Transcript and Presenter's Notes

Title: MRO


1
  • MRO
  • Archive Readiness and End to End Testing
  • Edward Guinness and Susan Slavney
  • Washington University
  • Presented to PDS Management Council
  • August 2, 2006

2
Data ARchive Working Group
  • The DARWG has been chaired by Carl Kloss, JPL,
    who is retiring. Brian Hammer, JPL, will be the
    new DARWG Chair.
  • Document status
  • Archive Plan V1.1 was signed in January 2006.
  • ICDs All signed except ONC Imaging ICD, which
    is in progress.
  • SIS Documents and Peer Reviews
  • CRISM EDR/RDR review is complete, documents are
    complete but being revised.
  • HiRISE EDR review is complete, RDR SIS is in
    progress.
  • SHARAD EDR/RDR review is in progress.
  • CTX / MARCI EDR SISs are in draft form, not yet
    reviewed.
  • ONC Will be safed according to agreement with
    Imaging Node (TBD).
  • MCS EDR and RDR SISs are ready for peer review.
  • ACC SIS documents are in progress, not yet
    reviewed.
  • Local data dictionary was submitted to EN will
    be revised as a result of E2E tests

3
End-To-End Test Summary
  • Purpose To exercise MRO science data flow from
    instrument teams through PDS.
  • Approach Conduct a series of engineering tests
    to identify and correct problems before the first
    PDS delivery in June 2007.
  • Tests participants
  • HiRISE ? Imaging Node ? Engineering Node
  • CTX / MARCI ? Imaging Node ? Engineering Node
  • CRISM ? Geosciences Node ? Engineering Node
  • SHARAD ? Geosciences Node ? Engineering Node
  • MCS ? Atmospheres Node ? Engineering Node

4
Test Plan Four Phases
  • Test 1, May 2006 (Completed)
  • Team delivers one EDR to PDS Node using any
    agreed delivery method
  • Node validates product against EDR SIS and PDS
    standards
  • Test 2, July 2006 (In progress)
  • Team delivers complete archive volume with at
    least one EDR generated by operational software,
    using planned delivery mechanism
  • Node validates archive volume against EDR SIS,
    Archive SIS, and PDS standards
  • Team verifies availability of product at node
    through PDS catalog search
  • Test 3, October 2006
  • EDR Test Same as Test 2 but with one days worth
    of EDRs
  • RDR Test Same as Test 1 but with one RDR
  • Both EDRs and RDRs to be assembled into archive
    volumes
  • Test 4, February 2007
  • Same as Test 3, but with seven days worth of
    EDRs and RDRs
  • Additional test if needed in April or May, 2007

5
Test Status
  • Test 1, May 2006
  • Test completed
  • Preliminary report issued with several minor
    Discrepancy Reports (DRs)
  • Lien issued No CTX/MARCI testing
  • Test 2, July 2006
  • Test period completed
  • Report in progress

6
Test Details CRISM ? Geosciences
  • Test 1 Success Test 1 requirements met.
  • Also satisfied CRISM Test 2 requirements as well.
  • Data transferred 350 EDR Products 2300 files
    700 Mb
  • EDRs validated against PDS standards and EDR SIS.
  • Results 1 DR on PDS data dictionary, 2 DRs on
    minor label errors
  • DRs were corrected in Test 2
  • Test 2 - Success Test 2 requirements met.
  • Data transferred same as Test 1 plus a few
    corrected files
  • EDR archive assembled at Geosciences using inputs
    from CRISM team
  • EDRs validated against PDS standards and EDR
    SISs
  • Archive validated against PDS standards and
    Archive SIS
  • Results 1 DR on PDS data dictionary, 5 DRs on
    minor label errors

7
Test Details SHARAD ? Geosciences
  • Test 1 Success Test 1 requirements met.
  • Data transferred Two hand-generated EDRs (10
    files, 13 MB)
  • Transferred via FTP from ASDC in Italy to
    Geosciences
  • EDRs validated against PDS standards and EDR SIS.
  • Results 1 DR on PDS data dictionary, 1 DR on
    minor label errors
  • DRs were corrected in Test 2
  • Test 2 Success Test 2 requirements met.
  • Data transferred 225 EDRs 660 files 2.95 GB
  • Products were generated by SHARAD processing
    software
  • Files were transferred from ASDC to Geosciences
    using the planned daily automated FTP-based
    transfer system
  • EDRs validated against PDS standards and EDR SISs
  • Archive validated against PDS standards and
    Archive SIS
  • Results 1 DR on PDS data dictionary, 3 DRs on
    minor label errors

8
Test Details HiRISE ? Imaging
  • Test 1 Success Test 1 requirements met.
  • Used automatically generated EDRs from HiRISE
    team.
  • Data transferred 28 automatically-generated EDRs
    500 MB
  • Files transferred from HiROC to PDS IN using
    product and profile servers.
  • EDRs validated against PDS standards and EDR SIS.
  • Results No AIs generated.
  • Test 2 Success Test 2 requirements met.
  • Used automatically generated EDRs from HiRISE
    team.
  • Files transferred from HiROC to PDS IN using
    product and profile servers.
  • Data transferred 28 EDRs 500 MB.
  • EDRs validated against PDS standards and EDR
    SISs
  • Archive validated against PDS standards and
    Archive SIS
  • Results No AIs generated

9
Test Details CTX/MARCI ? Imaging
  • Test 1 Failure Test 1 Not Conducted
  • Instrument team not ready.
  • Test 2 Success Test 2 minimal requirements
    met.
  • Used automatically generated EDRs from instrument
    team.
  • Files transferred from MSSS to Imaging Node using
    FTP.
  • Data transferred 3 EDRs 300 MB.
  • EDRs validated against PDS standards and EDR
    SISs.
  • Results Test minimally successful, but peer
    review of data and SISs has not been conducted,
    and no draft Archive SIS has been produced.

10
Test Details MCS ? Atmospheres
  • Test 1 Completed Report TBD
  • Test 2 Completed Report TBD

11
Test Details Engineering Node
  • Test 2 Success Test 2 requirements met.
  • Number of Catalog Files ingested 25
  • MISSION.CAT, INSTHOST.CAT, CRISM (5), SHARAD
    (5), CTX (3), MARCI (3), HiRISE (4), MCS (3)
  • Number of Resource Links ingested 7
  • Number of Release Objects ingested 7
  • Number of MRO Test Subscriptions 4 (MCS
    Sharad, 2 CRISM)
  • PDS Data Search capability verified 6 data sets
  • Provided updated MRO Local Data Dictionary
  • Results
  • 3 DRs on subscription incompletion
  • 4 DRs on incomplete data access verification
  • 1 DR on EN Test Bed data set catalog files need
    to be re-ingested to display Abstract
    Description values
  • Lesson Learned
  • First use of the test bed, good experience
    learned to facilitate future mission End to End
    tests.

12
Conclusion
  • Lessons Learned
  • Tests are useful for identifying problems before
    first delivery.
  • Tests help push instrument teams to finish SISs.
  • Tests can highlight problems in instrument
    processing software in time to make corrections
    before production begins.
  • We recommend future missions consider conducting
    E2E tests.