Title: Rehabilitation of 24th Street in Ogden, UT
1Rehabilitation of 24th Street in Ogden, UT
2Introduction
- State or Local Transportation Agencies when faced
with deciding what to do with deteriorated
Portland Cement Concrete Pavements (PCCP)
typically have two choices
- 1. Replace with new PCCP.
- 2. Rehabilitate with a Hot Mix Asphalt (HMA)
Overlay.
3Rehabilitation Techniques
- Place thick (4 inches) HMA overlays.
- Use a stress absorbing membrane interlayer
between the PCCP and the HMA overlay. - Place nonwoven geotech fabrics between the PCCP
and the HMA overlay. - Use woven geotech fabrics or geo-grid material
between the PCCP and the HMA overlay. - Crack Seat PCCP and place HMA overlay.
- Rubblize PCCP and place HMA overlay.
4Conventional Practice Requires Moderate to
severe distresses to be repaired full depth or
replaced prior to construction
Patch Deterioration
D-Cracking
Transverse Joint Spalling
From SHRP P-338 Distress Manual
5Factors Affecting Rehab Treatment Performance
- Existing condition of the PCCP.
- Construction Procedures.
- Weather Conditions.
- Traffic Loading.
6The Problem Reflective Cracking
Before
Conventional HMA Overlay6 months later
7Strata Reflective Crack Relief System (RCRS)
offers new approach
8Strata Reflective Crack Relief System (RCRS)
- Developed by Koch Pavement Solutions to address
the problem of reflective cracking in HMA
overlays when placed over PCCP . - RCRS consists of a highly elastic, impermeable
hot mix interlayer coupled with an elastomer
modified HMA overlay. - HMA overlay is designed to be compatible with the
interlayer as well as meet the demands of local
traffic. - Interlayer is composed of a premium
polymer-modified asphalt binder at a high asphalt
content in a dense fine aggregate mixture.
9Strata Reflective Crack Relief System (RCRS)
Cont.
- Performance-based specification is used to design
the mix and is certified using the Flexural Beam
Fatigue (AASHTO TP-8) Test. - Elastomer Modified PG binder at 98 reliability
is specified in the HMA overlay. - Both the interlayer and the overlay are placed
with conventional lay down equipment.
10Strata Reflective Crack Relief System (RCRS)
1124th Street Existing Pavement Condition
12GPS Survey Used to Define Locations of Existing
Pavement Distresses
13Distress Location Reference System A Street to
B Street (Control Section)
14Lineal Feet of Cracking in Control Section
15Distress Location Reference SystemB Street to C
Street (Test Section)
16Lineal Feet of Cracking in Control Test Sections
17Pavement Design
- Pavement Design Objectives
- Provide structural capacity for 20 years
- Minimize reflective cracking.
- Work within budget and profile constraints.
- Projected traffic loadings
- 3 million ESALs for 10 year design period.
- 7 million ESALs for 20 year design period.
18Pavement Design
- Pavement Layer Thicknesses
- Hot Mix Asphalt Overlay
- Plant Mix Seal Coat 30 mm
- Hot Mix Asphalt 80 mm
- Stress absorbing membrane (Strata Reflective
Crack Treatment 1 nominal) - Rotomill 120 mm below final pavement surface at
centerline to provide a 2 percent cross slope.
19Pavement Design
- Lane Widening
- Material Thicknesses
- Plant Mix Seal Coat 30 mm
- Hot Mix Asphalt 150 mm
- Untreated Base Coarse 180 mm
- Granular Borrow 300 mm
- AASHTO SN 4.4
20Pavement Design Information
21Typical Cross Section Control Section
22Typical Section DetailsTest Sections
23Design Performance Based Specs Hveem Stability
- Resistance to Rutting During Construction
- 18.0 minimum Hveem Stability
24Interlayer Materials Specifications
- Liquid AC Binder
- Performance Graded (PG) to meet service
conditions. - Elastic Recovery 45 min. _at_ 25 degrees C
- Separation 6 degrees C max. after 48 hrs.
