STATUS%20OF%20GSA%20NORTHERN%20BORDER%20PROJECTS - PowerPoint PPT Presentation

About This Presentation
Title:

STATUS%20OF%20GSA%20NORTHERN%20BORDER%20PROJECTS

Description:

Detroit, MI (Ambassador Bridge Cargo) Projects under construction. Champlain, NY (Phase 3) ... Alexandria Bay, NY. Coburn Gore, ME. Beebe Plain, VT ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 37
Provided by: thet7
Learn more at: http://www.thetbwg.org
Category:

less

Transcript and Presenter's Notes

Title: STATUS%20OF%20GSA%20NORTHERN%20BORDER%20PROJECTS


1
STATUS OF GSA NORTHERN BORDER PROJECTS
  • Ralph Scalise
  • Program Coordinator
  • Northern Border Program
  • October 24, 2007

2
Discussion Overview
  • Projects recently Completed
  • Champlain, NY (Phase 2)
  • Detroit, MI (Ambassador Bridge Cargo)
  • Projects under construction
  • Champlain, NY (Phase 3)
  • Massena, NY
  • Blaine, WA (Peace Arch)
  • Construction starts planned in 2008
  • Calais, ME (new international crossing)
  • Jackman, ME
  • Warroad, MN
  • Portal, ND
  • Out year projects (2009-2010)

3
Completed Projects
  • Champlain, New York (Cargo Facility)
  • Total Project Cost
  • 38,831,000
  • Construction Completed
  • 12/14/2006

4
Completed Projects
  • AMBASSADOR BRIDGE (Cargo Facility)
  • Estimated Total Project Cost
  • 34,857,000
  • Construction Start
  • Commenced 11/07/2005
  • Construction Complete
  • 09/06/2007

5
(No Transcript)
6
(No Transcript)
7
ONGOING CONSTRUCTION
  • CHAMPLAIN, NEW YORK (Phase 3)
  • Estimated Total Project Cost
  • 52,510,000
  • Construction Start
  • Commenced 4/26/2006
  • Estimated Construction Completion
  • 3/02/2009

8
(No Transcript)
9
(No Transcript)
10
ONGOING CONSTRUCTION
  • MASSENA, NEW YORK
  • Estimated Total Project Cost
  • 58,888,000
  • Construction Start
  • Commenced 7/03/2007
  • Estimated Construction Completion
  • 10/25/2009

11
ONGOING CONSTRUCTION
  • PEACE ARCH, WASHINGTON
  • Estimated Total Project Cost
  • 56,346,000
  • Construction Commenced
  • 08/31/2007
  • Estimated Construction Completion
  • 9/30/2009

12
(No Transcript)
13
(No Transcript)
14
2008 CONSTRUCTION
  • CALAIS, MAINE
  • Estimated Total Project Cost
  • 53,415,000
  • Estimated Construction Award
  • December 2007
  • Estimated Construction Completion
  • July 2007

15
(No Transcript)
16
2008 CONSTRUCTION
  • JACKMAN, MAINE
  • Estimated Total Project Cost
  • 30,562,000
  • Estimated Construction Award
  • 11/15/2007
  • Estimated Construction Completion
  • 01/29/2010

17
(No Transcript)
18
2008 CONSTRUCTION
  • WARROAD, MINNESOTA
  • Estimated Total Project Cost
  • 45,465,000
  • Construction Start
  • 8/16/2008
  • Estimated Construction Completion
  • 12/31/2010

19
(No Transcript)
20
(No Transcript)
21
2008 CONSTRUCTION
  • PORTAL, NORTH DAKOTA
  • Estimated Total Project Cost
  • 24,552,000
  • Construction Start
  • 2/25/2008
  • Estimated Construction Completion
  • 09/01/2011

22
(No Transcript)
23
Out Year Projects
  • Derby Line, VT
  • Richford, VT
  • Madawaska, ME
  • Alexandria Bay, NY
  • Coburn Gore, ME
  • Beebe Plain, VT
  • International Falls, MN
  • Dunseith, ND
  • Porthill, ID
  • Sumas, WA
  • 2009 Construction
  • 2009 Design
  • 2010 Construction
  • 2010 Construction
  • 2010 Design
  • 2010 Design
  • 2010 Design
  • 2010 Design
  • 2010 Design
  • 2010 Design

24
Derby Line, VT
25
(No Transcript)
26
(No Transcript)
27
Alexandria Bay, NY
28
Thousand Islands, NY
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
Questions?
  • Thank You
  • Ralph.scalise_at_gsa.gov
  • (617) 565-5821
Write a Comment
User Comments (0)
About PowerShow.com