Description:

TV cable company. Sofia, July 15 2005 SEEFIRE workshop 4 ... TV cable company. telco operator. railway company. 1 provider is able to build DF first mile ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 11
Provided by: nvog5

less

Transcript and Presenter's Notes

Title: Fibre lease contracts CESNET experience


1
Fibre lease contracts (CESNET experience)
Lada Altmannová CESNET Czech Republic
2
Total length of inter-city dark fibres trend
1999?2005
  • 1999 232 km
  • 2002 1.000 km
  • 2005 4.200 km in total
  • 3.500 km in CESNET2 production network
  • 350km of single fibre
    within CESNET2
  • 700 km of fibre pair in CzechLight testbed

3
Contracts for dark fibres
  • 1999 1 provider
  • oil transit company
  • 2002 3 providers
  • oil transit company
  • power distribution company
  • TV cable company

4
Contracts for dark fibres cont.
  • 2003 5 providers
  • oil transit company
  • power distribution company
  • TV cable company
  • telco operator
  • railway company
  • 1 provider is able to build DF first mile
  • 2005 8 providers
  • the same as 2003 3 telco operators

5
(No Transcript)
6
Recommendations for procurement process of DF
  • Procure DF line including first miles to NREN PoP
  • Request proposal of conditions for in-line
    equipment housing
  • Request specifications of line parameters
  • Most important points for decision
  • Monthly price
  • DF length
  • Optical parameters (attenuation, chromatic
    dispersion, PMD)
  • Contracted period should depend on monthly price
    (if price is relatively high, prefer shorter
    period, before end of the period re-procure)

7
Recommendations for the contract
  • DF availability 99.7 monthly or better
  • features of fibres should be according to
    relevant standards (geometrical, optical,
    mechanical)
  • acceptance procedure with a protocol of
    measurement
  • - provider covers the cost of measurement
  • guaranteed free testing period for NREN
  • if not observe the terms, a discount from monthly
    payment

8
Recommendations of discounts
  • If delay of line delivery is 7 days or more, then
  • the discount is 0.5 from monthly payment per
    day
  • If trouble removal time is longer than 12 hours
    then the discount is 0.15 from monthly payment
    per hour
  • If monthly availability of line is e.g. 99.7 and
    the availability is lower then the discount can
    be up to 100 of monthly payment

9
Prices of DF intercity leasing for CESNET
  • 0.1 0.5 Euro/m/y pair of fibres (fibre
    lengths from 30 km to 323 km)
  • 0.3 Euro/m/y one fibre (fibre lengths from 34
    km to 126 km)
  • Best prices are for DF between big cities for
    long distances

10