Transcript and Presenter's Notes

Title: Lake Como Rehabilitation City of Bloomer


1
Lake Como Rehabilitation City of Bloomer
  • Joseph M. Dorava, PE - Vierbicher Associates
  • Bloomer Community Lake Association and
  • Bloomer Rod and Gun Club Public Meeting
  • May 12, 2003

2
Lake Rehabilitation
  • Lake Bed Surveying
  • Lake Bed Dredging
  • Habitat Enhancement

3
Overall Status
  • Planning and Design, Where we are now
  • (Lake cross-sections and dredging volumes)
  • Permit Application, Where we are going (Dredging
    and Spoiling)
  • Construction, Where we end up
  • (Funding and Timing)

4
Planning and Design Background
  • Team Members - City, Vierbicher Associates, Lake
    Association, Local NGOs, Public
  • Construction Plans and Specs for Lake
    Rehabilitation Habitat Enhancement
  • Construction Contract

5
Planning and Design Status
  • Survey of Lake Complete
  • Preliminary Plans Complete
  • Issues (local input)
  • Storm sewer outfalls, Swimming beach, Boat
    launches. Sediment traps, Groundwater seeps,
    Fishing sites, Eroding sites, Wildlife site,
    etc.

6
Plan Sets
7
Plan Sets
8
Plan Sets
9
Plan Sets
10
Plan Sets
11
Plan Sets
12
Plan Sets
13
Permit Application Background
  • Team Members (City, Vierbicher Associates, Lake
    Association, WDNR, USACOE)
  • Environmental Assessment needed to describe and
    quantify (Dredging volumes, spoil site, aquatic
    and terrestrial habitat impacts)

14
Permit Application Status
  • Final lake rehabilitation plans needed for the
    application
  • Plans are in a preliminary stage
  • Issues, Access to spoil site, sediment
    quantity/quality, storm water runoff, erosion
    control, habitat impacts
  • Keep regulatory agencies informed and involved

15
Construction
  • Construction Contract Award
  • Construction Observation
  • Timing Seasonal (Winter)
  • Funding (Cost vs. Budget)

16
Next Steps
  • Plans revised to incorporate local input and
    habitat enhancements (May-June)
  • Permit Applications Completed (June - July)
  • Construction Bidding Documents Completed (July -
    August)
  • Bids and Budgets Aligned (Sept. - October)
  • Construction Contract Awarded (Oct -Nov)
  • Construction (Dec., 3003 - March, 2004)

17
Questions?