(ASTM-5976)
- Fine Aggregate Requirements
- Sand equivalency 45
- Crushed Natural Sand
Gradation Sieve Passing 3/8 inch
(9.5 mm) 100 No. 4 (4.75 mm) 80 100 No.
8 (2.36 mm) 60 85 No. 16 (1.18 mm) 40
70 No. 30 (600 mm) 25 55 No. 50 (300 mm)
15 35 No. 100 (150 mm) 8 20 No. 200 (75
mm) 6 14
25Design Volumetrics Specifications
Criteria for 9.5mm mixture, medium traffic.
26Performance Based Design Specs AASHTO TP 8
Flexural Beam Fatigue
- Interlayers resistance to repeated bending
- Data of cycles to failure
- loss of strength
- Test simulates PCC joint movement
27Design Performance Based Specs Fatigue
- Flexural Beam Fatigue Device, AASHTO TP-8
- Tests mixs ability to withstand repeated bending
- Data number of loading cycles to failure (loss
of strength) - Run at 10x typical strain (deformation) to
simulate PCC joint movement
28Performance Based Spec Highly Crack Resistant
AASHTO TP-8, at test temperatureTest temperature
determined by project climate
29Pavement Mix Design Procedure Results
- Strata interlayer exceeded the performance based
specification minimum requirement of 100,000
cycles at 2000 microstrain (??) using the
Flexural Beam Fatigue (AASHTO TP-8) Test. - Strata interlayer mix used on this project
exceeded 200,000 cycles. - Strata interlayer had Hveem Stabilometer value of
20.8.
30Construction Specifications
- Specified temperatures
- Mixing 320 to 340 F
- Laydown 300 to 320 F
- Compaction 290 to 310 F
- Density 96 min. of Max. Specific Gravity -Gmm
- Test strip required
- Surface preparation
- QC on mix binder required.
31Rehabilitation Work
- Rehabilitation work began with widening of 24th
Street and adding new curb and gutter and
sidewalks on both sides of the street. - Existing pavement was milled to provide a uniform
cross slope of two percent (2). This resulted
in varying depths of the existing old HMA overlay
left in place. - During construction, traffic was diverted to the
westbound lane while the eastbound lane was
milled. Construction process was reversed and
westbound lanes were milled with traffic diverted
to the eastbound lanes.
32Rehabilitation Work Cont.
- HMA leveling course was placed on the milled
surface of the test section to provide a uniform
surface for the placement of the RCRS interlayer
and the new pavement. - Leveling course extended from the West end of
the project to station B-4 on the east. - Leveling course extended 12 feet on either side
of the street centerline with a nominal depth of
one half inch (0.5) to three-fourths inch
(0.75).
33Construction Widening Process
34HMA Leveling Course - East-Bound Lane
35Construction of Pavement Interlayer
- After preparation of the existing pavement, the
Strata RCRS was placed with a conventional HMA
laydown machine.
36Placement of Strata Interlayer
37Density Testing/Temperature Measurement
38Strata Reflective Crack Relief System (RCRS)
39Interlayer after Five Days Traffic
Strata Interlayer is designed to take traffic for
several days before overlay is placed.
40Laydown of HMA Overlay
- Conventional
- Laydown
- Equipment.
- Asphalt Cement
- in overlay selected to
- give 98 reliability
- using LTPP Binder
- Selection Procedure.
4124th Street after Placement of Open Graded
Asphalt Friction Course
42Performance Evaluation Plan
- Document Existing Pavement Conditions
- Map All Pavement Distresses Locations
- Conduct Bi-annual Pavement Condition Surveys.
- Monitor and Document Traffic Conditions Yearly.
43Data Collection
- Extensive pavement condition data was collected
to assess and document the original street
condition after milling. This information
includes - A base map of the new roadway alignment.
- A map of existing pavement cracks.
- Core samples taken at five locations after the
Strata interlayer and before the HMA overlay and
Plant Mix Seal were constructed. - Field notes and photographs taken during
construction.
