Title: A Vision for Transmission: COMPETITION
1A Vision for Transmission COMPETITION
- Massachusetts Restructuring Roundtable
- Boston, MA
- November 16, 2001
- José A. Rotger
- Manager, Regulatory Strategy
2Is Transmission a Competitive Business?
- Historically, not treated as a business at all
- Generation and transmission planned together
- New transmission driven by generation plans
- Inter-area links for reliability ONLY, not
economic efficiency trade must maintain
self-sufficiency - But, industry restructuring has changed role for
transmission gt economic trade - New transmission competes against new generation,
demand-side measures, distributed generation, etc.
3Problems with Conventional Wisdom
- Undermined by new technology
- More modular, less lumpy gt changes economics
- Far less environmental/community impact gt
affects siting - Undermined by new regulatory structure
- Allows incentives inherent in restructured
electricity markets to be applied to transmission
investment - Recognize that transmission competes with other
solutions (G, DG, DSM) to meet customer needs - Owners bear risks, rewards of investments gt No
stranded cost risk
4Framework for Market-Based Transmission
- Bid-based markets
- Security-Constrained Economic Dispatch
- Locational Wholesale Prices
- Preferably nodal
- Tradeable Financial Transmission Rights
- Supporters of transmission expansions receive
FTRs - Term of FTRs should be as long as possible
- PJM, NYISO have this framework in place
- ISO-NE, Ontario IMO to follow
5Benefits of Market-Based Transmission
- Benefits to the environment
- More transmission gt more markets for cleaner
energy - Deployment of advanced technologies with much
lower impacts - Benefits to the community
- More underground transmission (faster permitting)
- Eminent domain not needed by market providers
- Benefits to consumers
- The right investments in the right place at the
right time - Protection from stranded costs
- Efficient competition among all sources of
delivered energy will lower costs to consumers
6Current Issues in Transmission
- Does a monopoly transco serve the best interests
of consumers? - Transco will be a market participant because it
will affect market outcomes - How will merchant transmission fit in?
- How will the RTO conduct transmission planning?
- Will the transmission planning expansion
process focus on reliability or economic needs? - Will the incumbents control the process?
- Do we need a regional/national approach to siting?
7RTOs Market-Based Transmission What is needed?
- Defined marketable property rights
- Supporters of transmission expansions receive
Financial Transmission Rights (FTRs) that can
then be monetized via RTO - Free entry by entrepreneurial transmission
companies - No de jure or de facto monopoly over new
transmission - Level competition between new entrants
incumbents - Equal opportunity for new entrants to compete for
new transmission investments regulated or
market-driven - RTO planning function Maintain reliability
- Planning serves as backstop for market failure,
not preempt it - Threat of socialized investments undermines
market alternatives - Allow greatest competition among all alternatives
8The Alternatives
- Status quo Gridlock in grid investment
- Endless debate about net benefits of project
who will pay - No mechanism to address links between markets
- Monopoly transmission company (ITC)
- One transmission company
- Operates under incentive rates
- Responsible for all congestion, losses,
reliability - Makes unilateral investment operating decisions
to maximize profit - But, regulator must guess at correct incentive
rates - Why not let market set marginal transmission
rates? - Strong central planning by RTO
- Requires crystal ball, and consumers bear risk of
imperfect planning foresight
9So, how do we get there?
- Dont fall prey to commonly held myths regarding
transmission expansion - Our Top 10 myths
10Top 10 Myths About Grid Expansion
No. 10 Transmission is and will remain a
natural monopoly
- Fact
- True for grid operation, but NOT for additions
and expansions - With LMP and tradeable property rights, G, T,
DSM, etc. all compete to meet new energy needs - Free rider problems, economies of scale
arguments are being resolved by technology
11Top 10 Myths About Grid Expansion
No. 9 Free riders restrict market-based
transmission investment
- Fact
- New controllable technologies address free
riders only users pay (HVDC, FACTS) - FTRs discourage free riders and provide vehicle
for investment recovery only users pay - The combination of risk aversion (bankruptcy)
and well-designed energy markets (with
volatility) prevents or eliminates free riders
(woe to the unhedged)
12Top 10 Myths About Grid Expansion
No. 8 Economies of scale (lumpiness)
restrict market-based transmission investment
- Fact
- New controllable technologies are smaller and
more modular (HVDC, FACTS) - Modularity preserves options
- Grid capacity can match market demand
- Generation has residual economies of scale
(even with GTs), but few worries of market
failures
13Top 10 Myths About Grid Expansion
No. 7 Need eminent domain and other state
police powers to site transmission
- Fact
- New cables are smaller and easier to place
underground (HVDC Light) in existing ROWs
(railroads, highways, pipelines, etc., just like
fiber optic cables) - New point source and converter devices allow
capacity to be increased in existing substations - Siting regulations/statutes changed to reflect
merchant generation why not transmission?
