Title: Materials and Processes Division
1SME INITIATIVE COURSE MATERIALS SUMMARY
PRESENTATION
- Dr. Ton de Rooij
- Head of Materials Mechanics and Processes Section
- Materials and Processes Division
- Product Assurance and Safety Department
2- The following section presents the requirements
for PMP. However the actual requirements for a
particular project depend on several factors,
e.g. - Type of spacecraft (manned or unmanned)
- Spacecraft orbit (LEO, GEO, polar, etc)
- Complexity (satellite, payload, etc.)
- Duration of space exposure (x years, y days,
etc.) - The requirements will therefore be specified as
part of the contract either in the statement of
work or in the PA plan
3THE REQUIREMENTS RELATED TO MATERIALS, MECHANICAL
PARTS AND PROCESSES
4PSS SpecificationsRelated to PMP
- PSS-01-70 - Issue 4 - Jan 94. Material,
mechanical-part and process selection
and quality control for ESA space
systems and associated equipment. - This specification establishes the detailed
requirements for the selection and control of
materials, mechanical parts and processes for
space systems and associated equipment in which
the use of materials etc. with specific
reliability and quality requirements is
mandatory. - PSS-01-700- Issue 2 - Aug 93. The technical
reporting and approval procedures for
materials mechanical parts and
processes. - This specification provides details concerning
the documentation requirements and the procedure
relevant to obtaining ESA approval for the use of
PMP in the fabrication of space systems
associated equipment.
5ECCS Specification Related to PMP
- ECSS-Q-70A-April 96 Space Product Assurance -
Materials, Mechanical Parts and Processes. - The purpose of this standard is to define the
requirements and statements applicable to
Materials, Mechanical Parts and Processes to
satisfy the mission performance requirements.
This standard also provides details concerning
the documentation requirements and the procedures
relevant to obtaining approval for the use of PMP
in the fabrication of Space Systems and
associated equipment. - This documentation is currently under revision
and issue B will include the documentation
Requirements presently given in PSS-01 -700. - In addition many of the lower level PSS
Specification (PSS-01-7XX series) are being
Replaced by ECCS Specification (ECSS-Q-70-XX
series).
6European Co-operation for Space Standardisation
(ECSS) 1.
- For materials and processes the situation is
presently as follows - ESA PSS-01 -70 has been replaced by ECSS
Specification ECCS-Q-70A - An additional twenty specifications, based on the
PSS-01 -7xx Series, have been issued a ECSS
Specifications - ECSS-Q-70-02A Thermal vacuum outgassing test for
the screening of space materials - ECSS-Q-70-04A Thermal Cycling test for the
Screening of space materials and
processes - ECSS-Q-70-07A Automatic machine wave soldering
- ECSS-Q-70-08A The manual soldering of high
reliability electrical connections - ECSS-Q-70-10A Qualification of printed circuit
boards - ECSS-Q-70-11A Procurement of printed circuit
boards - ECSS-Q-70-13A The Peel and Pull Off Strength of
Adhesives - ECSS-Q-70-18A Preparation, assembly and mounting
of RF coaxial cables - ECSS-Q-70-20A Determination of the susceptibility
of silver-plated copper wire and cable to
plague corrosion - ECSS-Q-70-21A Flammability testing for the
screening of space materials - ECSS-Q-70-22A The control of limited shelf-life
materials - ECSS-Q-70-25A The Application of Aeroglaze 2306
- ECSS-Q-70-26A Crimping of high-reliability
electrical connections
7European Co-operation for Space Standardisation
(ECSS) 2.
