Title: Tennessee Tombigbee Waterway Development Opportunities Conference
1Tennessee Tombigbee Waterway Development
Opportunities Conference
2FY 2008/2009/2010 OM PROGRAM
Includes 5.7M for Mooring Cells and Lock
Closures Includes 1.8M for Water Control
Manuals Includes 550K for Water Control
Manuals American Recovery and Reinvestment Act
(ARRA) Received an additional 4 Million
Supplemental Funding for Dredging
3TENN-TOM OM FUNDING FOR FY02 FY09(Presidents
Budget Appropriations)
4American Recovery and Reinvestment Act (ARRA)
OM Funding by Business Program
48.6M
5M
105.5M
59.1M
9.5M
5Mobile Harbor Turning Basin
- Type of Work New
- Depth 45 Feet
- Quantity 2.6Mcy
- Type of Material Sand, Silt and Clay
- Disposal Area (D/A) Upland/Ocean
- Distance to D/A 35 miles (Ocean)
- Type of Equipment Bucket/Pipeline
- Contract Awarded 8 Jul 09
- Contractor Great Lakes D D Co.
- Start Work Around late Aug 09
- Completion Projected in March 2010
Project Costs CG Federal 6M CG
Non-Federal 2M ARRA Federal
16M ARRA Non-Federal 5M Total
29M
6ARRA
- Key Focus Areas
- Job Preservation and Creation
- Infrastructure Investment
- Energy Efficiency
- Projects
- Backlog Maintenance/Buy Down Risk
- Energy Efficiency
- Focus on quick execution/job creation
- Cooperation of users during outages
7ARRA(Key Projects)
8Tennessee-Tombigbee Waterway Tonnage
9TTWW DREDGING PROGRAM
FY2007 Work
- Inland Dredge KELLY L
- 10 July 21 August 2007 (43 days)
- 4 Most Critical Locations
- Approximately 10,000 linear feet of bars,
191,000 cubic yards of material removed - Several locations were not dredged due to
funding limitations
FY2008 Work
- No Project Contract due to funding limitations
- Issued Task Order to Shared 16/24 Dredge
Contract with Coastal Project - Dredged 2 Locations
- Approximately 6,500 linear feet of bars,
130,000 cubic yards of material removed - Increased Survey Efforts to Monitor Channel
Conditions - Hot Spots Removed with R.W.DAVIS
10TTWW 2009 DREDGING PROGRAM
Supplemental Funding
- Received 4 million
- ENCO Dredge EDWARD G
(subcontract to Mike Hooks, Inc.) - Approximately 9 bars 225,000 cy
ARRA Funding
- Received 8 million
- 4.2M Committed for 2009 (balance carry over
to FY10) - Inland dredge INGENUITY
- Approximately 8 bars 350,000 cy
11DREDGE MATERIAL REMOVAL WORK
- Regain critical disposal capacity
- Agreements for removal of materials
- Beneficial use of materials
- Barge to Louisiana Gulf Coast
- Truck to local markets
- Approximately 200,000 cubic yards removed
12OM CONTRACT
- TTWs OM Contract expired September 30, 2008.
- Maintenance work performed under BWTs OM
contract from October 1, 2008 through April 8,
2009. - New TTW OM contract awarded April 7, 2009.
13LOCK CLOSURES
- Selden Lock September 9 October 8, 2009
-
- Coffeeville Lock September 11 October 1, 2009
-
- Bankhead Lock September 14 October 4, 2009
NOTE Next Scheduled Lock Closures on the
Tennessee-Tombigbee Waterway (2011) are Wilkins
Lock, Bevill Lock and Heflin Lock.
14BEVILL CROSS-CURRENT
15(No Transcript)
16Construct a system of nine submerged bendway weirs
Relocate the Snagboat Montgomery
17AQUATIC PLANT MANAGEMENT
- OM Contract
- Treated To Date 778 acres
- Projected Through End of FY 775 acres
- ARRA - Helicopter Contract (Projected Through End
of FY) - Floating Plant Treatment 1400 acres
- Submersed Plant Treatment 1000 acres
18(No Transcript)
19QUESTIONS?
20Tennessee-Tombigbee WaterwayCanal Section Levee
Certification
21Certification
- PAL gt Analyses gt Report gt FEMA
- 2 yr. max.
- Monroe, Itawamba, Tishomingo counties
- 31 August deadline to sign request or decline to
seek accreditation
22(No Transcript)
23(No Transcript)
24(No Transcript)
25Certification Requirements
- 44 CFR 65.10 and complementary USACE and FEMA
regs - Required report Submittals
- Engineering Analyses
- Operations and Maintenance Plans
- As-Builts
- Stamped by Engineer
- USACE requirements more comprehensive and
exhaustive
26Issue
- Authority Public Law 79-525, 79th Congress, 2d
Session, enacted July 24, 1946. - Two-way barge traffic, no provisions in the
authorization for flood control protection . . .
27Issue
- Certification no analyses exist that refute or
demonstrate flood control performance required
analyses are extensive. - Hydraulics, geotechnical, vegetation compliance,
OM . . .
28(No Transcript)
29Issue
- Vegetation currently heavily wooded, can not
certify unless vegetation and roots removed. - Would also require increased annual OM to
sustain levee requirements. . .
30(No Transcript)
31Vegetation Requirement, Overbuilt
32Vegetation Requirement, Typical
33Issue
- Wildlife Mitigation Wooded areas on levee are
part of Tenn-Tom mitigation lands. - Clearing would likely require acquisition of
replacement lands. . .
34(No Transcript)