James Webb Space Telescope Integrated Science Instrument Module Status - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

James Webb Space Telescope Integrated Science Instrument Module Status

Description:

Highly optimistic schedule which was not closing at the time of CDR ... Status and Recent Progress ISIM Electronics Compartment ... – PowerPoint PPT presentation

Number of Views:124
Avg rating:3.0/5.0
Slides: 21
Provided by: philsabelh
Learn more at: https://science.nasa.gov
Category:

less

Transcript and Presenter's Notes

Title: James Webb Space Telescope Integrated Science Instrument Module Status


1
James Webb Space TelescopeIntegrated Science
Instrument ModuleStatus
JWST-PRES-012901
Jamie Dunn JWST/ISIM Manager JWST Partners
Workshop May 19, 2009
2
ISIM CDR
  • Successfully conducted March 9-12 at GSFC
  • Major findings
  • Highly optimistic schedule which was not closing
    at the time of CDR
  • Resolved with new LRD of June 2014
  • SI flight deliveries not impacted by new LRD
  • Observatory thermal issues
  • NGAS/GSFC has chosen a set of minimally invasive
    options which result in radiator thermal
    performance margins above 50
  • Options to further reduce IEC backloading are
    still being explored
  • Identify responsible person for each critical
    test
  • Ongoing, accomplished as part of test planning
  • A total of 94 RFAs issued
  • As of today
  • 52 responses submitted to the originator
  • Of those, 29 have been closed

3
DRAFT
REV-H
DRAFT Rev H
05/14/09
As of 05/14/09
4
Status and Recent Progress - ASICs
  • Second flight run of ASICs is in process
  • Teledyne is making excellent progress finalizing
    the production details, and is working to a
    schedule that supports deliveries to flight
    instrument teams beginning this November
  • Pathfinder units begin assembly this week
  • First flight article builds beginning in July
  • Have determined that the minimum common mode
    voltage requirement needs to be increased
  • Instrument teams notified, design modifications
    are in process

5
Status and Recent Progress NIRSpec Detectors
  • Pathfinder Detector System testing is progressing
    well
  • Delivery to ESA scheduled for mid-July
  • Flight Detector System is awaiting delivery of
    flight ASICs
  • Scheduled for mid-November, supporting a Flight
    DS delivery of February 2010
  • Evaluating options for ASIC common mode voltage
    requirement change
  • Plan to implement on the flight FPE prior to
    flight ASIC delivery
  • Have two high quality spare SCA candidates
    in-hand
  • Selection agreement with ESA pending

8 Mpix HgCdTe Focal Plane Assembly
Focal Plane Assembly (FPA)
6
Status and Recent Progress - Microshutters
  • Flight Microshutter System integration is in
    progress and on track for September delivery to
    ESA
  • Selected flight arrays
  • MCE boards in testing
  • Final magnet motor deliveries from CDA imminent
  • Final shock requirements agreed to with Mission
    Systems
  • Plans envelope cryo and launch environments
  • Qualification testing at Astrium to begin next
    week

Microshutter Array
7
Status and Recent Progress ISIM Harness Radiator
  • Critical Design Review scheduled for June 15 at
    GSFC
  • Had been postponed due to interface loads issues,
    which have been resolved
  • Incorporation of a spherical bearing assembly
    reduced loads and simplified integration with the
    backplane
  • Most drawings complete and out for quote
  • Working toward December delivery

8
Status and Recent Progress Harness
  • Have shipped over 150 harness assemblies in
    support of
  • Instrument ETU and flight builds
  • EGSE (SITS, etc)
  • ISIM integration and test preparations
  • Held a successful NIRSpec Detector Harness
    Manufacturing Readiness Review on May 5, 2009
  • Tayco has improved the application and control of
    the potting where the cable meets the backshell

