 195M, to which is added 46M in
RSVP Management Contingency for a grand total
MREFC target cost of 241M. - Exactly how these totals were arrived at is not
clear, but the statement is that it was by
scaling June 2001 costs for MECO and KOPIO by a
common factor. Given that MECO presented costs of
85M and KOPIO 75M (less 20M for foreign
contribution) last month, there is a clear
disconnect that we need to resolve. - This also emphasizes that there has been a
(poorly communicated) fundamental shift in the
status of the magnets vis-à-vis the rest of MECO
(next slide).
4Magnet Management
- I have been informed that the MECO magnets are a
fundamentally different object and as such the
money for the magnets will be handled separately.
- Operationally this means that we cannot recoup
savings in the magnets elsewhere in MECO, nor
bolster the magnets if save money in our detector
cost scrubbing efforts. Any savings we realize
will revert into the RSVP contingency pool. - Management of the magnets has also changed, but
the details are vague. On one hand, Brad is still
reporting to me as the subsystem manager of this
MECO component. On the other hand, Brads
guidance on procurement activities is coming from
the RSVP Project Office. - Brad and I are working together to understand
what all of this means exactly. The only thing
that gives me hope is that we been able to work
well with Brad on everything to date and he
understands that we need to be intimately
involved in the magnets, regardless of what the
org chart looks like. - We may gain some additional insight late next
week as there will be a meeting with BNL to look
at the role SMD and C-AD can (and want to) play
in the magnets.
5Construction Schedule
- It now appears likely that RSVP will be cast as a
five-year construction program, not six as one
thought clearly an improvement - Begin construction in Fall of this year,
- Wrap up installation and pre-flight efforts no
later than the Fall of 2010 - Engineering running beginning in 2011
- This is consistent with our original MECO plan,
however that plan envisioned 30M in the first
year. We will need to determine the impact of
receiving half of that in the near future. More
on that in my next talk.
6RD Money 1
- All pre-FY04 funds have been expended
- UCI has received spending authority via a
subcontract with NYU for the 2M (less NYU
support) MECO portion of the nominal 6M in FY05
RRA money allotted to RSVP by Congress. - There are a total of nine subcontracts possibly
coming out of that money - MIT 516k In place Magnet Subsystem Manager
support, several small tests of prototype
components aimed at reducing cost risk in the
magnet procurement - BNL 171k Stalled Nominally for beamline
transport design, shielding layout, liaison staff
support, detector installation and support
structure designs, neutron absorber designs. We
have been trying for four months to get BNLs
Work for Others office to understand that this is
a NEW contract and handle it as such. Recent
KOPIO experience suggests that we reconsider how
we handle this. KOPIO funds finally reached the
Lab last week, only to withdrawn within days.
This because the money was going to be redirected
towards baselining efforts in C-AD in lieu of
KOPIO engineering work. Our money will likely
suffer a similar fate if we succeed in getting it
in the door. - Houston - 88k In Place Additional tracking
chamber prototype construction and testing,
chamber front-end electronics design and
prototyping, Education/Outreach support
7RD Money 2
- BU 91k Expected in the next week Conceptual
design of Trigger and DAQ electronics boards and
ASICs. - Syracuse 20k Expected in the next week
Transverse Tracker mechanical design and testing - LBL 125k No SOW Yet Six months of an
estimated one year effort to redesign the BaBar
"Elefant" readout chip - LLNL 40k On Hold Indefinitely This is for
magnet contracting support. Although consultation
with this group has been vastly more useful than
similar discussions with BNL procurement, there
remains the strong possibility that the latter
will handle this procurement. Until we have a
plan, there are no plans to go forward with work
at LLNL. - TBD 150k On Hold Indefinitely This is a
contract for the conceptual design of the RF
Modulated Magnet. We have not identified a vendor
yet, so this one is on hold - TBD 18k On Hold Indefinitely This is a
contract for the conceptual design of the Heat
and Radiation Shield. With the departure of Jon
Hock from the Lab, this activity halted at BNL.
The hope is that a new collaborator might take
this on.
