Title: NEW YORK CITY TRANSIT
1NEW YORK CITY TRANSITSCommunications-Based
Train Control Standard A Look at the Leaders
SystemGeoffrey P. HubbsNew York City
TransitEdwin A. MortlockParsons
Transportation Group April 5, 2000
2NYCTs CBTC Implementation
- Background
- Implementation Strategy
- Interoperability Objectives
- The Proposed System
- Milestones
- Innovations
- Conclusions
3Background
4Background
- NYCT subway system is one of the worlds largest
- Half of the signal system is more than 75 years
old - An extensive technology assessment conducted in
the early 90s concluded CBTC is the best way
forward for NYCT - 20 year implementation strategy
- A pilot system installation - Canarsie Line (L
Line) - Multiple sources of supply for the system
5CBTC System Benefits
- Operational
- Increase line capacity/minimise headways
- Permit greater flexibility and precision of
control - Safety
- Continuous ATP
- Protection of work crews
- RAM
- Redundancy and fault tolerance
- Remote diagnostics
- Reduction in trackside equipment
6Implementation Strategy
- System wide over a prolonged period (gt20 years)
- Subway system is a highly complex set of
interconnected lines - Flexibility of operation between lines is of
paramount importance - Interoperability standards to permit flexibility
at the same time as procuring from competitive
sources are key to success
7Pilot Project Procurement Strategy
Phase II, Install Pilot Line, Develop
Interoperability Specifications
One Lead Contractor
Six Proposals
Three Demonstrators
Two Follower Contractors
Phase III, Reengineer systems, demonstrate
interoperability through test
Shortlist Three
Select Lead (and standard)
Advertise RFP
8Background
The Canarsie L Line
9Canarsie Line CBTC Pilot Objectives
- A pilot project for future train control
- Establish new standards for future signal
modernization based on CBTC technology, to allow
future competitive procurement - Establish NYCT procedures and working practices
with new train control technology - Resignal the Canarsie Line on schedule and with
minimum disruption to revenue services
10Interoperability Specifications
- The establishment of a Standard for future CBTC
procurements is based upon a requirement for
future interoperability of separately procured
CBTC subsystems - The Leaders Interoperability Interface
Specification will become the key technical
component of future CBTC procurement
specifications
11Interoperability Specifications
- Draft interoperability specifications were
submitted by each Proposer during the Phase I
contract - Further interoperability specification updates
will be submitted by the Leader as Phase II
progresses and leads into Phase III - The future intent is for a black box approach to
subsystems, i.e., new trackside CBTC procurements
will be fully functional with adjacent CBTC
systems provided by other suppliers
12Interoperability Specifications
- All suppliers car equipment will work with all
suppliers wayside systems - Carborne equipment can be supplied as part of
future new car procurement (cars will be supplied
CBTC equipped) - The wayside systems will also interface fully
with the ATS system
13Interoperability Specifications
- Interoperability does not mean interchangeability
- Future CBTC procurements will result in multiple
spares holdings of both trackside and carborne
equipment
14Concept CBTC System Architecture
15Concept CBTC System Architecture
16Reasons to Choose the Leader
- Proven start up performance of the Meteor system
in Paris - Safety certification by independent agencies
- Superior availability, reliability, and
maintainability - Full support of mixed fleet operations
- Best understanding of interoperability objectives
and requirements
17Reasons to Choose the Leader
- High ratings of software development capabilities
- Overall performance throughout the various
components of Phase I
18CBTC System Description
- Operating Modes In CBTC Territory trains will
operate in - Automatic Train Operation ATO
- Automatic Train Protection Manual ATPM
- Auxiliary Wayside Protection AWP
- Yard
- Restricted Manual
- Bypass
19CBTC System Description
- Outside of CBTC territory CBTC equipped trains
will operate in Wayside Signal Protection mode
(WSP) - Train Operators drive according to signal aspects
- Onboard CBTC is in a dormant mode looking for
an entry indication to the next segment of CBTC
territory
20Proposed Matra System
- NYCT system is based on Paris Meteor Line with
some key differences - Meteor is unmanned, NYCT will have Train
Operators and Conductors - Radio links between train and wayside instead of
