Title: City of Washington Hurricane Isabel Response
1City of WashingtonHurricane Isabel Response
2Advance Preparations
- Prior to 8 a.m.
- Thursday,
- September 18
3Advance Preparations (Prior to 8 a.m. on 9/18)
- Management team, departments discuss
- Staffing (City contracted resources)
- Meals lodging
- Operations Support (supplies, call center)
- Alternative facilities (Police, Fire)
- Facilities, parks equipment preparation
- Public infrastructure preparation (ditches clear,
water tanks full) - Preparations for FEMA reimbursement
- Public information
4Advance Preparations (Prior to 8 a.m. on 9/18)
- Coordinate with other agencies
- Beaufort County Emergency Operations Center
- ElectriCities
- Large electric customers
5Operations During the Storm
- Starting 8 a.m.
- Thursday
- September 18
6Operations During the Storm (Starting at 8 a.m.
9/18)
- Maintain services (outage repair, public safety,
operations) in field until winds reach 50 mph to
protect employees, equipment - For public safety, de-energize electric circuits
near waterfront - Resume services in the field when winds drop to
below 50 mph - Jacks Creek Pumping Station monitored to protect
equipment in case of power outage
7Operations During the Storm (Starting at 8 a.m.
9/18)
- Debris cleared from streets to maintain emergency
vehicle access - Wells, wastewater lift stations use generators
for back-up power - Information distributed to public
8Operations After the Storm
- After midnight
- Friday
- September 19
9Operations After the Storm (After midnight 9/19)
- Normal staffing, operations resume when need for
emergency response passes - Heavy call volume continues at Utilities
Operations Center - Storm Debris clean-up begins (daylight hours)
- City parks
- Residential pick-up
10Operations After the Storm (After midnight 9/19)
- Equipment, facilities repairs begin
- Wastewater treatment adjusted to handle higher
inflow due to stormwater - Information distributed to the public
- FEMA reimbursement preparations
11Lessons Learned
- Post
- Incident
- Assessment
- What Went Well
12Lessons Learned What Worked Well
- Suspending/limiting outdoor activities when
sustained winds reached 50 mph - Maintains safety of personnel and equipment
- Coordinating City and county operations through
use of the County Emergency Operations Center - Assigning City staff or officials to County
Emergency Operations Center
13Lessons Learned What Worked Well
- Bringing in contracted electric line crews prior
to storm to be on site as soon as needed - Aggressive tree-trimming program for preventive
maintenance - Completed Hazard Mitigation Projects (elevation,
acquisitions) reduced chance of flooded
structures - Scheduling warehouse staff worked in shifts
14Lessons Learned What Worked Well
- Public acknowledged the fact they received their
power back in a timely manner - Public expressed appreciation for live voice at
the Utilities Customer Call Center - Field personnel knew what to expect with meal
preparations and schedule
15Lessons Learned
- Post
- Incident
- Assessment
- What
- We Need
- To Work On
16Lessons Learned Issues, Concerns, Things To Work
On
- Limiting outdoor operations
- Consider citywide policy on limiting outdoor
operations when sustained winds reach 50 mph - Identify consistent means to determine wind speed
- Sources wastewater plant, water plant, airport,
news media - Evaluate effectiveness, accuracy of telemetry now
in use
17Lessons Learned Issues, Concerns, Things To Work
On
- Staffing Staff Support
- Assign personnel from other departments to assist
Fire-Rescue-EMS in meal preparations, cooking - Expand amount of time utilities call center is
staffed (during storm as well as longer during
response period) - Address short-term storage of large quantities of
perishable food at Fire Station - Make advance arrangements for distributing
leftover food - Address staff rest and relief, stress management
18Lessons Learned Issues, Concerns, Things To Work
On
- Operations Logistics, Support Issues
- In General
- Recognize that differences in each storm may
require different means of preparation, response - Assign separate radio frequencies for Public
Works and Electric operations
19Lessons Learned Issues, Concerns, Things To Work
On
- Operations Logistics, Support Issues
- Public Safety
- Consolidate 9-1-1 dispatching for Police and
Fire-Rescue-EMS - Fire-Rescue-EMS had to develop two emergency
plans for remaining at or vacating fire station - Develop policy/procedure on responding to
transformer or power line fires
20Lessons Learned Issues, Concerns, Things To Work
On
- Operations Logistics, Support Issues
- Electric
- Evaluate de-energizing waterfront electric grid
remotely - Use of contracted crews limited by availability
of staff to guide crews around system, service
area - Assess equipment needs for Electric Line Crews,
such as mounted spotlights to aid in visual
inspections at night
21Lessons Learned Issues, Concerns, Things To Work
On
