Title: Monday: Steel arrives and is unloaded
1Monday Steel arrives and is unloaded
2Monday Band room ceiling grid is well
underway
3Monday Science addition masonry within roof
work beyond
4Tuesday Ceiling grid and other ceiling
installations continue
5Tuesday Restroom floor finishes are underway
6Tuesday Media structure columns are being set
7Tuesday Media structure columns are being set
8Tuesday Science addition (existing area)
9Tuesday Drainage installation is put off due to
rain
10Tuesday Mechanical / Kitchen / Health addition
11Wednesday Media structure framing is underway
12Wednesday Band room (case work in boxes all
over floor)
13Wednesday Tile work in the auditorium restrooms
14Wednesday CMU wall construction in Science
Addition
15Wednesday Drainage work near administration
trailer
16Wednesday Exterior of Science Addition
17Thursday Band Room
18Thursday Chorus Room
19Thursday B-hall Restrooms
20Thursday Rear parking lot demolition
21Thursday Science Addition (existing area)
22Friday Morning Steel workers continue on media
framing
23Friday Morning Steel workers continue on media
framing
24Friday Morning Rear parking lot
25Friday Morning Rear parking lot
26Friday Morning Band Room
27Friday Morning Chorus Room
28Friday Morning Chorus Room
29Friday Morning B-Hall Restrooms Left Girls
Right Boys
30Friday Morning Roof work over old library
(science classrooms)