- ECSS-Q-70-28A Repair and modification of PCB
assemblies - ECSS-Q-70-29A Offgassing Testing of Materials
- ECSS-Q-70-30A Wire-wrapping of high reliability
electrical connections - ECSS-Q-70-33A The Application of Thermal Coating
PSG120FD - ECSS-Q-70-34A The Application of Aeroglaze H322
- ECSS-Q-70-35A The Application of Aeroglaze L300
- ECSS-Q-70-36A Materials selection for controlling
stress corrosion - ECSS-Q-70-37A Test method for stress corrosion
cracking - An additional nine specifications are in various
stages of ECSS review. - ECSS-Q-70B Materials, mechanical parts and
processes - ECSS-Q-70-01 Contamination and cleanliness
control - ECSS-Q-70-05 Detection of organic contamination
of surfaces by IR spectroscopy - ECSS-Q-70-09 Measurement of thermo-optical
properties of thermal control materials - ECSS-Q-70-38 High reliability soldering for
surface mount and mixed technology PCBs - ECSS-Q-70-46 General requirements for procurement
of threaded fasteners - ECSS-Q-70-50 Particulate contamination control in
clean rooms by particulate fall-out
(PFO)measurements - ECSS-Q-70-71 Data for selection of space materials
8THE REQUIREMENTS
- GENERAL The Contractor shall establish and
implement throughout the duration of the
contract a PMP programme which ensures full
compliance to PSS-01-70/ ECSS-Q-70. - PLANNING AND DOCUMENTATION
- The Contractor shall ensure that the PMP
programme is thoroughly planned and
documented. Particular emphasis shall be placed
on Critical PMP. - PROGRAMME PLAN
- The Contractor shall prepare a PMP
Selection and Control Plan which describes
the programme and procedures he will adopt for
compliance with the requirements of PSS-01
-70/ ECSS-Q-70. It shall be the Contractor's
responsibility to ensure that all sub-contractors
PMP programmes are consistent with his
Plan. Particular attention shall be paid to
specific Project requirements for PMP, their
control and interfaces with sub-contractors
activities.
9THE REQUIREMENTS - Continued
- CLEANLINESS/CONTAMINATION CONTROL
- The Contractor shall establish and maintain
an effective contamination and
cleanliness-control programme in
compliance with Project requirements
according to PSS-01-201 (to be superceded
by ECSS-Q-70-01). - Cleanliness-requirement specification (chemical
and particle) - Cleanliness-control plan
- Cleanliness-monitoring procedures/methods.
10THE REQUIREMENTS (2)
-
- PMP which cannot be considered either space
proven or standard/established shall be subjected
to an evaluation programme in order to assess
their suitability for the intended application.
This programme and subsequently its result shall
be submitted to ESA. - Thermal Vacuum
- Products considered for use in space systems
shall have their outgassing properties
assessed by thermal vacuum tests according
to ECSS-Q-70-02. - Thermal Cycling
- Products which are likely to be subjected to
thermal stresses shall have their thermal
cycling properties assessed as per
ECSS-Q-70-04.
11THE REQUIREMENTS (2)
- Radiation
- Products which will be exposed to
particle/UV radiation shall be assessed to
determine their ability to withstand the type and
degree of radiation dosage expected during
the mission. Tests are specified in
PSS-01-706. - Stress Corrosion
- Products intended for structural
applications and likely to be exposed to
long term terrestrial storage, or flown on the
STS, or used in launchers shall possess a
high resistance to SCC. Structural products
of a metallic nature shall be selected from the
preferred list in Table 1 of ECSS-Q-70-36.
Where no data exists testing shall be
performed as per ECCS-Q-70-37.
12THE REQUIREMENTS (3)
- Flammability
- Products considered for use in unmanned
spacecraft to be launched by the STS and
manned spacecraft (including those of the
spacecraft itself, stored equipment or
payload/experiments) shall be evaluated
for flammability resistance in the most
hazardous environment Flammability testing
is described in ECSS-Q-70-21. - Offgassing and Toxic analysis
- All products considered for use in the crew
compartment of - manned spacecraft shall be evaluated for
offgassing and odour. Samples of each
product shall be tested according to
ECSS-Q-70-29.
13THE REQUIREMENTS (3)
- Atomic Oxygen
- All products considered for use on the
external surface of spacecraft intended
for low-orbit operations shall be evaluated for
their resistance to atomic oxygen erosion.
Proposed tests shall be subject to ESA
approval. - Supplementary tests
- The Contractor shall review his PMP
programme for particular Project
requirements and add any other test as relevant.
These tests are subject to ESA approval.
14MATERIAL/MECHANICAL PART ENGINEERING
- SELECTION The Contractor shall be responsible
for the selection and for demonstrating
that they are capable of meeting the operating,
environmental, physical, chemical, safety,
quality and reliability conditions defined
in the relevant specifications and in the
contract. - SELECTION OF SPACE-PROVEN MATERIALS
- Well known materials/mechanical parts for
which test data applicable to the space
environment are available or which have been
previously used in space, or similar,
applications shall be selected wherever
possible. However each material/mechanical
part and its applications for a given Project
shall be considered separately. - SELECTION OF OTHER MATERIALS
- Request for approval (RFAs) of
material/mechanical parts which do not meet
the requirements of 2) above shall be submitted
to ESA. The format and content of the RFA is
given in PSS-01 -700. This can be modified
by a Project (subject to approval) if the
specific requirements of the Project make
this necessary.
