Title: Module%20IV:%20Financial%20Strategy%20Real%20Investments%20and%20Strategy
1Module IV Financial StrategyReal Investments
and Strategy
- Week 10 October 28 and 30, 2002
2Objectives
- Review investment criteria
- Introduce strategic investment concerns
- Real options
- First mover advantage
- Capital budgeting
- Reasons
- Relation to financing
- Leasing overview
3Real and Financial Assets
- A real asset is a long-lived tangible or
intangible good that produces a stream of income
over time - Examples Patents, equipment, brand loyalty,
etc. - A financial asset is a claim to a real asset or
its income stream - Examples Stocks, bonds, etc.
4Key Decisions
- There are two fundamental functions of a
financial manager - Capital Budgeting Identify real assets to
invest in and avoid those that do not create
value - Raising Capital Issue financial assets to
finance real investments - A firm is the link between financial markets and
goods markets
5The NPV and IRR Rules
- Three step procedure
- Estimate future expected cash flows using
accounting data and other sources - Compute a discount rate or target rate of return
- Calculate NPV or internal rate of return
- accept positive NPV projects (or projects with
internal rates of return above the target rate of
return) - reject negative NPV projects (or project with
IRRs below the target rate of return)
6Evaluation of IRR
- The internal rate of return is not the best
criterion for ranking projects. Why? - It suffers from possible mathematical problems
(non-uniqueness, non-existence) - There are problems in application (mutually
exclusive projects, borrowing v. lending issues).
- It also ignores the information contained in the
yield curve.
7Example
- Consider two mutually exclusive projects
- Project A involves an initial outlay of 5 and
repays 10 next year - Project B involves an initial outlay of 20 and
repays 30 next year - What is the IRR of project A? Project B? At a
10 discount rate, what would you do?
8Target Rate of Return
- Many corporations use a target rate of return or
cutoff rate to value projects - In many cases, the target rate is the firms
weighted-average cost of capital (WACC) - Firms entering new businesses or investing in new
strategies may be changing the firms risk from
levels assumed in a firm-wide WACC - Project risk or ? is the relevant risk
9WACC Can Lead To Errors
Discount Rate ()
Accept Bad Projects
WACC
Reject Good Projects
Project b
10Capital Rationing
- Capital rationing Two types
- Hard The firm cannot obtain outside capital to
fund all its positive NPV projects - This typically applies to small, growing firms
with high insider ownership where there may be
significant agency costs - Soft To control managers or to have balanced
divisional growth, a firm may limit the funds
available for project investment even if it can
raise funds from the capital markets
11Capital Rationing
- Seemingly obvious rules like NPV, IRR, etc fail
when there is capital rationing. - Some projects yield first-mover advantages and
may free up capital for use in other projects
later on, so just picking the highest NPV project
is not correct. - Rather, we have to consider combinations of
projects that maximize NPV.
12NPV versus Option Values
- NPV estimates normally compute present value of
expected future cash flows - Expected cash flows weight each possible outcome
with the probability of that outcome - Management decisions through time can prevent
some bad outcomes from occurring, e.g. by not
making necessary future cash investments
13Example NPV versus real option
- Simple example of NPV building a motel
- Cost is 9.7 million, and WACC is 10
- Value of future cash flows estimated now at
either 9 or 13 million with equal probability,
thus expected value of project cash flows in one
year now 11 million - NPV of motel project (in millions) is
14Example real option
- If we wait one year we can take advantage of
future information - If value turns out to be low, dont build
- If high, build motel
- Value in one year is either 0 or 13 million
- Revised value with option to postpone
- Option adds about .7 million to value
15Flexibility creates Real Options
- Management options
- Growth options
- Timing options
- Switching options
- Option to expand or contract (scale)
- Abandonment options
- Real options exist with respect to investment in
real resources - What are sources of value of real options?
