Operations meeting on FY07 Shutdown - PowerPoint PPT Presentation

About This Presentation
Title:

Operations meeting on FY07 Shutdown

Description:

... know who will be working in the Facility, and on what, every week. ... If anyone is ever in doubt about how to perform a task, please contact Bob, Bill, ... – PowerPoint PPT presentation

Number of Views:17
Avg rating:3.0/5.0
Slides: 6
Provided by: chri2
Learn more at: https://www.star.bnl.gov
Category:

less

Transcript and Presenter's Notes

Title: Operations meeting on FY07 Shutdown


1
Operations meeting on FY07 Shutdown Date June
27, 2007. W.B. Christie
  • Outline
  • Brief Overview of Shutdown Plan
  • Details/discussion of next few weeks
  • Comments on Working at the STAR site

2
  • June 27-July2 Remove Shield Wall (3.5 days,
    Riggers)
  • June 27 July 2 Remove Vacuum pipe spool
    pieces.
  • July 3 Pull East Poletip
  • July 5 Pull West Poletip. Install scaffolding
    EW. (Charlie Steve)
  • June 27 July 13 Remove SVT RDOs, extender
    cables, and cabling back to the Racks. Remove
    EEMC Trigger Cables.
  • June 27 July 18 Install Rollers and disconnect
    utilities, and roll STAR to AB and connect
    utilities.
  • July 20 Aug. 24 EEMC electronics maintenance.
  • July 19 27 Install SVT platform, FTPC West
    platform, and disconnect end of cone cables,
    remove FTPCs, and extract cone to platform.
  • July 30 Aug. 14 Remove SSD, SVT, all
    utilities on cone, and reassemble cone.
  • Aug. 1 15 Install new BEMC PMT comm./controls
    system.
  • Aug. 16-21 Reinstall cone, reinstall FTPCs,
    remove rails. Remove installation platform.
  • Aug. 22 27 Disconnect utilities.
  • Aug. 28 - 29 Roll STAR back into IR.
  • Aug. 30 Sept. 10 Install Utilities.

Draft STAR Shutdown Schedule/Plan
July 2007
August 2007
Summer Sunday
3
September 2007
  • Sept. 6 18 Beam Pipe Bakeout
  • Sept. 11th STAR in IR with utilities connected.
  • Sept. 11 Oct. 12 TPC Electronics maintenance.
  • October 1st TOF Trays arrive at BNL for
    installation.
  • Oct. 15 18 SGIS Certification.
  • Oct. 17th West Poletip installed.
  • Oct. 24 East Poletip installed.
  • Oct. 25 30 Magnet testing.
  • Nov. 1st Collider Cooldown Begins.
  • Nov. 1 2 Install BBCs.
  • Nov. 7th Lose access to IR for Collider
    Commissioning.
  • Still Open
  • When/where best to install TOF trays? Best
    locations 2, 4, 7, 1000.
  • Details/plan for the TOF water system?

October 2007
Collider Cooldown Begins
4
June
Dates/Tasks 27th Install Hydraulic sys.
Pressure gauges 28th Remove BBCs, remove VPDs,
start on EEMC Trigger cable removal. 29th Start
Vacuum pipe spool pieces removal (East first),
continue EEMC effort.
July
Dates/Tasks 2nd Start removal of Shield wall.
Continues till Thursday noon. - Start removal
of TPC pipes/utilities - removal of Magnet water
lines, and blow out coils 3rd Continue TPC
utilities removal (finish?) - Start West SVT RDO
removal (?) 5/6th Remove East Poletip 9th
17th Pull West Poletip, Remove SVT RDOs, drop
all water/gas/power connections, install Hillman
Rollers, Remove stairs and Bridge for move. 18th
Planned date for Rolling STAR to AB.
5
General Comments on Work in the STAR Facility
  • Work Planning
  • N.B. All work undergoes Work Planning. Most of
    this is whats known as Worker Planned work.
    Before you start on a task think about what
    youre going to do, how youre going to do it,
    what the hazards are, and how youll minimize
    these possible Hazards.
  • As a General rule, Bob or Bill should always
    know who will be working in the Facility, and on
    what, every week. Please make every effort to
    keep us informed.
  • Safety
  • - All work should be performed in compliance
    with Safety rules. If there is a conflict between
    schedule and Safety, Safety must take precedence
    in all cases.
  • - If anyone is ever in doubt about how to
    perform a task, please contact Bob, Bill, or
    both.
  • - In the course of accomplishing your tasks
    throughout the Shutdown, if anything becomes
    apparent on how we could work safer, please bring
    them to Bill or Bobs attention.
  • - If you see anyone doing something that
    appears unsafe, or somehow incorrect, please
    bring it to Bob or Bills attention.
  • Housekeeping
  • - In performing work in the STAR Facility please
    clean up after yourself at the end of each day.
    Examples are picking up cable tie remnants, paper
    from Label makers, misc. litter that results
    from your work.
Write a Comment
User Comments (0)
About PowerShow.com