15MATERIAL/MECHANICAL PART ENGINEERING (2)
- DECLARED MATERIAL LIST (DML)/DECLARED MECHANICAL
PARTS LISTS (DMPL) - The Contractor shall establish a
consolidated DML and DMPL of all items used
in the system. - Notes The project may decide not to
consolidate the lists but to compile an
assembly of Lists per Configuration item. - The Project may decide not to require a
separate DMPL. In this case the items are
added to the DML - The format and content of the DML/DMPL is given
in PSS-01-700 (ECSS-Q-70B). This can be modified
by a Project (subject to approval) if the
specific requirements of the Project make this
necessary. -
- Amendments to the DML/DMPL shall only be
implemented through established change
procedures.
16MATERIAL/MECHANICAL PART ENGINEERING (3)
- SPECIFICATIONS/STANDARDS
- Each type of material/mechanical part used
by the Contractor and listed in the DML/DMPL
shall be covered by a specification or
standard. - NON-CONFORMANCES
- Non-conforming materials/mechanical parts
found during incoming inspections, assembly
or test shall be dispositioned in accordance
with ECSS-Q-20.
17PROCESS ENGINEERING
- SELECTION The Contractor shall be responsible
for the selection of processes and for
demonstrating that they are capable of meeting
the requirements as defined in the
applicable Specifications and in the
contract. The Contractor and
sub-contractor shall plan and enforce an
effective process control programme. ESA
reserves the right to audit critical
processing lines. - STANDARD/ESTABLISHED PROCESSES
- Standard processes shall be selected
whatever possible. Critical processes,
unless performed in accordance with
PSS-01 -7XX/ECSS-Q70-XX series documents
shall require further identification and
approval before use.
18PROCESS ENGINEERING (2)
- NONASSESSED PROCESSES
- RFAs for processes for which there is no
known previous history shall be fully
justified and be subjected to an evaluation
programme. The process identification and
approval documents, defined in PSS-01
-700, shall be submitted to ESA. - DECLARED PROCESSES LIST (DPL)
- The Contractor shall establish a DPL of all
processes used in the programme. The format
and content of such a DPL is given in
PSS-01 700. Amendments to the DPL shall be
implemented only through established change
procedure.
19PROCESS ENGINEERING (3)
- PROCESS SPECIFICATION/STANDARD
- Each process shall be covered by a process
specification or standard. Maximum use shall
be made of existing ESA Specifications/standards
and ESA approved Specifications/standards
produced by international organisations and
nations agencies. - PROCESS WORKMANSHIP STANDARDS
- The Contractor shall provide detailed
workmanship standards for processes to aid
operators and inspectors in the establishment of
accept/reject criteria.
20PROCESS ENGINEERING (4)
- CRITICAL PROCESSES
- Critical Processes shall be subject to
stringent controls in form of documentation,
QA supervision (MIP, KIPs etc). and final
inspection/test. Critical processes shall
be defined by the Contractor in the early
phase of the contract. - NON CONFORMANCES
- Any unsatisfactory performance or non
conformance which is observed shall be
dispositioned in accordance with ECSS-Q-20. - TRAINING The Contractors shall establish a
training programme for all critical process
operators and inspectors (e.g. PSS-01-748).
21THE DOCUMENTATION REQUIREMENTS
22CONTENTS OF THE DECLARED MATERIALS LIST
Materials are classified into 20 groups depending
on their type or their main use.
- Aluminium and aluminium alloys
- Copper and copper alloys
- Nickel and nickel alloys
- Titanium and titanium alloys
- Steels
- Stainless steels
- Filler metals welding, brazing, soldering
- Miscellaneous metallic materials
- Optical materials
- Adhesives, coatings, varnishes
- Adhesive tapes
- Paints and inks
- Lubricants
- Potting compounds, sealants, foams
- Reinforced plastics
- Rubbers and elastomers
- Thermoplastics (non adhesive tapes, foils
(MLI),...) - Thermoset plastics
- Wires and cables (for materials aspects only)
- Miscellaneous nonmetallic materials (ceramics...)
If for a given project it is deemed necessary and
approved by ESA to create new groups, these shall
bear numbers over 20. Primers shall be classified
in the group of their associated components.