- Operations Logistics, Support Issues
- Public Works
- Consider options for electric generator at Jacks
Creek to maintain pumping ability at all times
(new culverts will not help until river level
drops) - Purchasing Supply
- Evaluate need for policy on issuing City
supplies, such as rain suits and flashlights, to
contracted workers
22Lessons Learned Issues, Concerns, Things To Work
On
- Response management and oversight
- Pursue installation of an electric generator at
Municipal Building to retain municipal operations - Extend length (starting and stopping) of State of
Emergency - Establish system to deter price gouging,
unscrupulous outside contractors
23Lessons Learned Issues, Concerns, Things To Work
On
- Traffic control
- Barricade Main Street at Bridge Street and other
flood-prone areas (Park Drive area) to deter
sightseers, vehicle traffic - Develop methods to keep public at safe distance
from Electric Line Crews work areas
24Lessons Learned Issues, Concerns, Things To Work
On
- Traffic control
- For safety reasons (i.e. floating vehicles),
consider having a tow truck on standby to tow
vehicles from flood-prone areas - Heavy vehicle traffic interfered with relocation
of generators to wastewater lift stations during
the eye of the storm
25Lessons Learned Issues, Concerns, Things To Work
On
- Information gathering sharing
- Develop means for assessing power outage status,
such as an electronic map that could show when a
circuit is out - Provide information to assist Customer Call
Center staff in fielding caller inquiries - Script with responses to frequently asked
questions - Status reports on area outages, updated regularly
- Evaluate use of GIS system in storm status and
response
26Lessons Learned Issues, Concerns, Things To Work
On
- Information gathering sharing
- Evaluate use of existing utility customer records
in supporting electric emergency response efforts
(locating customers, poles, transformers, etc.) - Assess internal communications needs between
departments - Investigate use of text pagers as a
communications tool - Improve information flow of relevant information
from City to County EOC (power outage status,
street status)
27Lessons Learned Issues, Concerns, Things To Work
On
- Public Education and Information
- Conduct storm preparedness public education
campaign at start of hurricane season - Educate customers with medical concerns about
making advance provisions for power outages
during storms - Retain ability to access internet, email and
Government Access Channel for communications and
information during storm (i.e. wireless
connection fiber optic connection of City
facilities)
28Lessons Learned Issues, Concerns, Things To Work
On
- Staff training
- Implement annual training for hurricane
preparation and response - Train staff to assist Communications Services
during storm period - Train customer call center staff in advance on
procedures, information needed for the
dispatcher, electric operations, handling abusive
callers, etc. - Provide training in proper use of communications
radio
29Lessons Learned Issues, Concerns, Things To Work
On
- Utilities Operations Center
- Command Dispatch Center
- Assign a Communications/Operations Manager to
track and direct activities and resources in the
field - Update information on customers with medical
needs - Update electric system maps
- Assign supervisor for call center staff
30Lessons Learned Issues, Concerns, Things To Work
On
- Utilities Customer Call Center
- Establish procedure for sharing information at
shift changes - Fine-tune staffing (length of shifts, scheduling
relief personnel, when to open and close call
center) - Manage noise in call center environment
31Lessons Learned Issues, Concerns, Things To Work
On
- Continuing Needs
- Water Resources
- All 30 wastewater lift stations are required by
state law to be equipped with electric generators
at a cost of approximately 20,000 each - By end of 2003-2004, City will have approximately
½ of lift station generators in place
32Lessons Learned Issues, Concerns, Things To Work
On
- Continuing Needs
- Water Resources
- Research availability of pump motors with larger
hoods to prevent future damage during hurricane
due to water entering the housing (2 motors
ruined during Isabel) - Public Safety
- New and/or improved facilities
33Outcome/Statistics
- 8,000 of 12,000 electric customers were without
power at some point during storm - 95 restored by Saturday evening
- Washington spared projected 10-foot tidal surge.
Actual surge was 6 ½ - 7 feet above sea level,
and only a couple of streets were flooded. - Streets clear of flood water by 4 a.m. 9/19
34Outcome/Statistics
- Storm debris cleanup completed Oct. 3 estimated
7,000-8,000 cubic yards collected - No reports from public of flooded residences
- Generator loaned to neighboring city once
Washingtons power restored - FEMA has declared eligibility for reimbursement
for storm expenses
35City of WashingtonHurricane Isabel Response