Title: James Webb Space Telescope Integrated Science Instrument Module Status
1James Webb Space TelescopeIntegrated Science
Instrument ModuleStatus
JWST-PRES-012901
Jamie Dunn JWST/ISIM Manager JWST Partners
Workshop May 19, 2009
2ISIM CDR
- Successfully conducted March 9-12 at GSFC
- Major findings
- Highly optimistic schedule which was not closing
at the time of CDR - Resolved with new LRD of June 2014
- SI flight deliveries not impacted by new LRD
- Observatory thermal issues
- NGAS/GSFC has chosen a set of minimally invasive
options which result in radiator thermal
performance margins above 50 - Options to further reduce IEC backloading are
still being explored - Identify responsible person for each critical
test - Ongoing, accomplished as part of test planning
- A total of 94 RFAs issued
- As of today
- 52 responses submitted to the originator
- Of those, 29 have been closed
3DRAFT
REV-H
DRAFT Rev H
05/14/09
As of 05/14/09
4Status and Recent Progress - ASICs
- Second flight run of ASICs is in process
- Teledyne is making excellent progress finalizing
the production details, and is working to a
schedule that supports deliveries to flight
instrument teams beginning this November - Pathfinder units begin assembly this week
- First flight article builds beginning in July
- Have determined that the minimum common mode
voltage requirement needs to be increased - Instrument teams notified, design modifications
are in process
5Status and Recent Progress NIRSpec Detectors
- Pathfinder Detector System testing is progressing
well - Delivery to ESA scheduled for mid-July
- Flight Detector System is awaiting delivery of
flight ASICs - Scheduled for mid-November, supporting a Flight
DS delivery of February 2010 - Evaluating options for ASIC common mode voltage
requirement change - Plan to implement on the flight FPE prior to
flight ASIC delivery - Have two high quality spare SCA candidates
in-hand - Selection agreement with ESA pending
8 Mpix HgCdTe Focal Plane Assembly
Focal Plane Assembly (FPA)
6Status and Recent Progress - Microshutters
- Flight Microshutter System integration is in
progress and on track for September delivery to
ESA - Selected flight arrays
- MCE boards in testing
- Final magnet motor deliveries from CDA imminent
- Final shock requirements agreed to with Mission
Systems - Plans envelope cryo and launch environments
- Qualification testing at Astrium to begin next
week
Microshutter Array
7Status and Recent Progress ISIM Harness Radiator
- Critical Design Review scheduled for June 15 at
GSFC - Had been postponed due to interface loads issues,
which have been resolved - Incorporation of a spherical bearing assembly
reduced loads and simplified integration with the
backplane - Most drawings complete and out for quote
- Working toward December delivery
8Status and Recent Progress Harness
- Have shipped over 150 harness assemblies in
support of - Instrument ETU and flight builds
- EGSE (SITS, etc)
- ISIM integration and test preparations
- Held a successful NIRSpec Detector Harness
Manufacturing Readiness Review on May 5, 2009 - Tayco has improved the application and control of
the potting where the cable meets the backshell
9Status and Recent Progress ICDH and IRSU
- ICDH ETU IT scheduled to complete in June
- Support of instrument thread testing and FSW
development will continue - Helping out GLORY
- Failure of their flight spacecraft computer
boards has jeopardized the January 2010 launch
date - JWST flight assets will be utilized, and can be
implemented in time to preserve GLORYs schedule - Resultant 3 month impact to ISIM ICDH can be
absorbed - IRSU Protoflight boards build in process
- Box level IT to begin in September
ICDH
IRSU
10Status and Recent Progress ISIM Software and
ITSS
- Flight Software
- Build IC11 testing to begin next month
- NIRSpec MSS FSW
- Began development of MSS C4.1 (final build)
- NIRSpec DS FSW has transitioned into
maintenance mode
- ITSS
- Focus is now shifting to
- Build and test of the Certification Lab at GSFC
for ISIM IT - Build and test of ISIM Electrical Simulators for
testbeds at Northrop Grumman - Continuing to support systems in the field in
maintenance mode - Continuing to support instrument interface
testing
11Status and Recent Progress ISIM Electronics
Compartment
The first cure cycle of the IEC shell is
complete. Co-cure inserts and final fiberglass
layer fabrication begins in the first week of
May. Inserts ready for installation
- Integration of the prototype baffle test unit
completed and the first unit is being tested.
12Status and Recent Progress ISIM Structure
Nearly Complete
- Flight Structure delivery on schedule for July!
Assy Sequence Left to Right, Top to Bottom
A
B
E
C
H
J
F
G
N (GE2070600)
K
L
M
13Status and Recent Progress ISIM Structure Deck M
14Status and Recent Progress ISIM Optics
- LOTS of work on test data sets in support of ISIM
cryo performance testing - Extensive analysis efforts in support of test
budgets, wavefront sensing, calibrations, stray
light, etc - Cryogenic metrology equipment/plans nearly
complete (photogrammetry, laser radar, MATF,
IATF, scale bars, etc) - Optics Summit scheduled for June 16-19 at the ECO
- Agenda/Objectives
- Update on ISIM optical alignment and verification
plan, flows, and test error budgets not
previously covered - Follow-up on actions from IOTA in 2008 and ISIM
CDR
Cryogenic metrology hardware
15Status and Recent Progress OSIM
- Ball components are completing assembly and most
Goddard components are in fabrication - Primary mirror scheduled for shipment next week
- Ball deliveries on target for end of June
- OSIM integration at GSFC will begin in July
Pupil Select Mechanism wheel
Alignment Diagnostics Module
16Status and Recent Progress OSIM
Primary Mirror Interferometric testing
Optical Bench Assembly
Fold Mirror 2 after coating
Fine Phase Plate after coating
17Status and Recent Progress MGSE
Lower GESHA
- SAMORAI
- Assembled and ready for proof testing
- Upper GESHA
- Assembled w/ spare h/w, ready for chem film
- Ship Date May, following ITP to GESHA mating
interface work
18Status and Recent Progress MGSE
Received March 24, 2009
Received March 24, 2009
- ISIM Support Stand Dolly (ISSD)
- Full assembly to be complete at GSFC
- (April 2009)
- ISIM Metrology Integration Stand (IMIS)
- Full assembly to be completed at GSFC
- (April 2009)
Dolly-to-Stand Kinematic Interface
3
2
1
19Status and Recent Progress Integration and Test
- Space Environment Simulator modifications are
complete, and helium shroud is undergoing
acceptance testing - Operations team lead by Debbie Ramey is focusing
on procedure development and pending instrument
ETU deliveries starting late summer - Beginning in June
- Internal transition to the GSFC IT complex
begins - Major MGSE build-up and integration space secured
8 Mpix HgCdTe Focal Plane Assembly
20ISIM Year Ahead
- In a year
- Flight ISIM Integration and Test begins!