23Example of DML
24CONTENT of DML
The materials list consists of 10 columns which
shall be completed as indicated below.
Furthermore, similar materials shall be grouped
together as specified above. If a particular item
does not apply, write N.A. (Not Applicable).
- COLUMN 1 Item number
- Identification number in each group. One only per
material type. Does not change during the life of
the materials list (sub-items permitted when
deemed necessary). - COLUMN 2 Commercial identification
- Trade name and number (to be completed in full)
e.g. ARALDITE AV 100". Correct and standard
designation. - ESA has chosen
- Trade name number. For example, "ARALDITE AY
105" - If no trade name exists, then the manufacturer's
name plus number are entered e.g. "SCHOTT BK7 - In the case of metal alloys, the AA system is
recommended for aluminium alloys, and the AISI
system for steels for other metals or alloys,
the main constituent will be entered first
except in the case of a traditional name (e.g.
brass or bronze). - For each material as designated above, a unique
item number shall be given. If several lines
are used for different applications and/or
processing, sub-item numbers shall be added.
25CONTENT of DML, cont
- COLUMN 3 Chemical nature and type of product
- Example epoxy resin, polyurethane adhesive, or
Ti6AI4V alloy. - COLUMN 4 Procurement information
- Manufacturer/supplier name of the manufacturer
and name of the supplier if different. - Specification reference of the procurement
specification with, if considered useful, issue
and revision. It may be replaced by a national
specification number if this exists and makes
source of procurement irrelevant. - COLUMN 5 Processing parameters (summary)
- Give as relevant mixture proportions, cure
temperature, special cleaning agent, surface
treatment, thermal treatment, temperature, etc.. - NOTE Specification number is required, but not
sufficient for ESA purposes.
26CONTENT of DML, cont
- COLUMN 6 Use and location
- Indicate in what subsystems, box or item the
material is used and whether it acts as
structural element, thermal control, electrical
insulation etc. as relevant. - COLUMN 7 Environmental code
Radiation/UV/ATOX (1) R Ambiance A Temperature (2) T
G Geostationnary L Low orbit B Radiation belts I Interplanetary S outside shadow L outside light V Vacuum H Hermetic M Manned E Elevated pressure 1 0 to 100 K 2 101 to 200 K 3 201 to 300 K " etc.
(1) For materials inside the spacecraft, choose a
letter from the left-hand column. For materials
on the surface of the spacecraft, combine this
letter with "L" or "S". (2) Thermal cycling to
be indicated by two values, e.g. 3/5. (3) "RT"
can be accepted as a code between 283 K (10 C)
and 313 K (40 C). Materials which are at a
boundary between environments shall be described
by two sets of odes.
27CONTENT of DML, cont
- COLUMN 8 Size code
- Choose an alphanumeric combination from the above
mentioned table, e.g. A5 or V2 or W3.
AREA VOLUME MASS A (cm2) V (cm3) W (g) 0 0 lt 1 1 1 lt 10 2 10 lt 100 3 100 lt 1000 etc.
28CONTENT of DML, cont
- COLUMN 9
- All the codes of Column 9 shall be relevant for
the project concerned, which implies that they
refer to validated data applicable to this
project (not too old, same processing, same
composition, QC tests run on the same procured
lot, etc.) . - Reference of test report and relevant test result
code to be given in Subcolumn 9.1. - SUBCOLUMN 9.1
- Outgassing (OUT)
- P- The material passed the outgassing test
detailed in ECSS-Q-70-02 . - Reference of test report to be given in
Subcolumn 9.2. - F- The material failed . Waiver reference in
Subcolumn 9.2. - U- Materials of which outgassing characteristics
are unknown. - Stress Corrosion Cracking (SCC)
- A- The material is known to have a high
resistance to SCC. Table I document ECSS-Q-70-36
B- Table II and III document ECSS-Q-70-36. - Justification for approval (test reference)
stated in Subcolumn 9.2 (generally making
reference to ECSS-Q-70-36). - U- Materials and / or weldments for which SCC
characteristics are unknown. An SCC evaluation
form is required, based if necessary on tests
(see ECSS-Q-70-37 ).
29CONTENT of DML, cont
- Corrosion (Corr.)
