Materials and Processes Division - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

Materials and Processes Division

Description:

MATERIAL/MECHANICAL PART ENGINEERING ... PROCESS ENGINEERING ... file for materials approved for other space or aeronautical programmes ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 58
Provided by: tder6
Category:

less

Transcript and Presenter's Notes

Title: Materials and Processes Division


1
SME INITIATIVE COURSE MATERIALS SUMMARY
PRESENTATION
  • Dr. Ton de Rooij
  • Head of Materials Mechanics and Processes Section
  • Materials and Processes Division
  • Product Assurance and Safety Department

2
  • The following section presents the requirements
    for PMP. However the actual requirements for a
    particular project depend on several factors,
    e.g.
  • Type of spacecraft (manned or unmanned)
  • Spacecraft orbit (LEO, GEO, polar, etc)
  • Complexity (satellite, payload, etc.)
  • Duration of space exposure (x years, y days,
    etc.)
  • The requirements will therefore be specified as
    part of the contract either in the statement of
    work or in the PA plan

3
THE REQUIREMENTS RELATED TO MATERIALS, MECHANICAL
PARTS AND PROCESSES
4
PSS SpecificationsRelated to PMP
  • PSS-01-70 - Issue 4 - Jan 94. Material,
    mechanical-part and process selection
    and quality control for ESA space
    systems and associated equipment.
  • This specification establishes the detailed
    requirements for the selection and control of
    materials, mechanical parts and processes for
    space systems and associated equipment in which
    the use of materials etc. with specific
    reliability and quality requirements is
    mandatory.
  • PSS-01-700- Issue 2 - Aug 93. The technical
    reporting and approval procedures for
    materials mechanical parts and
    processes.
  • This specification provides details concerning
    the documentation requirements and the procedure
    relevant to obtaining ESA approval for the use of
    PMP in the fabrication of space systems
    associated equipment.

5
ECCS Specification Related to PMP
  • ECSS-Q-70A-April 96 Space Product Assurance -
    Materials, Mechanical Parts and Processes.
  • The purpose of this standard is to define the
    requirements and statements applicable to
    Materials, Mechanical Parts and Processes to
    satisfy the mission performance requirements.
    This standard also provides details concerning
    the documentation requirements and the procedures
    relevant to obtaining approval for the use of PMP
    in the fabrication of Space Systems and
    associated equipment.
  • This documentation is currently under revision
    and issue B will include the documentation
    Requirements presently given in PSS-01 -700.
  • In addition many of the lower level PSS
    Specification (PSS-01-7XX series) are being
    Replaced by ECCS Specification (ECSS-Q-70-XX
    series).

6
European Co-operation for Space Standardisation
(ECSS) 1.
  • For materials and processes the situation is
    presently as follows
  • ESA PSS-01 -70 has been replaced by ECSS
    Specification ECCS-Q-70A
  • An additional twenty specifications, based on the
    PSS-01 -7xx Series, have been issued a ECSS
    Specifications
  • ECSS-Q-70-02A Thermal vacuum outgassing test for
    the screening of space materials
  • ECSS-Q-70-04A Thermal Cycling test for the
    Screening of space materials and
    processes
  • ECSS-Q-70-07A Automatic machine wave soldering
  • ECSS-Q-70-08A The manual soldering of high
    reliability electrical connections
  • ECSS-Q-70-10A Qualification of printed circuit
    boards
  • ECSS-Q-70-11A Procurement of printed circuit
    boards
  • ECSS-Q-70-13A The Peel and Pull Off Strength of
    Adhesives
  • ECSS-Q-70-18A Preparation, assembly and mounting
    of RF coaxial cables
  • ECSS-Q-70-20A Determination of the susceptibility
    of silver-plated copper wire and cable to
    plague corrosion
  • ECSS-Q-70-21A Flammability testing for the
    screening of space materials
  • ECSS-Q-70-22A The control of limited shelf-life
    materials
  • ECSS-Q-70-25A The Application of Aeroglaze 2306
  • ECSS-Q-70-26A Crimping of high-reliability
    electrical connections