8Supplemental RD Money
- RSVP has put in a proposal for additional
emergency funding this year - The only items included were RSVP PO and MECO
Magnet RD, no other MECO tasks, nor anything for
KOPIO or the AGS - Note that the magnet RD task list differs
significantly from our request RSVP Management
prerogative were told
9Recent Reviews
- October 04 MECO Magnet Review
- November 04 AGS Review
- January 05 RSVP Simulations Review
- January 05 BNL LOG Cost Review
- Upcoming Reviews
- Early April RSVP Internal Baselining Readiness
Review (next talk) - Late April NSF RSVP Baseline Review (next talk)
- TBD NSF RSVP Operations Cost Review - could be
as early as April but we can hope reason prevails
10Magnet Review
- MECO (primarily Brad) presented a very detailed
exposition on the current state of the magnet
design to a committee consisting mostly of ATLAS
magnet experts - Magnet layout
- Component masses
- Coil operating point summary
- Field spec and tolerances
- Conductor, joints, leads and buses
- Electrical insulation
- The report of the review committee was generally
favorable. There were, however, a large number of
recommendations, on both technical and management
/ procurement issues. The following slides
summarize these points. - One benefit of the review is that allowed us to
include funds for magnet studies (the only MECO
money that made the cut) in the supplemental
proposal to NSF that appears likely to be funded
soon.
- Power supplies
- Quench detection and protection
- Structural design criteria
- Cryogenic design
- Costs and Construction Schedule
11Magnet Recommendations 1
- Reduce the number of coils to minimize number of
connections / interfaces - Conduction cooling of the PS coils to eliminate
the need for 6700 liters of LHe - Gaseous He cooling of the internal heat shields
and warm-to-cold supports - Simplified analog quench detection / protection
system with far fewer channels - There is clearly insufficient input for single
vendor bid package. In our opinion there needs to
be model coil input for a final engineering
design. This is required in order to qualify the
technology adopted for winding and bonding, the
indirect cooling and thermal performance, and in
addition to perform the operations and thereby
train the core team for following up the
production. - Our rough estimate is that the overall project
might take about a year more than that
presented. - Cost comments
- 10 profit appears optimistic it may be 15
- Labor rates look low (in particular for
qualified welders) - Cost is based on 04 prices. Should escalate to
06 prices - The most important comment is that we would
expect the final price coming from a single
vendor to be considerably higher than that
quoted. This is primarily because certain
features are either underestimated or omitted,
e.g. 15 purchasing overhead appears low. Our
experience is 20-25 - 0 risk included. Once again, our recent
experience suggests 20-30
12Magnet Recommendations 2
- In total, the real cost may be 25 higher when
the single vendor option is chosen. The estimate
of cost of system integration at BNL requires
further study. Our proposal would be to get
independent budget cost estimates based on the
purchase of major components. - We consider the risk involved in going to a
single vendor to be too high. You may pay twice -
now for risk, later for cost overruns (and have
to do some of the work yourself anyway).
Consequently we strongly advise to go for a
Buy-in-Parts scenario. This may save 25 in
cost, as well as increase the likelihood of
getting a working magnet on time. This cost
saving will be more than sufficient to finance
the core magnet team required for production
follow-up, trouble-shooting and assembly.
Important side note, ATLAS got burned on a bad
procurement which sensitized 4 of the 5 committee
members to vendor reliability - Coming back to the magnet itself, it would be
helpful to get feedback from industry in
particular on coil winding, segmentation and
impregnation. With this in mind it would be
useful to make a draft RFI as soon as possible
(within 3 months, say) for the magnet, to be
followed by a draft RFP/SOW to get some answers
on cost, schedule and technical feasibility from
a few companies within the next 6 to 9 months. In
addition, and most important, this process should
be exploited in the short term to permit visits
to potential suppliers for technical discussions
that will hopefully lead to improvements in the
final engineering design.
13Magnet Recommendations 3
- We advise that in order to reduce project risk
the effort should now be concentrated on the
magnet itself. The provision of immediate funding
should enable the achievement of the following
critical studies and preparatory work in the
course of the next 6 months, which are essential
in order to keep the magnet project on track - Re-design of cooling of the PS, replacing bath by
conduction cooling, - Simplification of the magnet by reducing the
number of coil segments, - Make test windings to validate conductor, winding
and insulation technologies, - Do the industrial studies through the RFI, and
prepare the RFP, - Strengthen the team at MIT to speed up design
work, - Design and start construction of tooling for a
full scale model test coil. - The Reports conclusions
- We are confident that the conceptual design which
has been developed is a sound basis to move
forward to an RFP for the magnet. - The groups that have carried out this work should
be supported and strengthened. - To this end we recommend sufficient intermediate
funding, following a cost estimate, for the high
priority studies listed above. - Equipment that will have to be operated and
maintained by BNL should be specified with their
collaboration, and procured through BNL. - These recommendations are made with the objective
of reducing technical, financial and schedule
risk, and minimizing the overall cost of the
magnet.
