Title: Energy Efficient Design
1Energy Efficient Design
Energy Efficient Design
Presented by Ken Bruton BE MEngSc MIEI
Presented by Ken Bruton BE MEngSc MIEI
2My Background
- RPS Energy Team in Cork
- SEI SME Advisor
- Provide Energy consultancy support to large
industry - Implement IS393 Energy Management Systems
- Six Sigma Green Belt
- Sit on the SEI working group on Energy Efficient
Design (EED) - Currently writing an EED guideline methodology
document for large industry
3Why is EED not utilised extensively?
- Tight budgets and schedules
- Extra design time required
- More emphasis placed on reducing capital costs
rather than reducing subsequent operational costs - Possible legal ramifications
4Why undertake EED?
- Savings potential far higher at design stage
- Lower project capital operating Costs
5EED MethodologyConcept
- Work from the Energy service out
- Challenge design standards
- Select integrated efficient system choices
- Optimise Control strategies to minimise energy
use - Maximise component efficiencies
- Maintain system efficiently through commissioning
and operation - Validate savings through efficient MT
6EED MethodologyProject Organisational Structure
7EED Key IndividualsEnergy Sponsor
- Imperative to the success of the EED process
- Must have senior management commitment to remove
barriers to success - Ensures EED methodology followed for the duration
of the project by all project participants
8EED Key Individuals Energy Co-ordinator
- Critical to EED process
- Independent Reviewer outside of project
constraints - Must be knowledgeable of all engineering
disciplines - Challenges energy service requirements
- Lifetime costs each opportunity for energy
efficiency improvement - Identifies new technologies which could be
utilised in place of standard solutions - Must be involved from initial design stages for
most effect but can carry out an EED review at
any project stage using the 3-step approach
9EED Methodology3 Step Approach
- Calculate Energy Baseline
- Calculate the project Energy Baseline at the
earliest design phase possible in order to focus
EED resources on significant energy using areas - Analyse
- Challenge the Proposed Design and develop a
prioritised Energy Savings Register of
Opportunities based on the significant energy
using areas - Agree Implement
- Agree which items on the Energy Savings Register
should be carried forward into the next phase of
the design process for implementation
10EED MethodologyStep 1 Project Energy Baseline
- Formulate an energy baseline of the project based
on the information available at the earliest
design phase possible - This aids in the identification of the
significant energy using areas of the project - Focus EED efforts on these areas for most effect
11EED MethodologyStep 2 Analyse
- Challenge energy service requirements and system
integration of these significant energy using
areas - Compile a list of energy saving opportunities
- Calculate the before and after EED operational
costs associated with these opportunities - Prioritise opportunities for progression based on
economic, environmental or company specific
requirements
12EED MethodologyStep 3 Agree Implement
- Project Team should agree on the energy saving
opportunities progressed to the next stage of
design - If barriers to this agreement are met within the
project team, the energy co-ordinator should have
access to senior management via the investor
energy sponsor to progress relevant items - Opportunities progressed from one design stage to
the next should require a change control to
remove them from the project scope. - Energy Efficient User Requirement Specification
should be furnished to prospective suppliers
13Supplier URS
- Extremely important document as it instructs
project suppliers/contractors in the EED
requirements of the project - This document should specify standards used by
design team - It should also specify the minimum requirements
of the project in terms of - Rating of motors to be utilised in building
services - Minimum lighting efficiency in terms of
lumens/watt - Temperature/humidity requirements of a space
- Minimum Boiler Efficiency
- Control strategy incorporated etc.
14Concept/Basic Design PhaseTypical EED Actions
- Challenge Energy Service Requirements
- Consider project holistically
- Calculate operational costs over lifecycle of
project - Investigate opportunities for heat recovery and
system integration - Tailor control strategy to end user requirements
- Facilitate the setback of systems in line with
production patterns
15Detail Design PhaseTypical EED Actions
- Improve the efficiency of each system component
- Reduce energy waste
16Tendering and Construction PhaseTypical EED
Actions
- EED Project team must be vigilant of
- Value engineering energy efficiency improvements
off the project - Product substitutions due to cost/lead time
- Reducing Costs/Staying on Schedule
- Energy Co-ordinator review imperative at each
stage of project
17Operational PhaseTypical EED Actions
- Utilise effective MT as a means to validate and
maintain project performance - Ensure system users are aware of performance
parameters
18Engineering Tools for EED
- Needs Analysis
- Six Sigma
- Pinch Analysis
- Financial Analysis Tools
- Value Engineering etc.
19Key Points
- Achieving client buy in can prove difficult
- Energy Champion support for Energy Co-ordinator
key to success of EED project - SEI Working group on EED to publish guideline
document early 2009
20Thank You
- Ken Bruton BE MEngSc MIEI
- Ken.Bruton_at_rpsgroup.com