7
European Co-operation for Space Standardisation
(ECSS) 2.
  • ECSS-Q-70-28A Repair and modification of PCB
    assemblies
  • ECSS-Q-70-29A Offgassing Testing of Materials
  • ECSS-Q-70-30A Wire-wrapping of high reliability
    electrical connections
  • ECSS-Q-70-33A The Application of Thermal Coating
    PSG120FD
  • ECSS-Q-70-34A The Application of Aeroglaze H322
  • ECSS-Q-70-35A The Application of Aeroglaze L300
  • ECSS-Q-70-36A Materials selection for controlling
    stress corrosion
  • ECSS-Q-70-37A Test method for stress corrosion
    cracking
  • An additional nine specifications are in various
    stages of ECSS review.
  • ECSS-Q-70B Materials, mechanical parts and
    processes
  • ECSS-Q-70-01 Contamination and cleanliness
    control
  • ECSS-Q-70-05 Detection of organic contamination
    of surfaces by IR spectroscopy
  • ECSS-Q-70-09 Measurement of thermo-optical
    properties of thermal control materials
  • ECSS-Q-70-38 High reliability soldering for
    surface mount and mixed technology PCBs
  • ECSS-Q-70-46 General requirements for procurement
    of threaded fasteners
  • ECSS-Q-70-50 Particulate contamination control in
    clean rooms by particulate fall-out
    (PFO)measurements
  • ECSS-Q-70-71 Data for selection of space materials

8
THE REQUIREMENTS
  • GENERAL The Contractor shall establish and
    implement throughout the duration of the
    contract a PMP programme which ensures full
    compliance to PSS-01-70/ ECSS-Q-70.
  • PLANNING AND DOCUMENTATION
  • The Contractor shall ensure that the PMP
    programme is thoroughly planned and
    documented. Particular emphasis shall be placed
    on Critical PMP.
  • PROGRAMME PLAN
  • The Contractor shall prepare a PMP
    Selection and Control Plan which describes
    the programme and procedures he will adopt for
    compliance with the requirements of PSS-01
    -70/ ECSS-Q-70. It shall be the Contractor's
    responsibility to ensure that all sub-contractors
    PMP programmes are consistent with his
    Plan. Particular attention shall be paid to
    specific Project requirements for PMP, their
    control and interfaces with sub-contractors
    activities.

9
THE REQUIREMENTS - Continued
  • CLEANLINESS/CONTAMINATION CONTROL
  • The Contractor shall establish and maintain
    an effective contamination and
    cleanliness-control programme in
    compliance with Project requirements
    according to PSS-01-201 (to be superceded
    by ECSS-Q-70-01).
  • Cleanliness-requirement specification (chemical
    and particle)
  • Cleanliness-control plan
  • Cleanliness-monitoring procedures/methods.

10
THE REQUIREMENTS (2)
  • PMP which cannot be considered either space
    proven or standard/established shall be subjected
    to an evaluation programme in order to assess
    their suitability for the intended application.
    This programme and subsequently its result shall
    be submitted to ESA.
  • Thermal Vacuum
  • Products considered for use in space systems
    shall have their outgassing properties
    assessed by thermal vacuum tests according
    to ECSS-Q-70-02.
  • Thermal Cycling
  • Products which are likely to be subjected to
    thermal stresses shall have their thermal
    cycling properties assessed as per
    ECSS-Q-70-04.

11
THE REQUIREMENTS (2)
  • Radiation
  • Products which will be exposed to
    particle/UV radiation shall be assessed to
    determine their ability to withstand the type and
    degree of radiation dosage expected during
    the mission. Tests are specified in
    PSS-01-706.
  • Stress Corrosion
  • Products intended for structural
    applications and likely to be exposed to
    long term terrestrial storage, or flown on the
    STS, or used in launchers shall possess a
    high resistance to SCC. Structural products
    of a metallic nature shall be selected from the
    preferred list in Table 1 of ECSS-Q-70-36.
    Where no data exists testing shall be
    performed as per ECCS-Q-70-37.

