Title: Auditorium
1Auditorium Cloud ceiling and lights are
installed scaffolding has been removed wood
flooring subcontractor is reviewing the existing
wood floor condition and is making recommendations
2Auditorium Some electrical demolition has been
taking place intermittently
3E-wing as seen early in the week
4E-wing Roof demolition in progress Thursday and
Friday on the wood framed hip roof
5E-wing Interior wall tile demolition in progress
6E-wing Interior wall tile demolition complete in
the same area as the previous photo
7E-Wing
8E-Wing Room C38 (Arch numbering) Pallets of VCT
are being stored until installation
9Work continues after school hours on the
Auditorium entranceway
10Trees and mulch in the planters make for a nice
appearance out front
11Trees and mulch in the planters make for a nice
appearance out front
12Landscaping and seeding past the last trailer on
the East side
13Tree planting near the auxiliary gym
14Hydro-seeding on Tuesday
15Facing Northside Middle
16Science Addition Landscaping
17East Courtyard Grass is coming up
18Media Courtyard Facing the back of the library
19Media Center / Library New cushioned wooden
chairs arrived this week
20Media Courtyard Facing the back hallway entry
21Outdoor dining 9-11-08
22Receiving Hallway New masonry wall and door
have been installed
23Mobile Classrooms are being broken down and
readied for transport
24Mobile Classrooms are being broken down and
readied for transport
25Mobile Classrooms are being broken down and
readied for transport
26Wrestling room Drywall work where a section of
wall was replaced
27Wrestling room Being used for storage while the
lower level gets epoxy floors installed
28Football locker room Being occupied as needed
29Fitness room 1 Epoxy floor installation in
progress
30Primer coat was applied in the hallway
31Locker room Flooring in progress / New lockers
are installed
32Flooring installation at the entrance to Girls
PE office and Laundry room
33Storage room access through Fitness Room 2 New
doors and frame installation in progress Ceiling
grid is substantially complete
34Electrical switch gear demolition finishes up in
the old boiler room