- A- The material does not require a surface
treatment or coating for its intended
application, otherwise it shall be rated B. - B- Details of the surface treatment to be given
in Column 5. - Flammability (Flamm.) (if applicable)
- P- The material passed the requirements of
document ESA PSS-01 -721. - F- The material failed the test of document ESA
PSS-01 -721 in the applicable atmosphere. Waiver
reference in Subcolumn 9.2. - U- Materials of which characteristics are
unknown. - Offgassing (OFF) (if applicable)
- P- The material passed the requirements of
document ESA PSS-01 -729. - F- The material failed waiver reference in
Subcolumn 9.2 - U- Materials of which offgassing characteristics
are unknown.
30CONTENT of DML, cont
- SUBCOLUMN 9.2 Justification for approval
- The purpose of this Subcolumn is to enter any
additional information that may be necessary in
order to achieve customer approval. This
information is reference of the Requests For
Approval, reference of justificatory file for
materials approved for other space or
aeronautical programmes meeting the specific
needs of the programme, reference of the
evaluation report or waivers etc.. These
documents must be made available to ESA on
request.
31CONTENT of DML, cont
- SUBCOLUMN 9.3 Approval status of the Contractor
- A Approved - All Materials classified A may be
used without restriction. - Y Approved with restriction - These materials
require the preparation of QC test specimens or
a treatment before use potting, coating, test
specimens... - W Approved with a waiver - These materials do
not meet the requirements but are used for
functional reasons. The use of such materials
shall be reduced to a minimum. All the waivers
shall be approved by ESA. The waiver number shall
be entered in Subcolumn 9.2. - P Pending a decision - Materials for which an
evaluation report or a waiver is awaiting the
Contractor's provisional or definitive approval. - O Open - New materials or materials for which
investigations and qualification are in
progress. - D Deleted - This classification is used for a
material which is no longer used . - COLUMN 10 ESA approval and comments
- This column will be completed by ESA in
accordance with the standard - comments listed in Annex E.
32CONTENTS OF THE DECLARED PROCESS LIST
Processes are classified into 17 groups depending
on their type or their main use
- Adhesive bonding
- Composite manufacture
- Encapsulation/moulding
- Painting/coating
- Cleaning
- Welding/brazing
- Crimping/stripping/wire wrapping
- Soldering
- Surface conversion treatments
- Plating
- Machining
- Forming
- Heat treatment
- Special fabrication processes developed
specifically for the programme - Marking
- Miscellaneous processes
- Inspection procedures
If for a given project it is deemed necessary to
create new groups, these shall bear numbers over
17.
33Example of DPL
34CONTENT of DPL
The header information identifies the list as the
declared materials list and includes the issue
number and date of issue. It includes the
relevant CI number (configuration item number as
per project definition) if required by the
business agreement. The materials group number
may also be included here.
COLUMN 1 Item number Sequential item number in
each group of the declared process list. One only
per process type. Does not change during the life
of the process list. COLUMN 2 Process
identification The correct and standard
identification of the process shall be indicated,
e.g. the process name or title bonding, coating
or soldering.
35CONTENT of DPL, cont
- COLUMN 3 Specification
- The name or abbreviation of the one who applies
the process shall be identified. - A reference shall be made to the associated
procedure, e.g. national, international, EN, ISO,
- ECSS or company in house together with the issue,
revision and date. - COLUMN 4 Process description
- A short description of the process shall be
entered. - COLUMN 5 Use and location
- The codes entered shall define the location of
the process with respect to the - subsystem,
- particular piece of equipment (box or item),
- location within the equipment, and
- use of the equipment (e.g. a structural element,
thermal control, electrical insulation).
36CONTENT of DPL, cont
COLUMN 6 Manufacturers name The name or
abbreviation of the one who applies the process
shall be identified by a project agreed user code
if different to that entered in column 3. COLUMN
7 Associated item numbers The associated
material list (DML) or mechanical parts list
(DMPL) with the process shall be entered. COLUMN
8 Criticality The criticality shall be
considered either as critical C or non-critical
N. If a process is considered critical
references to the relevant RFA shall be entered.