12
THE REQUIREMENTS (3)
  • Flammability
  • Products considered for use in unmanned
    spacecraft to be launched by the STS and
    manned spacecraft (including those of the
    spacecraft itself, stored equipment or
    payload/experiments) shall be evaluated
    for flammability resistance in the most
    hazardous environment Flammability testing
    is described in ECSS-Q-70-21.
  • Offgassing and Toxic analysis
  • All products considered for use in the crew
    compartment of
  • manned spacecraft shall be evaluated for
    offgassing and odour. Samples of each
    product shall be tested according to
    ECSS-Q-70-29.

13
THE REQUIREMENTS (3)
  • Atomic Oxygen
  • All products considered for use on the
    external surface of spacecraft intended
    for low-orbit operations shall be evaluated for
    their resistance to atomic oxygen erosion.
    Proposed tests shall be subject to ESA
    approval.
  • Supplementary tests
  • The Contractor shall review his PMP
    programme for particular Project
    requirements and add any other test as relevant.
    These tests are subject to ESA approval.

14
MATERIAL/MECHANICAL PART ENGINEERING
  • SELECTION The Contractor shall be responsible
    for the selection and for demonstrating
    that they are capable of meeting the operating,
    environmental, physical, chemical, safety,
    quality and reliability conditions defined
    in the relevant specifications and in the
    contract.
  • SELECTION OF SPACE-PROVEN MATERIALS
  • Well known materials/mechanical parts for
    which test data applicable to the space
    environment are available or which have been
    previously used in space, or similar,
    applications shall be selected wherever
    possible. However each material/mechanical
    part and its applications for a given Project
    shall be considered separately.
  • SELECTION OF OTHER MATERIALS
  • Request for approval (RFAs) of
    material/mechanical parts which do not meet
    the requirements of 2) above shall be submitted
    to ESA. The format and content of the RFA is
    given in PSS-01 -700. This can be modified
    by a Project (subject to approval) if the
    specific requirements of the Project make
    this necessary.

15
MATERIAL/MECHANICAL PART ENGINEERING (2)
  • DECLARED MATERIAL LIST (DML)/DECLARED MECHANICAL
    PARTS LISTS (DMPL)
  • The Contractor shall establish a
    consolidated DML and DMPL of all items used
    in the system.
  • Notes The project may decide not to
    consolidate the lists but to compile an
    assembly of Lists per Configuration item.
  • The Project may decide not to require a
    separate DMPL. In this case the items are
    added to the DML
  • The format and content of the DML/DMPL is given
    in PSS-01-700 (ECSS-Q-70B). This can be modified
    by a Project (subject to approval) if the
    specific requirements of the Project make this
    necessary.
  • Amendments to the DML/DMPL shall only be
    implemented through established change
    procedures.

16
MATERIAL/MECHANICAL PART ENGINEERING (3)
  • SPECIFICATIONS/STANDARDS
  • Each type of material/mechanical part used
    by the Contractor and listed in the DML/DMPL
    shall be covered by a specification or
    standard.
  • NON-CONFORMANCES
  • Non-conforming materials/mechanical parts
    found during incoming inspections, assembly
    or test shall be dispositioned in accordance
    with ECSS-Q-20.

17
PROCESS ENGINEERING
  • SELECTION The Contractor shall be responsible
    for the selection of processes and for
    demonstrating that they are capable of meeting
    the requirements as defined in the
    applicable Specifications and in the
    contract. The Contractor and
    sub-contractor shall plan and enforce an
    effective process control programme. ESA
    reserves the right to audit critical
    processing lines.
  • STANDARD/ESTABLISHED PROCESSES
  • Standard processes shall be selected
    whatever possible. Critical processes,
    unless performed in accordance with
    PSS-01 -7XX/ECSS-Q70-XX series documents
    shall require further identification and
    approval before use.

18
PROCESS ENGINEERING (2)
  • NONASSESSED PROCESSES
  • RFAs for processes for which there is no
    known previous history shall be fully
    justified and be subjected to an evaluation
    programme. The process identification and
    approval documents, defined in PSS-01
    -700, shall be submitted to ESA.
  • DECLARED PROCESSES LIST (DPL)
  • The Contractor shall establish a DPL of all
    processes used in the programme. The format
    and content of such a DPL is given in
    PSS-01 700. Amendments to the DPL shall be
    implemented only through established change
    procedure.

