Title: Stabilizing%20Slides%20%20Using%20a%20Spider%20Excavator
1Stabilizing Slides Using a Spider Excavator
Eric L Kay Rob Wilson
2Stabilizing Slides
Part 1 - Spider Excavator, (the tool) Part 2 -
Landslide Headscarps Part 3 - Multiflow
Drainpipe Part 4 - Contour Drainage
Eric
Eric
Rob
Rob
3Kaiser X5 M
.
Part 1 - Spider Excavator Description
J
.. .
4Hydraulic thumb
Pushes and pulls itself around
Work on steep slopes 100 (One to One slope)
Extending stick
Twist wrist bucket
Walks on 4 legs
Hydraulic winch 12,000lbs
Rolls on two back wheels
Kaiser X5 M
Optional Hydrostatic drive (6kmph)
5Agility
Step over
- Logs
- Shrubs
- Small trees
Schaeff HS 40 D
- Boulders
6Safely work on a 1 to 1 slope
Kaiser X5 M
7 Previously deactivated road system
site accessibility
Schaeff 41 M
8Perched material in the gully
Schaeff 41 M
Beyond the reach of a normal excavator
9The power of an excavator 1 1/2 times the size
Schaeff HS 40 D
10Schaeff HS 40 D
Working in water 2 meters deep
11Transportable by Helicopter For remote site work
Fueled and ready to work
12Part 2 - Landslide Headscarps
13- Retrogressive Failures
- Maintenance problems
- Destruction of remedial works
- Loss of productive land inventory
14Unstable headscarp
15Kaiser X5 M
16Large woody debris
Kaiser X5 M
17 Caution ? ? ? ? ? Need good understanding of
soils, water and slope processes
18Part 3 - Multiflow Drainpipe
19Multiflow pipe Available in 15,30 46 cm widths
Made up of multiple miniature Big O pipes laid
flat, joined together and covered in a filter
fabric
A viable alternative for Drain rock
20Part 4 - Contour Drainage
21This site is located in the Cariboo Mountains
where a hanging glacial valley slopes into a
typical U shaped glacial valley.
Glacial fluvial out-wash deposits are buried
below glacial till, resulting in seepage related
slope instability problems.
22A road cut slide, with retrogression of the
headscarp and an ongoing maintenance problem.
23The Spider Excavator digs a trench above the
crest of the headscarp
The base of the trench should slope at least 2
towards an outlet end of the drainage.
24The multiflow drainage composite was put into the
bottom of the trench, against the uphill slope,
and a 6 mil polyethylene sheet against the down
slope side.
25The multiflow drainage composite was put into the
bottom of the trench, against the uphill slope,
and a 6 mil polyethylene sheet against the down
slope side.
Alternatively a composite Blanket Drain
material such as Nudrain DM50 could be employed
Excavator starts backfilling the trench. Woody
debris is then scattered over top
26Excavator starts backfilling the trench. Woody
debris is then scattered over top
275 liters/min X 60 min/hr X 24 hrs day
7200 liters/day Thats over 7000 kg less weight
on a day to day basis! What difference does a
month or two make?
Steady seepage from subsurface drainage
collector (Multiflow)
28Finished swale above head scarp with debris
scattered over top. (Picture has been stretched
to emphasize the swale)
29Finished drainage swale directing surface run-off
along flank of slide area
30Stable cut slope with reduced seepage after
finishing the contour drainage work.
31Thank You
Eric Kay - Rob Wilson
32References Kaiser X5 M - JOHOE Inc Joe Gisler
250 398-3507 Schaeff HS 40 D - Nu Creek
Developments Len Masson 250 833-0173 Schaeff HS
41 M - J W Berry Trucking Brad Berry 250
724-4912 Rob Wilson - Weldwood - 250
392-7731 Eric L Kay - Kay Associates -
250 337-5096