37CONTENT of DPL, cont
COLUMN 9 and 10 Justification The purpose of the
justification and approval fields shall be to
enter any additional information that can be
necessary to obtain customer approval. Supporting
references for the justification shall be made
available if re-quested. The supplier and
customer approval status code shall be selected
from
A Approved All processes classified A may be
used without restriction. X Approved with a RFA
These processes shall be subjected to an
evaluation or validation programme. The RFA
number shall be entered as a comment. W Approved
with a waiver These processes do not meet the
requirements but are used for functional
reasons. The use of such processes shall be
reduced to a minimum. All deviation requests
shall be approved by the customer. The waiver
number shall be entered as a comment. P Pending
a decision Mechanical parts for which an
evaluation report or a waiver is waiting for the
contractors provisional or definitive
approval. O Open New processes or processes
for which investigations and qualifications are
in progress. R Rejected. D Deleted This
classification is used for a process which is no
longer used. Comments shall be entered wherever
approval cannot be given.
38CONTENTS OF THE DECLARED MECHANICAL PARTS LIST
Mechanical parts are classified into 11 groups
depending on their type or their main use
- Spacing parts (e.g. washers and spacers)
- Connecting parts (e.g. bolts, nuts, rivets,
inserts and clips) - Bearing parts (e.g. ball-bearings and needle
bearings) - Separating parts (e.g. pyrotechnics, springs and
cutters) - Control parts (e.g. gears)
- Fluid handling parts (e.g. diffusers)
- Heating parts
- Measuring instruments (e.g. gauges and
thermocouples) - Optical passive equipment
- Magnetic parts
- Other parts
- If for a given project it is deemed necessary to
create new groups, these shall bear - numbers over 61.
- Items which should appear in the EEE parts list
should not be repeated here (e.g. - heaters, some valves, thermostats, relays,
transformers coils, solenoids and ferrite cores)
39Example of DMPL
40CONTENT of DMPL, cont
This refers to the information which shall be
included in the DMPL The header information
identifies the list as the declared materials
list and includes the issue number and date of
issue. It includes the relevant CI number
(configuration item number as per project
definition) if required by the business
agreement. The materials group number may also be
included here.
41CONTENT of DMPL, cont
- COLUMN 1 Item number
- Sequential itemnumber in each group of the list.
One only per mechanical part type. Does not
change during the life of the mechanical parts
list. - COLUMN 2 Commercial identification
- Part number and material of construction. Where
complex items involving many materials are used
then reference shall be given to a document where
the relevant materials are listed. This document
may be included as an annex to the DMPL or shall
be available for inspection if requested. - COLUMN 3 Type of part
- A standard nomenclature shall be used to ensure
correct grouping of simi-lar - parts, e.g.
- valve, one way (and not one-way valve)
- valve, two way (and not two-way valve).
- Surface treatment should be described if
applicable.
42CONTENT of DMPL, cont
- COLUMN 4 Procurement information
- A short designator M or D shall be entered to
indicate if the mechanical part is procured from
a manufacturer or distributor. - Manufacturer or supplier name of the
manufacturer and name of the supplier if
different. - Procurement specification reference of the
procurement specification with, if considered
useful, issue, revision and date. It may be
replaced by a national or international
specification if this exists and identifies the
source of procurement if relevant. - COLUMN 5 Elementary function, main
characteristics - The function of the mechanical part shall be
entered. - The main characteristics of the mechanical part
shall be entered, e.g. number of revolutions per
minute for a ball bearing. - COLUMN 6 Use and location
- The codes entered (6.1) shall define the location
of the mechanical part with respect to the - subsystem,
- particular piece of equipment (box or item),
- location within the equipment, and
- use of the equipment.
- The subcontractors name shall be identified by a
project agreed user code (6.2).
43CONTENT of DMPL, cont
COLUMN 7 Environmental code The environmental
code is defined using
Radiation/UV/ATOX (1) R Ambiance A Temperature (2) T
G Geostationnary L Low orbit B Radiation belts I Interplanetary S outside shadow L outside light V Vacuum H Hermetic M Manned E Elevated pressure 1 0 to 100 K 2 101 to 200 K 3 201 to 300 K " etc.
(1) For materials inside the spacecraft, choose a
letter from the left-hand column. For materials
on the surface of the spacecraft, combine this
letter with "L" or "S". (2) Thermal cycling to
be indicated by two values, e.g. 3/5. (3) "RT"
can be accepted as a code between 283 K (10 C)
and 313 K (40 C).