19
PROCESS ENGINEERING (3)
  • PROCESS SPECIFICATION/STANDARD
  • Each process shall be covered by a process
    specification or standard. Maximum use shall
    be made of existing ESA Specifications/standards
    and ESA approved Specifications/standards
    produced by international organisations and
    nations agencies.
  • PROCESS WORKMANSHIP STANDARDS
  • The Contractor shall provide detailed
    workmanship standards for processes to aid
    operators and inspectors in the establishment of
    accept/reject criteria.

20
PROCESS ENGINEERING (4)
  • CRITICAL PROCESSES
  • Critical Processes shall be subject to
    stringent controls in form of documentation,
    QA supervision (MIP, KIPs etc). and final
    inspection/test. Critical processes shall
    be defined by the Contractor in the early
    phase of the contract.
  • NON CONFORMANCES
  • Any unsatisfactory performance or non
    conformance which is observed shall be
    dispositioned in accordance with ECSS-Q-20.
  • TRAINING The Contractors shall establish a
    training programme for all critical process
    operators and inspectors (e.g. PSS-01-748).

21
THE DOCUMENTATION REQUIREMENTS
22
CONTENTS OF THE DECLARED MATERIALS LIST
Materials are classified into 20 groups depending
on their type or their main use.
  1. Aluminium and aluminium alloys
  2. Copper and copper alloys
  3. Nickel and nickel alloys
  4. Titanium and titanium alloys
  5. Steels
  6. Stainless steels
  7. Filler metals welding, brazing, soldering
  8. Miscellaneous metallic materials
  9. Optical materials
  10. Adhesives, coatings, varnishes
  1. Adhesive tapes
  2. Paints and inks
  3. Lubricants
  4. Potting compounds, sealants, foams
  5. Reinforced plastics
  6. Rubbers and elastomers
  7. Thermoplastics (non adhesive tapes, foils
    (MLI),...)
  8. Thermoset plastics
  9. Wires and cables (for materials aspects only)
  10. Miscellaneous nonmetallic materials (ceramics...)

If for a given project it is deemed necessary and
approved by ESA to create new groups, these shall
bear numbers over 20. Primers shall be classified
in the group of their associated components.
23
Example of DML
24
CONTENT of DML
The materials list consists of 10 columns which
shall be completed as indicated below.
Furthermore, similar materials shall be grouped
together as specified above. If a particular item
does not apply, write N.A. (Not Applicable).
  • COLUMN 1 Item number
  • Identification number in each group. One only per
    material type. Does not change during the life of
    the materials list (sub-items permitted when
    deemed necessary).
  • COLUMN 2 Commercial identification
  • Trade name and number (to be completed in full)
    e.g. ARALDITE AV 100". Correct and standard
    designation.
  • ESA has chosen
  • Trade name number. For example, "ARALDITE AY
    105"
  • If no trade name exists, then the manufacturer's
    name plus number are entered e.g. "SCHOTT BK7
  • In the case of metal alloys, the AA system is
    recommended for aluminium alloys, and the AISI
    system for steels for other metals or alloys,
    the main constituent will be entered first
    except in the case of a traditional name (e.g.
    brass or bronze).
  • For each material as designated above, a unique
    item number shall be given. If several lines
    are used for different applications and/or
    processing, sub-item numbers shall be added.

25
CONTENT of DML, cont
  • COLUMN 3 Chemical nature and type of product
  • Example epoxy resin, polyurethane adhesive, or
    Ti6AI4V alloy.
  • COLUMN 4 Procurement information
  • Manufacturer/supplier name of the manufacturer
    and name of the supplier if different.
  • Specification reference of the procurement
    specification with, if considered useful, issue
    and revision. It may be replaced by a national
    specification number if this exists and makes
    source of procurement irrelevant.
  • COLUMN 5 Processing parameters (summary)
  • Give as relevant mixture proportions, cure
    temperature, special cleaning agent, surface
    treatment, thermal treatment, temperature, etc..
  • NOTE Specification number is required, but not
    sufficient for ESA purposes.

