Title: City of Greencastle Flood Protection Plan
1City of GreencastleFlood Protection Plan
Presented by, United Geotech, LTD
2Introduction
- Team Overview
- Project Overview
- Design Requirements
- Project Approach
- Final Design
- Questions
3Team Overview
- Sarah Bireley Project Manager
- Amee Wicks Project Engineer
- Brad Pickering Project Engineer
- Troy Cunat Project Engineer
4Project Overview
- Greencastle Water Treatment Plant
- Located in Greencastle, Indiana south of Big
Walnut Creek - Six wells provide 4,000 gpm peak
- Serves population of 10,000
- Site subject to flooding
- Located in the flood plain
- Rains on Labor Day flooded site
5Project Overview (cont.)
Big Walnut Creek
Well field
Lagoon
Filter Facility
US-231
6Project Overview (cont.)
Taken September 16, 2003
Taken September 2, 2003
7Design Requirements
- Confirm finished floor elevation of filter
facility - Confirm base flood elevation
- Investigate flood protection options
- Investigate security options
- Deliverables
- Proposal
- Progress report
- Final report
8Project Approach
- Site assessment
- Codes and regulations
- Research design options
- Flood protection
- Security
- Choose final design
- Complete final design
9Site Assessment
- Topographic map
- Finished floor elevation 688.54 feet (MSL)
Big Walnut Creek
Lagoon
Filter Facility
10Site Assessment (cont.)
- Watershed area obtained
- 216 mi2
- Determined base flood elevation
- Obtained Big Walnut Creek topographic map
- 100-year flow determined
- Q 21,400 cfs
- Maximum flows used in HEC-RAS to determine base
flood elevation - 690.0 feet (MSL)
11Site Assessment (cont.)
12Site Assessment (cont.)
Finished floor elevation
Low head dam
13Codes and Regulations
- Cannot raise base flood elevation more than 0.15
feet - Water tower must be enclosed in fence
- Maximum levee side slope of 12.5
- No levee construction restrictions
14Design Options
Levee under construction
Floodwall under construction
15Design Options (cont.)
- Flood control options (cont.)
Dry floodproofing
Elevated structure
16Design Options (cont.)
- Decision based on four criteria
- Initial cost
- Lifespan
- Maintenance
- Constructability
Initial Cost (35) Lifespan (35) Maintenance (20) Constructability (20) Overall
Levee 4 4 3 2 3.6
Floodproofing 5 1 5 4 3.5
Floodwall 2 4 3 4 3.1
Building Relocation 1 5 5 1 3.2
17Levee Design
- Obtained soil borings performed tests
B6
B5
B3
B2
B4
B1
- Clay (CH), silt (MH), and sand (SW) present
- Suitable for levee
18Levee Design (cont.)
Lagoon Expansion
Filter Facility
19Levee Design (cont.)
20Seepage Analysis
- Used SefDam to calculate seepage
Elev. 692
Elev. 690
13
Section Permeability (ft/s) Height (ft) Width (ft) Seepage (ft3/s/ft)
A-A 3 x 10-10 5 28 6.494 x 10-11
B-B 3 x 10-10 6.5 35.5 1.238 x 10-10
C-C 3 x 10-10 13 68 4.578 x 10-10
D-D 3 x 10-10 12 63 4.005 x 10-10
E-E 3 x 10-10 11.25 59.5 3.639 x 10-10
- Total seepage is 0.0244 ft3/day
21Slope Stability
22Slope Stability (cont.)
- XSTABL utilized to analyze slope stability
- Eroding slope improved by Greencastle
- Additional load from levee analyzed
- Additional load does not cause failure
-
23Security
- Fencing, lighting, and cameras investigated
- Lighting and cameras may be added in future
Initial Cost (30) Lifespan (30) Maintenance (20) Protection (20) Overall
Chain Link Fence with Barbed Wire 1 4 5 5 3.8
Color Weatherproof Camera 5 2 4 1 3.0
Infrared Sensor Lights 5 1 5 3 3.5
24Security (cont.)
Filter Facility
25Cost
- R.S. Means Manual used to estimate costs
- Levee
- 71,500
- Security
- 24,000
- Total cost
- 95,500
-
26Conclusion
- Flood levels warrant need for flood protection
- Levee chosen as protection option
- Seepage and slope stability not a problem
- Fencing with barbed wire chosen for security
- Cameras and lighting may be added
- Total cost of 95,500
- Levee - 71,500
- Security - 24,000
27