14Top 10 Myths About Grid Expansion
No. 6 Transmission takes too long to build
need to pre-approve projects
- Fact
- New transmission technologies can approximate
project schedule for generation (e.g. 2-3 years) - If RTO-sponsored transmission is pre-approved,
generators will locate at sending end of planned
upgrades (and what is the future of distributed
generation?)
15Top 10 Myths About Grid Expansion
No. 5 Transmission is only 5-6 of total cost
why bother?
- Fact
- Marginal cost of transmission much higher than
average cost (10x? 20x?) - Congestion charges visible under LMP/FTR
frameworks N.E. Mass Boston congestion costs
5/99-7/00 80 million - To achieve efficiency, get prices right at the
margin - or generators in remote locations will push RTO
to expand grid
16Top 10 Myths About Grid Expansion
No. 4 Why not over-build transmission the
benefits outweigh any efficiency losses
- Fact
- Must build to eliminate congestion (at any
cost) why bother with LMPs and FTRs? Let this
market structure work! - Why saddle captive customers with uneconomic
transmission investments? (think nuclear) - Must build to mitigate market power there
are cheaper and better ways (behavioral
solutions) - Must build to improve liquidity at what
price?
17Top 10 Myths About Grid Expansion
No. 3 Only a central planning process can
efficiently reduce congestion
- Fact
- Backstop role for reliability-driven upgrades,
but NOT for economic upgrades - Why forfeit the competition benefits of new
entrants? - Central planners are destined to be wrong and
the burden is on captive customers, NOT
shareholders - Central planners may be biased and may NOT be
sufficiently independent - Any residual central planning requires complete
independence and a competitive solicitation
process
18Top 10 Myths About Grid Expansion
No. 2 We need incentive rates (PBR) to build
new transmission
- Fact
- Why not rely on market-based CMS -- LMPs and
FTRs? Let this market structure work! - Why do we need incentive rates for the existing
wires in order to build new ones? - Price caps (RPI X) With LMPs FTRs in
place, why pre-determine and lock in productivity
improvements (X)? Why not let the market set X?
19and the Number One Myth about Grid Expansion is
20Top 10 Myths About Grid Expansion
No. 1 Market-based transmission cannot be
financed or built on basis of market rights
- Fact
- The US (and other nations) have implemented the
market structure (LBMPs FTRs) necessary for
market-based transmission investments - Let the markets work!
- TEUS is actively building transmission in USA
and Australia on a fully market basis over
1,200 MW of in service and proposed projects (
more to come)
21Our Solution
- Over 500 million in market-driven projects
- Australia
- Directlink 180 MW, 65 km u/g DC Operation
- Murraylink 220 MW, 180 km u/g DC Construction
- Southernlink 150 MW existing lines
upgrade Permitting - United States
- Cross Sound 330 MW, 40 km subsea DC Permitting
- Final permit may be issued by December gt
operational by summer 2002 - Lake Erie Link 325-975 MW, 120 km DC Permitting
- Harbor Cable 330-990 MW u/g subsea
Development - Other competitors NU (CLIC), Neptune, GenPower
22Final Thoughts
- Market-based solutions are a reality
- Technology is changing the industry
- Trust, but verify
- Markets can and do work!
- But, ensure that the right structures are in
place to allow full and fair competition
23For more information
- Our web sites
- US www.transenergieus.com
- CSC www.crosssoundcable.com
- Australia www.transenergie.com.au
- Contact information
- Jeff Donahue (508) 870-9900 x105
jeff.donahue_at_transenergieus.com - Ray Coxe (508) 870-9900 x106
ray.coxe_at_transenergieus.com - José Rotger (508) 870-9900 x108
jose.rotger_at_transenergieus.com