26
CONTENT of DML, cont
  • COLUMN 6 Use and location
  • Indicate in what subsystems, box or item the
    material is used and whether it acts as
    structural element, thermal control, electrical
    insulation etc. as relevant.
  • COLUMN 7 Environmental code

Radiation/UV/ATOX (1) R Ambiance A Temperature (2) T
G Geostationnary L Low orbit B Radiation belts I Interplanetary S outside shadow L outside light V Vacuum H Hermetic M Manned E Elevated pressure 1 0 to 100 K 2 101 to 200 K 3 201 to 300 K " etc.
(1) For materials inside the spacecraft, choose a
letter from the left-hand column. For materials
on the surface of the spacecraft, combine this
letter with "L" or "S". (2) Thermal cycling to
be indicated by two values, e.g. 3/5. (3) "RT"
can be accepted as a code between 283 K (10 C)
and 313 K (40 C). Materials which are at a
boundary between environments shall be described
by two sets of odes.
27
CONTENT of DML, cont
  • COLUMN 8 Size code
  • Choose an alphanumeric combination from the above
    mentioned table, e.g. A5 or V2 or W3.

AREA VOLUME MASS A (cm2) V (cm3) W (g) 0 0 lt 1 1 1 lt 10 2 10 lt 100 3 100 lt 1000 etc.
28
CONTENT of DML, cont
  • COLUMN 9
  • All the codes of Column 9 shall be relevant for
    the project concerned, which implies that they
    refer to validated data applicable to this
    project (not too old, same processing, same
    composition, QC tests run on the same procured
    lot, etc.) .
  • Reference of test report and relevant test result
    code to be given in Subcolumn 9.1.
  • SUBCOLUMN 9.1
  • Outgassing (OUT)
  • P- The material passed the outgassing test
    detailed in ECSS-Q-70-02 .
  • Reference of test report to be given in
    Subcolumn 9.2.
  • F- The material failed . Waiver reference in
    Subcolumn 9.2.
  • U- Materials of which outgassing characteristics
    are unknown.
  • Stress Corrosion Cracking (SCC)
  • A- The material is known to have a high
    resistance to SCC. Table I document ECSS-Q-70-36
    B- Table II and III document ECSS-Q-70-36.
  • Justification for approval (test reference)
    stated in Subcolumn 9.2 (generally making
    reference to ECSS-Q-70-36).
  • U- Materials and / or weldments for which SCC
    characteristics are unknown. An SCC evaluation
    form is required, based if necessary on tests
    (see ECSS-Q-70-37 ).

29
CONTENT of DML, cont
  • Corrosion (Corr.)
  • A- The material does not require a surface
    treatment or coating for its intended
    application, otherwise it shall be rated B.
  • B- Details of the surface treatment to be given
    in Column 5.
  • Flammability (Flamm.) (if applicable)
  • P- The material passed the requirements of
    document ESA PSS-01 -721.
  • F- The material failed the test of document ESA
    PSS-01 -721 in the applicable atmosphere. Waiver
    reference in Subcolumn 9.2.
  • U- Materials of which characteristics are
    unknown.
  • Offgassing (OFF) (if applicable)
  • P- The material passed the requirements of
    document ESA PSS-01 -729.
  • F- The material failed waiver reference in
    Subcolumn 9.2
  • U- Materials of which offgassing characteristics
    are unknown.

30
CONTENT of DML, cont
  • SUBCOLUMN 9.2 Justification for approval
  • The purpose of this Subcolumn is to enter any
    additional information that may be necessary in
    order to achieve customer approval. This
    information is reference of the Requests For
    Approval, reference of justificatory file for
    materials approved for other space or
    aeronautical programmes meeting the specific
    needs of the programme, reference of the
    evaluation report or waivers etc.. These
    documents must be made available to ESA on
    request.