14AGS Review
- Technical and Cost Review in November
presentations on - Booster
- AGS
- Electrical
- Mechanical
- Switchyard
- The committee noted the significant cost growth
although they acknowledged that much of it was
due to costs originally covered in pre-ops.
They nonetheless questioned the need for the full
scope of the AGS upgrade effort - The committee generally recommended addition cost
scrubbing, resource loaded schedule development,
and searching for major savings if possible - They also made a specific recommendation to
reduce beam development from five years to three
in order to save 14M in support of operations
personnel and power costs.
- KOPIO, MECO infrastructure
- Beam development
- Schedule Personnel
- Operations cost schedule
- Management Issues
15Simulation Review Recommendations
- While MECO has done a good job addressing many
issues via simulation, a clear inadequacy of the
simulations is the lack of detector digitization
and realistic event reconstruction. An increased
level of manpower devoted to software and
simulations is clearly needed. We recommend
that, as soon as possible, MECO - Develop a detector Monte Carlo with full
digitization of detector signals, and realistic
event reconstruction starting from raw data to
validate background estimates. - Perform tests with the AGS to demonstrate the
required extinction when running at 8 GeV with
intensity of at least 20 Tp/spill. - Continue to develop more realistic simulations of
the full target/transport channel/detector chain
to further explore exotic background scenarios. - In addition, the committee recommends that both
KOPIO and MECO - Develop deliverables-based schedules with
performance milestones, which include the steps
recommended in this report planned for completion
as early as possible. - Finally, the scenario described to us for AGS
running during RHIC data-taking, while perhaps
conservative, would provide only a marginal
amount of RSVP running per year. We urge BNL to
make it a high priority to maximize AGS slow
spill running during RHIC operation. Also, both
KOPIO and MECO should benefit if data-taking is
structured to provide the longest possible runs
in alternate years, rather than shorter runs
based on an equal division of available running
each year.
16LOG Cost Review
- An attempt was made to understand RSVP costs at
level 3 over the course of a three day review
under the auspices of the Laboratory Oversight
Group (LOG) for RSVP - Each level 3 system (e.g. Tracker, Calorimeter,
etc.) prepared a single sheet summary of their
costs broken down by materials, labor,
contingency, total in addition to a brief
presentation that tended to be a technical
presentation owing to the way the review charge
was written. - Given the difficulty of digesting this
information with little material in advance
(there were zero working days between the
Simulations and LOG Reviews), it is not
surprising that we did not get a lot of
substantive feedback. The conclusions (verbal
only) were - The AGS and the MECO Magnets appear ready to
baseline costs - Contingencies appear to be systematically
underestimated - No technical show stoppers were noted by the
committee, although they did endorse early beam
testing to validate the MECO beam extinction and
KOPIO neutral beam
17MECO Cost Estimate (FY05 )
WBS Task Cost (M) with academics Cost (M) without academics Cont without academics
1.3 MECO 94.52 85.83 28.8
1.3.1 Extinction 2.62 2.28 43.1
1.3.2 Production Target Shield 2.83 2.76 40.9
1.3.3 Superconducting Solenoids 55.20 55.20 28.6
1.3.4 Muon Beamline 3.35 3.25 33.6
1.3.5 Straw Tracking Chamber 5.50 3.78 24.5
1.3.6 Electron Calorimeter 7.98 6.30 25.6
1.3.7 Cosmic Ray Shield 2.47 1.67 13.3
1.3.8 Data Acquisition and Trigger 3.38 2.47 25.4
1.3.9 Simulations and Analysis 4.00 0.93 46.0
1.3.10 Installation and Integration 3.07 3.07 27.6
1.3.11 Project Management 4.13 4.13 28.7
18AGS Cost Cutting Measures
- The AGS cost target is 40M. The Jan 04
estimate was 82M including upgrades to the AGS,
Booster, Switchyard, and A and B Lines plus a
five year beam development plan. - Now, ALL beam development efforts have been
eliminated - C-AD questions whether we can exceed 20 Tp/s
proton throughput, let alone reach 40 Tp/s due to
ALARA limits. Losing these studies means we
wont start trying to understand what that factor
of two requires until 2008 when operating funds
start - The same statement applies to testing of
extinction and extraction at 7.5 GeV/c - Other changes
- Using existing shielding blocks for the concrete
portion of the cosmic ray shielding. Measured
activity rates are low so this looks like a
painless change. - Existing equipment removal will be on the DOEs
dime, as it should be - Reusing exists (ancient) power supply controls,
which might lead to reliability problems but
there is a large stock of working spares
available - Reuse existing vacuum pumps likely not a
problem - Reuse existing counting house (trailer) quality
of life issue