Title: Risk Assessment Contingency Endgame
1Risk AssessmentContingencyEndgame
- John N. Galayda Director of LCLS Construction
- March 30, 2009
2Risks
- Technical
- Injector through undulator system, risks are
understood and controlled - Electron beam systems performing well
- X-Ray systems construction complete
- Thoroughly tested functionality prior to delivery
- Risks associated with damage to optics
- Attenuator, sacrificial test coupons, spare
mirrors - Early ongoing testing of B4C damage threshold
3Risks
- Schedule
- Attempting to advance the schedule for AMO
experiments compared to baseline schedule - Accelerate commissioning of upstream hardware
- Accelerate installation
- Not a concern for CD-4
- Hutch construction schedule is on critical path
to CD-4, with 108 days float to CD-4 - Space renovation schedule has less float, 83 days
float to CD-4 - Schedule for contingency allocation
- Get bids for space renovation by end of April
4Risks
- Cost
- Overruns late in the project
- Perform a bottoms-up cost estimate on all
remaining work (Nov08) - Perform monthly EAC and contingency analysis
- FEE AMO installation
- Perform a readiness review
- Monitor detailed installation planning schedule
- Owner-directed changes (hutches)
- Perform cost estimates at 30, 60 90
- Design-to-cost A/E contract
- Space renovation
- Scope of re-habilitation of Bldgs 28 750 is
controllable - GMAX for new space
5Risks
- Cost
- Change orders for TCCo subs are largely
negotiated - 600K return on allowances
- 200K unused field change order BA
- Claims (4.6M) still the biggest risk
- Accruals for claims have been established and
subjected to external review - Enact endgame plans for construction budget
- Revise accruals when new information is obtained
- FEH Hutches Todays presentation
- Space renovation is last major CF cost driver
6Risks
- Safety
- New work planning process
- LCLS personnel are experienced and well-trained
- New civil construction contractors onsite
- LCLS experience, lessons learned
- X-ray commissioning
- Readiness Process
7January Contingency Analysis
8Scope Restoration Candidates
9LCLS End-Game Timeline
Design LCLS Office Space w/Options
OPA Review (DC)
Turner Punchlist Done
CD-4 (7/31/2010)
Turner Constr Comp
Award LCLS Office Space
now
Construct LCLS Office Space
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
N
A
S
O
2008
2009
2010
ETC Complete w/SXR
Construct H4 H5
H4 H5 BO
1st Light in FEH
Design H4, H5 H6
X-Rays in NEH
1st Light in FEE
Award H4 H5 H6 TBD
Timeline allows endgame scope decisions to be
made sequentially. Final scope contingency
(space renovation) includes options.
10Decision Timeline
11(No Transcript)
12(No Transcript)
13(No Transcript)
14Normalized phase space centroid jitter after BC1
(4 of rms beam size)
RMS AyN 3.4
RMS AxN 3.9
Stability is not so far from the goal (10)
1-s beam size
D. Ratner
near end of linac (10-15 of rms beam size)
RMS AxN 14
RMS AyN 9
DE/E jitter ? 0.03 DQ/Q jitter ? 1.5
Q 0.25 nC
15Measuring Bunch Arrival Time Jitter
e-
S-band (2856 MHz)
BPM
V(t)
Q 0.25 nC
slope -2.34 mm/deg
Now measure BPM jitter both with transverse RF
OFF, and then ON (at constant phase)
Timing Jitter (w.r.t. RF) (110 mm)/(2.34
mm/deg) 0.047 deg ? 46 fsec rms
16Other Commissioning Results
- Measured effect of
- vacuum chamber
- wake fields- good
- agreement with
- predictions
17Trajectory is Straight Enough for 1.5 Angstom
18Diagnostics Working Well
- 3 nanoradian kick easily discerned
- Submicron motion of electrons easily discerned
19Predicted X-Ray FEL power, computed from electron
beam properties
20Measurements and Simulations for 20-pC Bunch at
14 GeV
Photo-diode signal on OTR screen after BC2 shows
minimum compression at L2-linac phase of -34.5
deg.
PRELIMINARY
Y. Ding
1.5 Å, 3.6?1011 photons Ipk 4.8 kA ge ? 0.4 µm
Horizontal projected emittance measured at 10
GeV, after BC2, using 4 wire-scanners.
LCLS FEL simulation at 1.5 Å based on measured
injector beam and Elegant tracking, with CSR, at
20 pC.
2120-pC Bunch at 4.3 GeV, 15 Angstrom Approaches a
Longitudinally Coherent Single Spike
z 25 m
(power profile at z 25 m varies from shot to
shot due to noisy startup)
Y. Ding
15 Å, z 25 m, 2.4?1011 photons, Ipk 2.6
kA, ge ? 0.4 µm
1.2 fs
LCLS FEL simulation at 15 Å based on measured
injector beam and Elegant tracking, with CSR, at
20 pC.
22(No Transcript)