16Management options
Contract
Switch
Wait
Expand
Grow
Currently Invested React to Bad News
Not Currently Invested
Currently Invested React to Good News
17Valuing Real Options
- All options have value, since we are not obliged
to use them - Seemingly unprofitable ventures may have positive
NPV when real options are considered - Use of Black-Scholes and other option pricing
techniques is used but option-pricing assumptions
may not be met
18Capital Rationing
- Capital rationing Two types
- Hard The firm cannot obtain outside capital to
fund all its positive NPV projects - This typically applies to small, growing firms
with high insider ownership where there may be
significant agency costs - Soft To control managers or to have balanced
divisional growth, a firm may limit the funds
available for project investment even if it can
raise funds from the capital markets
19Capital Rationing
- Seemingly obvious rules like NPV, IRR, etc fail
when there is capital rationing. - Some projects yield first-mover advantages and
may free up capital for use in other projects
later on, so just picking the highest NPV project
is not correct. - Rather, we have to consider combinations of
projects that maximize NPV.
20Strategic Concerns
- Strategic issues may substantially alter our
views of a project - These concerns cannot be easily quantified but
are critical - Two types of factors
- External
- Internal
21Strategy External Factors
- The External Environment
- Political
- Expropriation, war, trade policy, etc.
- Economic
- Currency devaluations, labor unrest, etc.
- Regulatory
- Rule changes, price controls, etc.
- Industry
- Growth, technology.
22Strategy Internal Factors
- Internal Factors
- Externalities with other divisions synergies
- Reaction of competitors
- Followers or aggressive competitors?
- Follow-up projects and options
- Managerial constraints and incentives
- Moral hazard, risk aversion, executive
compensation.
23Example Plant Capacity and Strategic
Interactions
- A firm faces a decreasing average cost curve
price is determined by world supply and demand. - Building a large plant is profitable at Q but
only if its competitors do not themselves expand
their plants, reducing output to Q - Project NPV depends on the reactions of
competitors
24Profits and Competitors Reactions
Average Cost Curve
Price
Quantity
25Investment/Financing Strategy
- If markets are efficient and there is no
corporate taxation (Modigliani-Miller
assumptions), firms should be able to finance all
positive NPV projects - Many departures from those assumptions
- Transactions costs
- Bankruptcy risk
- Tax differentials
- These departures lead to a link between financing
and investment strategies
26Leasing Overview
- Two basic type of leases
- Operating lease (use of asset over limited time)
- Capital or financial lease (acquire asset over
time from lessor) - Two basic considerations
- Accounting treatment on financial statements
- Tax treatment
- Treatments differ between accounting standards
and tax codes and lead to advantages to leasing
27Lessors
- Owner of real property or equipment leases to
users - Manufacturers of equipment lease equipment to
users, often as a form of financing - Development of third-party leases began when
investment tax credit (1964 to 1986) created
opportunity for non-operating firms like banks to
use tax credits by leasing equipment like
airplanes
28Third-party Leases
- Equity or leverage lease is determined by whether
asset is owned outright by lessor or partially
financed by debt - Synthetic lease creates a special purpose entity
(SPE, a legal entity) to hold assets - Assets are financed by a combination of debt and
equity - Asset ownership rights and cash flows
distributions are determined by lease terms
29Division of Cash Flows
- Cash flows from lessee to claimants on SPE are
divided into tranches (a French word meaning cut) - The ordering of the claim on cash flows (lease
payments) determines risk, with the A tranche
getting first claim, hence lowest risk - Other tranches have subordinated claims to cash
flows - A residual trance (lowest claim) is equity claim
30Guarantees to Lease Investors
- Principal and interest on debt issued by SPE can
be guaranteed by lessee - Typically occurs with A tranche of synthetic
lease - Use of corporate guarantee is on-credit,
meaning affects lessees credit rating through
claim on cash flows - Asset can be used as collateral for a tranche
- B tranche has claim on asset value in synthetic
lease
31Allocation of Risks
- Risks to investors in lease are
- Non-payment of interest and principal (Tranche A
and B) - Loss of investment capital in case of default
- Guarantee provides A-tranche investors recourse
to corporate sponsor for claims, thus must be
considered in credit rating - B-tranche investors have no recourse to
corporation but have collateral in form of title
to the underlying asset
32Summary
- Project evaluation sounds scientific, but it
often involves a considerable amount of artistry
in its application - In the real-world, many factors contribute to
complicate capital budgeting - While the tools and analytics are helpful, you
also need to consider strategic interactions of
projects and financing.
33Next Week Nov. 6 and 8, 2002
- Review financial planning and RWJ, Chapter 26 on
sustainable growth - Read and begin to prepare Clarkson Lumber as an
individual case write-up - Work with group to arrange schedule for working
on Avon Products case for week following