Title: Transjakarta Busway


1
Transjakarta Busway
  • Heru Sutomo, PUSTRAL

2
Appraisal
  • No standardised CBA (cost benefit anal)
  • Foreign funding requires CBA, Local does not!
  • Even when choosing from alternatives
  • Best project selected intuitively
  • Private projects excepted

3
Evaluation
  • No evaluation required, may be a completion
    report
  • Most cases completion report and as built drawing
    not available
  • Never learn benefits impacts of a project
  • Foreign funding requires PBME (proj benefit
    monitoring evaluation)
  • A project may be funded from local or foreign
    money

4
Brief Story of Jakarta Busway
  • Patronage down from 45- 37 90s
  • Awaiting some mass transport means
  • Commissioned mid 2002 for a new bus system
    awaiting MRT
  • Interactive, participative process
  • Led and guarded by vice governor
  • 2-weekly regular consultation with different
    parties

5
Intensive interaction
  • Little money for the project, use meetings in
    vice governor meeting room
  • Consistent ways to convince that new system will
    be completely new system
  • Priority, exclusive lane
  • Operating under government control

6
Intensive interaction
  • 6 month debate to choose left-lane or middle lane
  • Competition on bus stop design (41 entries)
  • End of 2001 introduced to international
    community ITDP picked up and support Penalosa
  • Feb 2002- confirmed by governor
  • Mar 2002- confirmed by legislator funding

7
Intensive interaction
  • Feb 2003 trip to Bogota (ITDP)
  • Bus prepared 54
  • Mid 2003Preparation infrastructure
  • Public consultation Pelangi 2003/04
  • Launching 15 Jan 2004 (line 1 13km)
  • Pass 30,000/day early, 2004 70,000/day
  • 1st year running deficit Rp 38 billion
  • 2nd year running BEP expected

8
Organization
  • Run by Trans Jakarta Operating body
  • Buses owned by gov
  • Private supply drivers, maintenance, tickets
  • Revenues go to gov. revenue, operating costs paid
    using local budget
  • Line 2 3 (31km), all provided by private
  • Soft launch end Dec 2005
  • 2006 Line 4, 5, 6 tendering system