Title: Location Public Hearing
1Location Public Hearing
- Brief Presentation Begins at 600 pm
- May 28, 29, 30, 2002
2Welcome!
- William C. Cuttler, P.E.
- Fairfax Preliminary Engineering Manager
3Capital Beltway Study
- Overview
- Purpose
- Alternatives
- Draft EIS
- Public Input
- Project Study Team
- Federal Highway Administration
- Virginia Department of Transportation
- Fairfax County Department of Transportation
- Virginia Department of Rail and Public
Transportation - Metropolitan Council of Governments
- Northern Virginia Transportation Commission
- Washington Metropolitan Area Transit Authority
- Metropolitan Airports Authority
- Maryland State Highway Administration
4Coordination with Other Studies
- Springfield Interchange
- Capital Beltway Rail Feasibility Study
- I-66 Major Investment Study / EIS
- Dulles Corridor Rapid Transit Project
- Northern Virginia 2020 Transportation Plan
- Marylands Capital Beltway Corridor
Transportation Plan
5Public Coordination
- Public Meetings
- Civic and Community Groups
- Citizen Workshops
- Fairfax County Task Force
6Public Coordination
- Public Meetings
- Civic and Community Groups
- Citizen Workshops
- Fairfax County Task Force
- Public Information Tools
- Telephone Hotline
- Internet Website
- E-Mail Address
- Mailing List
- Newsletters
- Brochures
7Purpose Improve Safety and Mobility
8Purpose Improve Safety and Mobility
9Major Investment Study
- Further Evaluate Feasibility of Beltway Rail
Transit - Advance Highway Improvements to National
Environmental Policy Act (NEPA) Phase - Coordinate with Other Major Studies in the Region
10Rail Feasibility Study
- Advance the Study to the Alternative Phase
- Perform Similar Studies for Other Rail Projects
- Further Examine Land Use and Transit Relationship
- Coordinate Highway and Transit Improvements in
the Beltway Right-of-Way
11Draft Environmental Impact Statement
- No Build vs. Build Alternatives
- Candidate Build Alternatives
- Location Approval by the Commonwealth
Transportation Board
12Project Overview
- Ken Wilkinson
- Environmental Project Manager
13Why was the Study Initiated?
- Improvements to the Capital Beltway are needed
to - Correct Safety and Design Deficiencies
- Address Current and Future Congestion
- Increase Capacity of Roadway
- Connect Regional HOV Network
- Provide Dedicated Express Bus Facilities
- Improve Operations and Traffic Flow
- Reduce Cut-Through Traffic
14What Did the Study Involve?
- Traffic Analysis
- Development of Alternatives
- Detailed Engineering, Traffic Operations, and
Environmental Analysis - Draft Environmental Impact Statement
15Traffic Analysis
- Travel Demand Modeling
- 2020 Traffic Volumes and Travel Patterns
- Evaluation of Traffic Operations
- Beltway
- Interchanges
- Intersecting Roadways
16Traffic Volumes
17Wide Range of Alternative Solutions
- Rail Transit
- Express Bus
- Transportation System Management
- Highway Improvements
18Highway Improvements
- Build Alternatives
- 3 Mainline Alternatives
- Improvements at 10 Interchanges
- Direct HOV Access at Route 29
19Concurrent HOV
- 2002 Preliminary Cost Estimate 2.5 - 2.8
Billion
20Express / Local with HOV
- 2002 Preliminary Cost Estimate 3.0 - 3.25
Billion
21Barrier-Separated HOV
- 2002 Preliminary Cost Estimate 2.7 - 2.9
Billion
22Environmental Document
23Impact Assessments
- Land Use
- Socio-Economics
- Natural Environment
- Parks and Recreation Areas
- Air Quality
- Noise
- Cultural Resources
- Visual and Aesthetic Conditions
- Hazardous Materials
24Summary of Environmental Impacts
Barrier- Separated HOV
Express/ Local with HOV
Concurrent HOV
Noise Impacts (Dwellings)
3,879
3,717
3,672
Dwellings Protected
5,123
5,199
5,129
Homes Displaced
206-217
258-294
219-258
Businesses Displaced
19-31
20-32
20-32
Parkland Required (Acres)
15.05
18.13
19.88
Historic Resources Affected
1
1
1
Wetlands Displaced (Acres)
4.62
4.74
5.06
25Remaining Schedule
JAN 1997
JUL-NOV 1998
NOV 1998
- Location Public Hearings
- CTB Decision
- Final Environmental Impact Statement
- Record of Decision
- Design and Construction
CITIZEN WORKSHOPS
MAJOR INVESTMENT STUDY (MIS)
DEVELOP CONCEPTS TO IMPLEMENT MIS STRATEGIES
NOV 1998-JUN1999
MARCH 2002
JUN 1999
DRAFT ENVIRONMENT IMPACT STATEMENT
CITIZEN WORKSHOPS
REFINE IMPROVEMENT ALTERNATIVES
MAY 2002
SUMMER/FALL 2002
FALL 2002
FINAL ENVIROMENTAL IMPACT STATEMENT
LOCATION PUBLIC HEARING
COMMONWEALTH TRANSPORTATION BOARD ACTION
FALL/WINTER 2002
RECORD OF DECISION
DESIGN AND CONSTRUCTION
26Public Input
- Comment Forms
- Letters
- E-Mail
- Court Reporter
- Comment Tonight
27CommentsandQuestions
28Panel
- Bill Cuttler VDOT Fairfax Preliminary
Engineering - Ken Wilkinson VDOT Environmental
- Debra Moore VDOT Right-of-Way
- Bob McDowell HNTB
- Jim Curren TransCore
- Steve Walter Parsons Transportation Group
29Contact Us
Call the Hotline at 703-352-7185
E-mail us at beltway_study_at_parsons.com
Visit our web site at http//project1.parsons.com
/capitalbeltway
- Send comments to
- Capital Beltway Study
- c/o Parsons Transportation Group of Virginia
- 10521 Rosehaven Street, 2nd Floor
- Fairfax, Virginia 22030
30(No Transcript)