inductive loops - Meteor was a green field start, NYCT involves
major changes to existing rules and procedures - Canarsie Line services must continue during CBTC
construction, test and cutover
21Proposed Matra System
- Zone controllers are independent of adjacent
zones - Vital computers are based on single processor
platforms - Zone controllers determine safe limits of travel
(Movement Authority Limit - MAL) for each train - MAL transmitted to trains via RF network
- Zone controllers interface to conventional relay
based interlocking and wayside signal equipment
(AWS)
22Proposed Matra System
- Zones are divided into virtual blocks, sized to
meet headway and junction operational performance - Virtual block philosophy facilitates a mix of
equipped and unequipped train operation through
CBTC territory - Passive transponders are mounted between the
rails for position fixes - Carborne equipment also uses a mix of tachometer
and Doppler radar equipment for positioning
23Proposed Matra System
- Stand alone ATS being provided for Canarsie
will interface to other systems within a new Rail
Control Center - ATS remote workstations will also facilitate
control of the L Line from strategic points on
the line as well as providing real time
maintenance data to signals and car maintenance
centers
24Proposed Matra System
- ATS will
- Track and display train locations, train and car
identities, schedule information etc. - Provide computer aided dispatching including
automated routing, schedule adjustments through
dwell and performance level control
25Proposed Matra System
- An AWS subsystem is to be provided, integrated
with the zone controller and ATS subsystems - AWS provides home signals at interlockings and
track circuits throughout as a minimum - Some other wayside signals are being provided
where relatively close headway of unequipped
trains is needed
26Proposed Matra System
- RF data network will provide two way continuous
data communications between trains and wayside - 2.4 GHz Spread Spectrum transmission in the
unlicensed ISM band - Direct Sequence Spread Spectrum BPSK/DQPSK
- 2 Frequency channels allocated to every cell, all
frames transmitted successively at both
frequencies - Radio is different to that used in Phase I test
- Matra has tested this system extensively in Paris
Metro and elsewhere including NYCT
27Proposed Matra System
28Matra Proposed Wayside Architecture
Station PA/CIS
ATS
Zone Controller
AWS
Radio Data Network
Maintainers Panel
OBCU
Car Subsystems
Car Subsystems
OBCU
Track Equipment
Carborne
Carborne
Transponder
Transponder
29Matra Proposed Carborne Architecture
A Car
A Car
B Car
B Car
Radio Antenna
Radio Antenna
To Train Systems
To Train Systems
Interface/data com Equip
TO Display
TO Display
OBCUs
Unit Lines
Train Lines
Tachogenerators
Transponder Interrogator Antenna
Doppler Radar Units
30Wayside Signal Aspect
NEW CBTC ASPECT (FLASHING GREEN IN TOP HEAD) -
PROCEED ON CBTC INDICATIONS NON-EQUIPPED
TRAINS MUST STOP
A2 1567
N L24
31R143 Cars
- R143 Cars are being delivered CBTC
- Ready
32Contract Innovations
- Listen, listen, listen
- Partnering
- Between all parties, Contractor, Consultants, and
NYCT - Working Groups
- Established to cover critical topics and
subsystems - Led by the Systems Engineering Group, others have
been formed to help the contractor develop the
design in a no surprises atmosphere - Co-located Teams
33Key Milestones
- Award Phase II Contract
- Draft Interoperability Specs
- Complete CBTC/R143 Interface Design
- Award Phase III Contracts
- Complete System Design Review
- Complete Preliminary Engineering
12/1999 3/2000 4/2000 7/2000 7/2000 3/2001
34Key Milestones
- Preliminary Interoperability Specs
- Final Interoperability Specs
- Initial Shadow Mode Operation
- First Section of CBTC in Revenue
- Phases II and III Complete
4/2001 3/2003 10/2003 11/2003 12/2004
35Canarsie CBTC Project Summary
- Three years after design start, project is on
original schedule - Phase I demonstrations have helped to cement a
strong partnering relationship between previously
diverse NYCT departments - The development of interoperable standards for
New York and potentially other North American
properties remains a key goal and a reality
36Canarsie CBTC Project Summary
- The Phase I test results indicate that the
Contractor(s) and the selected technology can
perform - There is a very close watch on Canarsie by other
US transit properties - The industry wide standards resulting from this
pilot project will be applicable to many of these
properties
37Questions and Answers?
?