31
CONTENT of DML, cont
  • SUBCOLUMN 9.3 Approval status of the Contractor
  • A Approved - All Materials classified A may be
    used without restriction.
  • Y Approved with restriction - These materials
    require the preparation of QC test specimens or
    a treatment before use potting, coating, test
    specimens...
  • W Approved with a waiver - These materials do
    not meet the requirements but are used for
    functional reasons. The use of such materials
    shall be reduced to a minimum. All the waivers
    shall be approved by ESA. The waiver number shall
    be entered in Subcolumn 9.2.
  • P Pending a decision - Materials for which an
    evaluation report or a waiver is awaiting the
    Contractor's provisional or definitive approval.
  • O Open - New materials or materials for which
    investigations and qualification are in
    progress.
  • D Deleted - This classification is used for a
    material which is no longer used .
  • COLUMN 10 ESA approval and comments
  • This column will be completed by ESA in
    accordance with the standard
  • comments listed in Annex E.

32
CONTENTS OF THE DECLARED PROCESS LIST
Processes are classified into 17 groups depending
on their type or their main use
  1. Adhesive bonding
  2. Composite manufacture
  3. Encapsulation/moulding
  4. Painting/coating
  5. Cleaning
  6. Welding/brazing
  7. Crimping/stripping/wire wrapping
  8. Soldering
  9. Surface conversion treatments
  1. Plating
  2. Machining
  3. Forming
  4. Heat treatment
  5. Special fabrication processes developed
    specifically for the programme
  6. Marking
  7. Miscellaneous processes
  8. Inspection procedures

If for a given project it is deemed necessary to
create new groups, these shall bear numbers over
17.
33
Example of DPL
34
CONTENT of DPL
The header information identifies the list as the
declared materials list and includes the issue
number and date of issue. It includes the
relevant CI number (configuration item number as
per project definition) if required by the
business agreement. The materials group number
may also be included here.
COLUMN 1 Item number Sequential item number in
each group of the declared process list. One only
per process type. Does not change during the life
of the process list. COLUMN 2 Process
identification The correct and standard
identification of the process shall be indicated,
e.g. the process name or title bonding, coating
or soldering.
35
CONTENT of DPL, cont
  • COLUMN 3 Specification
  • The name or abbreviation of the one who applies
    the process shall be identified.
  • A reference shall be made to the associated
    procedure, e.g. national, international, EN, ISO,
  • ECSS or company in house together with the issue,
    revision and date.
  • COLUMN 4 Process description
  • A short description of the process shall be
    entered.
  • COLUMN 5 Use and location
  • The codes entered shall define the location of
    the process with respect to the
  • subsystem,
  • particular piece of equipment (box or item),
  • location within the equipment, and
  • use of the equipment (e.g. a structural element,
    thermal control, electrical insulation).

36
CONTENT of DPL, cont
COLUMN 6 Manufacturers name The name or
abbreviation of the one who applies the process
shall be identified by a project agreed user code
if different to that entered in column 3. COLUMN
7 Associated item numbers The associated
material list (DML) or mechanical parts list
(DMPL) with the process shall be entered. COLUMN
8 Criticality The criticality shall be
considered either as critical C or non-critical
N. If a process is considered critical
references to the relevant RFA shall be entered.
37
CONTENT of DPL, cont
COLUMN 9 and 10 Justification The purpose of the
justification and approval fields shall be to
enter any additional information that can be
necessary to obtain customer approval. Supporting
references for the justification shall be made
available if re-quested. The supplier and
customer approval status code shall be selected
from
A Approved All processes classified A may be
used without restriction. X Approved with a RFA
These processes shall be subjected to an
evaluation or validation programme. The RFA
number shall be entered as a comment. W Approved
with a waiver These processes do not meet the
requirements but are used for functional
reasons. The use of such processes shall be
reduced to a minimum. All deviation requests
shall be approved by the customer. The waiver
number shall be entered as a comment. P Pending
a decision Mechanical parts for which an
evaluation report or a waiver is waiting for the
contractors provisional or definitive
approval. O Open New processes or processes
for which investigations and qualifications are
in progress. R Rejected. D Deleted This
classification is used for a process which is no
longer used. Comments shall be entered wherever
approval cannot be given.
38
CONTENTS OF THE DECLARED MECHANICAL PARTS LIST
Mechanical parts are classified into 11 groups
depending on their type or their main use
  • Spacing parts (e.g. washers and spacers)
  • Connecting parts (e.g. bolts, nuts, rivets,
    inserts and clips)
  • Bearing parts (e.g. ball-bearings and needle
    bearings)
  • Separating parts (e.g. pyrotechnics, springs and
    cutters)
  • Control parts (e.g. gears)
  • Fluid handling parts (e.g. diffusers)
  • Heating parts
  • Measuring instruments (e.g. gauges and
    thermocouples)
  • Optical passive equipment
  • Magnetic parts
  • Other parts
  • If for a given project it is deemed necessary to
    create new groups, these shall bear
  • numbers over 61.
  • Items which should appear in the EEE parts list
    should not be repeated here (e.g.
  • heaters, some valves, thermostats, relays,
    transformers coils, solenoids and ferrite cores)