44GPS Monitoring Process
45Base Map
- The base map was produced by the Utah T2 Center
using Global Positioning System (GPS) technology - Map shows the new curb line of the roadway.
- Condition of the street was recorded by mapping
the cracks in the existing pavement after the
surface had been milled and before the level-up
course was placed. - A line was surveyed for every major transverse
crack, longitudinal crack, block cracking, and
utility cut. - In addition, a point feature was taken for each
pothole found in the existing pavement.
46Additional Information Collected
- The following additional information was
collected for each distress type to determine
its location, extent, and severity - A letter coding system was used to identify each
type of distress and its location within each
section. - Distress type.
- Date information collected.
- Crack width.
- The pavement area affected by spalling,
secondary cracking, fatigue, etc.) - A digital photograph of every crack
47Distress Map (Control Section)
48Distress Map (Test Section)
49Transverse Cracking
50Pothole
51Utility Cut
52Core Samples
- Before overlaying the Strata with the HMA, five
(5) core samples were extracted and tested by
Granite Construction. - Stratas average specific gravity in the cores
was 2.285 with a standard deviation of 0.043. - Average percent compaction was 96.4 with a
standard deviation of 1.8. - Core number three was significantly thinner than
the other cores and had a lower density. This is
likely due to damage sustained during coring and
extraction.
53Core Samples
5424th Street, Ogden, UtahConstructed in 2002
Strata treatment
Surface before Strata treatment
55Condition Survey and Surface Evaluation
- Periodic condition surveys surface evaluations
will be made to determine the effectiveness of
the Strata system in delaying reflective cracks.
- Original condition of the pavement has been
assessed by mapping the cracks in the original
surface of the street. - Bi-annual surface condition surveys will be
conducted and will include mapping any new cracks
that appear using the same GPS technology so
that any reflective cracking can be determined.
56 Condition Survey Surface Evaluation
- Future distress maps will be compared to the
original condition map to assess whether new
cracks are due to reflective cracking through the
Strata system. - Information such as the location of the crack,
type of distress, date, width of the crack, and
the width of pavement affected by the crack will
be collected for each new crack. - A digital picture of every new crack will be
taken. Any deformation or abnormality of the
pavement will be noted and a digital photograph
will be taken of the location. - A pavement condition survey using the Utah T2
Centers T2_RMP Pavement Management Program will
be conducted to assess surface condition and the
added service life the Strata system provides to
the street.
57Traffic Evaluation
- Annual Average Daily Traffic information will be
acquired from Utah DOT to monitor traffic
loadings and changes in traffic conditions. -
- A report will be prepared at the end of each
yearly evaluation, summarizing evaluation
findings and recommendations for future
evaluations.
58Conclusion
- 1. The problem of reflective cracking in HMA
overlays on Portland cement pavements is a
problem faced by many transportation agencies.
The continual development and testing of new
technologies will help find a solution to this
problem. - 2. Performance monitoring of the rehabilitation
work on 24th Street should provide information as
to the effectiveness of the Strata Reflective
Crack Relief System to prevent reflective
cracking in HMA overlays of deteriorated PCCP.
59Results of Pavement Condition Surveys One Year
After Construction.(November 14, 2003)
- Following pictures show current condition of
control section and test sections
60Pavement Condition After One Year of
Service(Control Section)
61Pavement Condition After One Year of
Service(Test Section B to C)
62Pavement Condition After One Year of
Service(Test Section C to D)
63Pavement Condition After One Year of
Service(Test Section D to E)
64Pavement Condition After One Year of
Service(Test Section E to F)
65Pavement Condition After One Year of
Service(Test Section F to G)
66Pavement Condition After One Year of
Service(Test Section G to end)
67Findings
- Performance monitoring of the rehabilitation work
on 24th Street after one year of service shows no
discernible cracking or distress in either the
control section or any of the test sections where
the Strata Relective Crack Relief System was
placed. - All sections are performing well with no
discernible rutting, as well.