Project Status Report - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Project Status Report

Description:

Linde cryoplant delivered (not tested) Q35s stripped down; coils tested ' ... Front end shielding disassembly. Re-establish shielding & create a 'door way' ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 10
Provided by: pdr3
Category:

less

Transcript and Presenter's Notes

Title: Project Status Report


1
Project Status Report
  • Project Achievements
  • Project Schedule
  • Financial Report
  • Issues

2
Visible Achievements
  • Target test!
  • Linac side stairs
  • Trench strengthened new access installed
  • Floor cleaned painted
  • Holes (almost) all drilled
  • Solenoid in hall
  • Linde cryoplant delivered (not tested)
  • Q35s stripped down coils tested
  • Cable Store ? MICE Local Control Room
  • Have ownership (PK coordinating)
  • ...
  • Many more invisible achievements ? need to be
    made real!

3
Project Schedule
  • Outline of work in the hall
  • Front end shielding disassembly
  • Re-establish shielding create a door way
  • Install concrete plinth rail system for
    solenoid
  • Installation commissioning of Linde Cryo-plant
  • Build of shielding and installation of beam line
  • Solenoid
  • Dipole 2
  • Quad triplets 2 3
  • Installation of beam line power supplies

4
Prerequisites
  • Shielding
  • Detailed shielding design has only just started
  • Delivery of first set of shielding blocks is
    booked
  • Need to organise cleaning prior to use
  • Some special pieces of steel may need to be
    ordered
  • Concrete plinth needs to be manufactured (dwg
    ready)... Ditto rail system
  • Solenoid
  • Vac test, MLI heat shield repair ...
  • Trolley modifications

5
Prerequisites/Issues
  • Dipole 2 Quad triplet stands
  • design underway at DL
  • Dipole 1 First triplets stands
  • Designs nearly ready for manufacture
  • Limited in space!
  • Resource issues
  • Mechanical Installation workforce is 2
  • Electrical may be ok (covered by RAL DL)

6
Further away
  • Magnetic Shielding Walls
  • MICE Plinth support structure
  • Diffuser!
  • ToF0 CKOV
  • ToF1
  • Spectrometer Tracker

7
Financial Status
  • Report to OSC (December)
  • By end October spend 3.7M
  • Represents ½ of project budget before WMC
  • 1M on non-staff costs
  • 2.4M on staff-cost (Budget 3.4M)
  • 140k on travel (Budget 200k)
  • PPRP OSC ?Cost 2 Completion
  • Current staff cost extrapolation
  • Likely to be significantly over budget
  • but good chance to be within CWM!
  • Material needs to be justified against original
    plans!

8
Issues
  • RF power system
  • completion of test stand in 2007
  • relationship with CERN phase 2
  • Travel!
  • Financial constraint!
  • Collaboration meeting!
  • Time penalty!

9
(No Transcript)