39
Example of DMPL
40
CONTENT of DMPL, cont
This refers to the information which shall be
included in the DMPL The header information
identifies the list as the declared materials
list and includes the issue number and date of
issue. It includes the relevant CI number
(configuration item number as per project
definition) if required by the business
agreement. The materials group number may also be
included here.
41
CONTENT of DMPL, cont
  • COLUMN 1 Item number
  • Sequential itemnumber in each group of the list.
    One only per mechanical part type. Does not
    change during the life of the mechanical parts
    list.
  • COLUMN 2 Commercial identification
  • Part number and material of construction. Where
    complex items involving many materials are used
    then reference shall be given to a document where
    the relevant materials are listed. This document
    may be included as an annex to the DMPL or shall
    be available for inspection if requested.
  • COLUMN 3 Type of part
  • A standard nomenclature shall be used to ensure
    correct grouping of simi-lar
  • parts, e.g.
  • valve, one way (and not one-way valve)
  • valve, two way (and not two-way valve).
  • Surface treatment should be described if
    applicable.

42
CONTENT of DMPL, cont
  • COLUMN 4 Procurement information
  • A short designator M or D shall be entered to
    indicate if the mechanical part is procured from
    a manufacturer or distributor.
  • Manufacturer or supplier name of the
    manufacturer and name of the supplier if
    different.
  • Procurement specification reference of the
    procurement specification with, if considered
    useful, issue, revision and date. It may be
    replaced by a national or international
    specification if this exists and identifies the
    source of procurement if relevant.
  • COLUMN 5 Elementary function, main
    characteristics
  • The function of the mechanical part shall be
    entered.
  • The main characteristics of the mechanical part
    shall be entered, e.g. number of revolutions per
    minute for a ball bearing.
  • COLUMN 6 Use and location
  • The codes entered (6.1) shall define the location
    of the mechanical part with respect to the
  • subsystem,
  • particular piece of equipment (box or item),
  • location within the equipment, and
  • use of the equipment.
  • The subcontractors name shall be identified by a
    project agreed user code (6.2).

