Title: DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE
1DOING A PARTICIPATORY PERTHE VIETNAM EXPERIENCE
- David Shand
- PEAM Seminar
- 24 May, 2001
2Why a Participatory PER?
- 1996 PER of good technical quality, not used by
GOV - various reasons including inter-ministry
rivalries - Vietnam a CDF pilot country
- Idea of a participatory PER seemed logical - and
strongly endorsed by World Bank Hanoi - But perceived as the first step in a lengthy
process - build ownership and capacity to do
their own PERs in future - Impact through dialogue, not just a report
3Obtaining Ownership by Government
- Agreement on scope and timing on PER
- Set out a continuous consultation process
- Everything to be translated into Vietnamese
- And stress the advantages to GOV
- And little to fear - no surprises
- Flexible, non-preaching approach by WB
- High standing of WB with GOV
- But WB and GOV agree to disagree if necessary
-
-
4Some Other Issues
- GOV will not be pushed around
- Apparently good results from public expenditures
- if it aint broke dont fix it - Government itself doesnt know what is going on -
and therefore isnt in full control - Shining light into dark corners - but focus on a
few key issues - sowing some ideas - Comparisons with other countries in the region
interest GOV - Other topics can be covered in later PER
-
5Involvement of Donor Community
- Key stakeholders in the PER - PER was A C-G
requirement - Key donors involved, UK, Netherlands, Denmark
- Provision of funding (242k of total PER spending
of 522K) - Interest in particular issues (Netherlands
gender, UK programmatic lending) -
6Involvement of Donor Community
- Regular consultation with key donors (but some
difficulty - one donor felt it was not consulted
closely enough) - General briefing meetings of all donors and NGOs
at the end of each mission - UNDP funding of capacity building
- Cooperation with IMF - Fiscal sustainability and
transparency chapter
7The Mechanisms and Theory of Consultation
- GOV a full partner to sign a joint report with
WB/International donor community - GOV counterpart committee of officials (MOF, MPI
and sectoral ministries) to work with PER team - Agreement on TOR and timing and provision of
information - WB consultants work with local consultants - to
improve quality and increase local capacity -
- Critical role of WB Hanoi Office in maintaining
the liaison
8The Mechanisms and Theory of Consultation
- GOV comment on draft chapters as they emerge
- WB held the pen
- Key role of WB Hanoi Office in maintaining
the liaison - But in reality there were some problems
- Some local counterparts not appropriate - only
from accounting/finance branch of the ministries - In some areas local consultants did not add value
or were not used - GOV decision - Initially some lack of cooperation by other
ministries - PER perceived as only a MOF exercise
9Chronology of the Participatory Approach
- October/November 1999 Preliminary mission
- Meeting with Vice-Minister of Finance
- Meetings with MOF, MPI and Sectoral Ministries
- Workshop on PER for senior officials
- Discussion of draft concept paper with GOV
- agreement on scope
- timetable and meeting information requirements -
consultants to provide these in advance to GOV -
10Chronology of the Participatory Approach
- January Main mission (two weeks)
- team of 12
- some work with local consultants
- visits to Quang Binh province
- workshop in HCMC
- End February/early March
- draft chapters provided to GOV
11Chronology of the Participatory Approach
- March 24 - April 4 Follow-up mission
- discussions with MOF, MPI and sectoral ministries
on draft chapters - sectoral workshops (some involving Vice
Ministers) and plenary workshops - first draft of report provided to GOV
12Chronology of the Participatory Approach
- Late April
- final draft report provided to GOV
- Mid May
- formal comments from MOF
- WB Hanoi line by line discussion with MOF
13Chronology of the Participatory Approach
- June Final mission to discuss PER report
- Agreement with MOF and submission to leadership
- June 23-23 C-G meeting in Vietnam
- GOV presents PER report to C-G
- September discussions on PER implementation and
follow-up
14Impact of a Participatory Approach
- On issues to be covered
- Agreement on
- Cross-cutting issues
- fiscal sustainability and transparency
- public expenditure management and public
investment processes - fiscal decentralization gender (Netherlands
interest, fees and contributions) - Sectoral issues agriculture, education, health,
transport, social safety nets (added later) - Issues not to be covered Civil Service Reform,
Corruption, Defense expenditure
15Impact of a Participatory Approach
- On timing and costs
- Lengthy consultations with GOV and number of
missions - As much emphasis on dialogue as on report
writing - Value added by GOV?
- Detailed study of all draft material, correction
of errors and elaboration of information, mainly
by MOF - MPI provided draft chapter on PIP
- Improved consistency and overall quality
- But not major changes or disagreements
- On tone of recommendations - not preaching
- An agenda of reform options,
- GOV should consider,
- were we tough enough?
16Follow-up
- Recommendations which are well specified
- Areas needing further work or study
- Areas not yet covered
- Consideration of T.A. needs
- Action Plan to guide follow up/implementation
17Follow-up
- MAIN MESSAGES IN THE REPORT
- Fiscal sustainability problems
- Overall reasonably good expenditure management
- but improvements needed in expenditure
prioritization capital/recurrent imbalance,
improve pro-poorness - and need to improve information flows, both
external and internal