44CONTENT of DMPL, cont
COLUMN 8 Criticality Mechanical parts shall be
considered either as critical C or non-critical
N. If a mechanical part is considered critical
the reason for the criticality and methods of
control shall be entered. COLUMN 9 Supplier
justification and approval The purpose of the
supplier justification and approval fields shall
be to enter any additional information that can
be necessary in order to achieve customer
approval. This information comprises reference
and issue of the RFA or approval, mechanical
parts justification file, evaluation reports and
deviation requests. These documents shall be made
available to the final customer on request. In
order to justify the use of a mechanical part,
reference shall be given to the relevant test
data that demonstrate acceptability of the
mechanical part under the environment conditions
and the application relevant to the particular
project concerned. Standard abbreviations shall
be used to summarize the acceptance status of a
mechanical part for a particular property. These
shall be defined by the customer. The supplier
approval status code shall be selected from the
next table. COLUMN 10 The customer approval
status code shall be selected from the
table. Additional comments shall be included
where appropriate.
45CONTENT of DMPL, cont
Approval status Code Description A Approved
All mechanical parts classified A may be used
without restriction. X Approved with a RFA
These mechanical parts shall be subjected to an
evaluation or validation programme. The RFA
number shall be entered as a comment. W Approved
with a waiver These mechanical parts do not
meet the requirements but are used for
functional reasons. The use of such mechanical
parts shall be reduced to a minimum. All
deviation requests shall be approved by the
customer. The waiver number shall be entered as
a comment. P Pending a decision Mechanical
parts for which an evaluation report or a waiver
is waiting for the contractors provisional or
definitive approval. O Open New mechanical
parts or mechanical parts for which
investigations and qualifications are in
progress. R Rejected. D Deleted This
classification is used for a mechanical part
which is no longer used. Comments shall be
entered wherever approval cannot be given.
46The Request for Approval(RFA)
- This is a document with which the user asks the
customer for permission to use a - critical mechanical part, material or process.
- The information given shall make possible to
judge whether the critical mechanical - part, material or process is appropriate for the
application envisaged. - Two issues of this are required
- Issue 0 Request accompanied by the evaluation or
validation / qualification programme - Issue 1 Request accompanied by the validation or
qualification results. - (Definition from ECSS- Q- 70B Draft)
47The RFA (cont)
For critical PMP the supplier shall submit an
RFA, suitable formats are given in PSS- 01- 700
and ECSS- Q- 70B (Draft). The initial issue
(Issue 0) of the RFA for provisional approval
should be provided as early as possible and not
later than PDR. This approval gives agreement to
perform the evaluation / validation /
qualification programmes and allows the PMP to be
included in the design process. Definitive
approval is only given after successful
completion of the relevant test programme at
which time the RFA is updated with the relevant
test report references etc and reissued (Issue 1)
in its final form. This should be complete prior
to CDR such that the material can be used in
flight hardware construction.
48Request for Approval (RFA)Request for Deviation
(RFD)Request for Waiver (RFA)
There is, unfortunately, much confusion
surrounding the use of the above terms.
Strictly speaking they should be used as
follows RFA Document which asks customer
permission to use a critical part, material or
process. RFD Document which asks customer
permission to use a part, material or process
which does not meet one or more of the
specified requirements (e. g. material which
fails outgassing, is flammable, etc.). The
document includes rationale for acceptance.
This RFD would be applicable for all subsequent
items manufactured. RFW Document which asks
customer permission to use a part, material or
process where as a result of inspection etc. a
non conformance has been identified (e. g. hole
drilled in wrong place, non acceptable adhesive
used etc.). This RFW would be applicable to
this one item only.
49RFA - RFD - RFA
- European companies and ESA are more used to using
the term RFW to cover both RFD and RFW. The RFD
is called up in ECSS documentation (not
consistently) and it is not uncommon to find a
statement of work where, for example, ECSS- Q-
70A is a requirements document, that a specific
change from the use of the term RFD to RFW is
included. - On manned space projects, the term RFA is used in
place of the RFD / RFW to give a rationale for
approval for safety critical materials and
mechanical parts (equivalent to the NASA
materials usage agreement, MUA). One added
complication is that the format of the RFA is
different to that given in either PSS- 01- 700 or
ECSS- Q- 70B (draft) and the two should not be
confused.
50RFA for Materials Certification
As mentioned earlier on manned space programmes
on RFA is used to justify the use of materials /
mechanical parts which do not meet the materials
requirements related to specify (flammability,
offgassing and stress corrosion). Some examples
of completed RFAs are attached.
51PMP Flow chart
52Material RFA -1
53Material RFA -2
54Mechanical part RFA-1
55Mechanical part RFA-2
56Process RFA-1
57Process RFA-2