43
CONTENT of DMPL, cont
COLUMN 7 Environmental code The environmental
code is defined using
Radiation/UV/ATOX (1) R Ambiance A Temperature (2) T
G Geostationnary L Low orbit B Radiation belts I Interplanetary S outside shadow L outside light V Vacuum H Hermetic M Manned E Elevated pressure 1 0 to 100 K 2 101 to 200 K 3 201 to 300 K " etc.
(1) For materials inside the spacecraft, choose a
letter from the left-hand column. For materials
on the surface of the spacecraft, combine this
letter with "L" or "S". (2) Thermal cycling to
be indicated by two values, e.g. 3/5. (3) "RT"
can be accepted as a code between 283 K (10 C)
and 313 K (40 C).
44
CONTENT of DMPL, cont
COLUMN 8 Criticality Mechanical parts shall be
considered either as critical C or non-critical
N. If a mechanical part is considered critical
the reason for the criticality and methods of
control shall be entered. COLUMN 9 Supplier
justification and approval The purpose of the
supplier justification and approval fields shall
be to enter any additional information that can
be necessary in order to achieve customer
approval. This information comprises reference
and issue of the RFA or approval, mechanical
parts justification file, evaluation reports and
deviation requests. These documents shall be made
available to the final customer on request. In
order to justify the use of a mechanical part,
reference shall be given to the relevant test
data that demonstrate acceptability of the
mechanical part under the environment conditions
and the application relevant to the particular
project concerned. Standard abbreviations shall
be used to summarize the acceptance status of a
mechanical part for a particular property. These
shall be defined by the customer. The supplier
approval status code shall be selected from the
next table. COLUMN 10 The customer approval
status code shall be selected from the
table. Additional comments shall be included
where appropriate.
45
CONTENT of DMPL, cont
Approval status Code Description A Approved
All mechanical parts classified A may be used
without restriction. X Approved with a RFA
These mechanical parts shall be subjected to an
evaluation or validation programme. The RFA
number shall be entered as a comment. W Approved
with a waiver These mechanical parts do not
meet the requirements but are used for
functional reasons. The use of such mechanical
parts shall be reduced to a minimum. All
deviation requests shall be approved by the
customer. The waiver number shall be entered as
a comment. P Pending a decision Mechanical
parts for which an evaluation report or a waiver
is waiting for the contractors provisional or
definitive approval. O Open New mechanical
parts or mechanical parts for which
investigations and qualifications are in
progress. R Rejected. D Deleted This
classification is used for a mechanical part
which is no longer used. Comments shall be
entered wherever approval cannot be given.
46
The Request for Approval(RFA)
  • This is a document with which the user asks the
    customer for permission to use a
  • critical mechanical part, material or process.
  • The information given shall make possible to
    judge whether the critical mechanical
  • part, material or process is appropriate for the
    application envisaged.
  • Two issues of this are required
  • Issue 0 Request accompanied by the evaluation or
    validation / qualification programme
  • Issue 1 Request accompanied by the validation or
    qualification results.
  • (Definition from ECSS- Q- 70B Draft)

47
The RFA (cont)
For critical PMP the supplier shall submit an
RFA, suitable formats are given in PSS- 01- 700
and ECSS- Q- 70B (Draft). The initial issue
(Issue 0) of the RFA for provisional approval
should be provided as early as possible and not
later than PDR. This approval gives agreement to
perform the evaluation / validation /
qualification programmes and allows the PMP to be
included in the design process. Definitive
approval is only given after successful
completion of the relevant test programme at
which time the RFA is updated with the relevant
test report references etc and reissued (Issue 1)
in its final form. This should be complete prior
to CDR such that the material can be used in
flight hardware construction.
48
Request for Approval (RFA)Request for Deviation
(RFD)Request for Waiver (RFA)
There is, unfortunately, much confusion
surrounding the use of the above terms.
Strictly speaking they should be used as
follows RFA Document which asks customer
permission to use a critical part, material or
process. RFD Document which asks customer
permission to use a part, material or process
which does not meet one or more of the
specified requirements (e. g. material which
fails outgassing, is flammable, etc.). The
document includes rationale for acceptance.
This RFD would be applicable for all subsequent
items manufactured. RFW Document which asks
customer permission to use a part, material or
process where as a result of inspection etc. a
non conformance has been identified (e. g. hole
drilled in wrong place, non acceptable adhesive
used etc.). This RFW would be applicable to
this one item only.
49
RFA - RFD - RFA
  • European companies and ESA are more used to using
    the term RFW to cover both RFD and RFW. The RFD
    is called up in ECSS documentation (not
    consistently) and it is not uncommon to find a
    statement of work where, for example, ECSS- Q-
    70A is a requirements document, that a specific
    change from the use of the term RFD to RFW is
    included.
  • On manned space projects, the term RFA is used in
    place of the RFD / RFW to give a rationale for
    approval for safety critical materials and
    mechanical parts (equivalent to the NASA
    materials usage agreement, MUA). One added
    complication is that the format of the RFA is
    different to that given in either PSS- 01- 700 or
    ECSS- Q- 70B (draft) and the two should not be
    confused.

50
RFA for Materials Certification
As mentioned earlier on manned space programmes
on RFA is used to justify the use of materials /
mechanical parts which do not meet the materials
requirements related to specify (flammability,
offgassing and stress corrosion). Some examples
of completed RFAs are attached.
51
PMP Flow chart
52
Material RFA -1
53
Material RFA -2
54
Mechanical part RFA-1
55
Mechanical part RFA-2
56
Process RFA-1
57
Process RFA-2
Write a Comment
User Comments (0)
About PowerShow.com