9
Status and Recent Progress ICDH and IRSU
  • ICDH ETU IT scheduled to complete in June
  • Support of instrument thread testing and FSW
    development will continue
  • Helping out GLORY
  • Failure of their flight spacecraft computer
    boards has jeopardized the January 2010 launch
    date
  • JWST flight assets will be utilized, and can be
    implemented in time to preserve GLORYs schedule
  • Resultant 3 month impact to ISIM ICDH can be
    absorbed
  • IRSU Protoflight boards build in process
  • Box level IT to begin in September

ICDH
IRSU
10
Status and Recent Progress ISIM Software and
ITSS
  • Flight Software
  • Build IC11 testing to begin next month
  • NIRSpec MSS FSW
  • Began development of MSS C4.1 (final build)
  • NIRSpec DS FSW has transitioned into
    maintenance mode
  • ITSS
  • Focus is now shifting to
  • Build and test of the Certification Lab at GSFC
    for ISIM IT
  • Build and test of ISIM Electrical Simulators for
    testbeds at Northrop Grumman
  • Continuing to support systems in the field in
    maintenance mode
  • Continuing to support instrument interface
    testing

11
Status and Recent Progress ISIM Electronics
Compartment
The first cure cycle of the IEC shell is
complete. Co-cure inserts and final fiberglass
layer fabrication begins in the first week of
May. Inserts ready for installation
  • Integration of the prototype baffle test unit
    completed and the first unit is being tested.

12
Status and Recent Progress ISIM Structure
Nearly Complete
  • Flight Structure delivery on schedule for July!

Assy Sequence Left to Right, Top to Bottom
A
B
E
C
H
J
F
G
N (GE2070600)
K
L
M
13
Status and Recent Progress ISIM Structure Deck M
14
Status and Recent Progress ISIM Optics
  • LOTS of work on test data sets in support of ISIM
    cryo performance testing
  • Extensive analysis efforts in support of test
    budgets, wavefront sensing, calibrations, stray
    light, etc
  • Cryogenic metrology equipment/plans nearly
    complete (photogrammetry, laser radar, MATF,
    IATF, scale bars, etc)
  • Optics Summit scheduled for June 16-19 at the ECO
  • Agenda/Objectives
  • Update on ISIM optical alignment and verification
    plan, flows, and test error budgets not
    previously covered
  • Follow-up on actions from IOTA in 2008 and ISIM
    CDR

Cryogenic metrology hardware
15
Status and Recent Progress OSIM
  • Ball components are completing assembly and most
    Goddard components are in fabrication
  • Primary mirror scheduled for shipment next week
  • Ball deliveries on target for end of June
  • OSIM integration at GSFC will begin in July

Pupil Select Mechanism wheel
Alignment Diagnostics Module
16
Status and Recent Progress OSIM
Primary Mirror Interferometric testing
Optical Bench Assembly
Fold Mirror 2 after coating
Fine Phase Plate after coating
17
Status and Recent Progress MGSE
Lower GESHA
  • SAMORAI
  • Assembled and ready for proof testing
  • Upper GESHA
  • Assembled w/ spare h/w, ready for chem film
  • Ship Date May, following ITP to GESHA mating
    interface work

18
Status and Recent Progress MGSE
Received March 24, 2009
Received March 24, 2009
  • ISIM Support Stand Dolly (ISSD)
  • Full assembly to be complete at GSFC
  • (April 2009)
  • ISIM Metrology Integration Stand (IMIS)
  • Full assembly to be completed at GSFC
  • (April 2009)

Dolly-to-Stand Kinematic Interface
3
2
1
19
Status and Recent Progress Integration and Test
  • Space Environment Simulator modifications are
    complete, and helium shroud is undergoing
    acceptance testing
  • Operations team lead by Debbie Ramey is focusing
    on procedure development and pending instrument
    ETU deliveries starting late summer
  • Beginning in June
  • Internal transition to the GSFC IT complex
    begins
  • Major MGSE build-up and integration space secured

8 Mpix HgCdTe Focal Plane Assembly
20
ISIM Year Ahead
  • In a year
  • Flight ISIM Integration and Test begins!