Title: Passaic River Sediment Cleanup Phase 1
1Passaic River Sediment Cleanup - Phase 1
- Public Meeting on the Proposed Cleanup Plan
- December 2, 2008
Imagine the result
2About Tonight
- Thank you for taking the time to come
- Public comment is being taken on Phase 1 of the
Passaic River contaminated sediment cleanup
project - Goals for tonights meeting
- The agenda
- Requests
3How the Cleanup Began..
- Spring 2008 Tierra Solutions, Inc (Tierra)
proposed a cleanup in front of the Diamond Alkali
site - EPA and New Jersey DEP determined what work
should be done - June 2008 EPA authorized an accelerated form of
sediment cleanup (the removal) - Nov 19, 2008 Phase 1 engineering studies
completed and released to the public
4Sediment Cleanup The Agreement
- June 23, 2008 Tierra Occidental Chemical
agreed to pay for and perform the Phase 1 and
Phase 2 cleanups - 200,000 cubic yards of the most contaminated
sediment will be taken out of the river bed next
to the Diamond Alkali site - Work will be done in two separate phases, each
with its own engineering study and cleanup
proposal - Phase 1 construction is expected to begin in the
fall of 2010
5Sediment Cleanup The Agreement
- Phase 1 digging up 40,000 cubic yards of the
worst sediment, behind a barrier, transported
out-of-state for treatment disposal - Phase 2 digging up 160,000 cubic yards of
lesser-contaminated sediment, behind a barrier,
transported and placed in an engineered
containment structure in the Newark Bay region
6Sediment Cleanup The Requirements
- Biggest source of dioxin to be dredged out of the
river - Work performed behind a barrier to prevent
movement of sediment - Process contaminated sediment on nearby land
- Transport contaminated sediment to a disposal
facility in sealed containers to prevent spillage - Restore the dredged work area
7Regional View
8Phase 1 Removal Area
9Sediment Cleanup
- What we hope to achieve through the cleanup
- Why were doing this now and why the accelerated
form of cleanup - Tierra performs the work
- EPA oversees all work in collaboration with New
Jersey DEP - EPA consults with public throughout
10Sediment Cleanup What It Is
- The first installment of a much bigger Passaic
River effort (doesnt address all problems in the
lower Passaic) - Pulls out a large amount of the dioxin in the
river along with numerous other contaminants
11Work Continues on Other Passaic River Projects
- Other companies are performing studies on the
lower 17 miles of the Passaic - EPA continues to develop cleanup options for the
lower 8 miles of the Passaic
12(No Transcript)
13Sediment Cleanup Future Decisions
- How the Phase 1 sediments will be transported out
of the region - Where the worst sediments (Phase 1) will be
treated and disposed of - How the sediments will be treated
14Major Considerations in Designing the Phase 1
Cleanup
- Minimize Impacts to Community
- Community Health Safety Plan
- Clean diesel
- Protect Structures During Cleanup
- Floodwall in front of Diamond Alkali site
- Bulkhead in front of Sherwin-Williams site
- Barrier surrounding dredging area
15Major Considerations in Designing the Phase 1
Cleanup (Cont.)
- Proper characterization and disposal of
contaminated materials - Minimize impacts to river outside of cleanup area
16Engineering Evaluation Summary
- Evaluated four options for removing the
contaminated sediments - Used proven and reliable technologies
- Used EPA criteria
- All four options have many common features
17Common Features of the Alternatives
- Work done within barrier
- Sediment/Debris removal
- Materials separation
- Material dewatering
- Water treatment
- Transport, treatment and disposal out of state
- Sediment replacement
18Work Area Barrier
- Walls will isolate dredging from rest of the
river
19Sediment Removal - Mechanical
- Clamshell
- Mechanical Excavator
http//education.usace.army.mil/navigation/lessons
/6/dredgels6lv2.html
20Sediment Removal - Hydraulic
21Debris Handling
- Expect to encounter large small debris
- Will manage on-site and dispose off-site
22On Site Materials Separation
- Once dredged, need to remove the larger solids
23Materials Dewatering - Mechanical
24Materials Dewatering - Geotube
25Water Treatment
- Water produced during operations will be treated
on-site - Treated water to go to Passaic (must meet safety
standards before discharge)
26Transport of Sediment Out-of-State
- Strong preference for rail or barge
- Transport of sealed water-tight containers
27Sediment Treatment and Disposal Out-of-State
- Incineration Landfill
- Landfill
28Possible Treatment/Disposal Sites
29Replacing the Contaminated Sediment
- Use dredging-type equipment
- Replace with similar material
- Look to restore surface
30We Looked at Four Cleanup Options
- Alternative A
- Hydraulic dredging with geotextile tube sediment
dewatering - Alternative B
- Hydraulic dredging with mechanical sediment
dewatering - Alternative C
- Mechanical dredging with mechanical dewatering
- Alternative D
- High-solids pump dredging with mechanical
dewatering
31Alternative A Hydraulic Dredging With Geotextile
Tube Dewatering
32Alternative B Hydraulic Dredging With Mechanical
Dewatering
33Alternative C Mechanical Dredging With
Mechanical Dewatering
34Alternative D High-Solids Pump Dredging With
Mechanical Dewatering
35EPAs Preferred Cleanup Option
36How EPA Evaluates Cleanup Alternatives
- Analyze cleanup alternatives for effectiveness,
cost implementability - Compare alternatives for consistency with state
and federal requirements
37Mechanical Dredging
- Clamshell
- Environmental Bucket
38Dredging Controls
39Mechanical Dewatering
- Filter or belt press
-
- Squeeze material to remove as much
- water as possible
Filter Cake out of Third Stage
Second Stage on Belt
40Overhead View of Work Area
41Cross-Section of Work Area
42Mechanical Dredging is Best Because
- Best-suited to dredging in areas containing
debris - Most likely to avoid major delays in the cleanup
schedule - Better control and more precise in areas with
debris and near structures like the floodwall and
bulkhead
43Mechanical Dewatering is Best Because
- Most effective for sediments like those contained
in the river - Most likely to avoid major delays in the cleanup
schedule - Requires less space on nearby land to do the
dewatering
44The Communitys Role in Cleanup
45We Need Your Input
- Now, on EPAs proposal to use mechanical removal
and mechanical processing of Phase 1 sediment - Comment period on the Proposed Plan runs through
December 19
46We Need Your Input
- Later, during the design of the Phase 1 cleanup
- Later, throughout the Phase 1 cleanup, which
begins in 2010 - Later, on the Phase 2 cleanup plan selection and
design of the Phase 2 cleanup
47 Community Involvement Plan
- Draft plan developed by EPA companion plan to
Lower Passaic River Restoration Project Newark
Bay Study - Based on community interviews (see handout)
- Guides public involvement during both phases of
cleanup - Plan finalized by February, updated as needed
thereafter
48Some of the Ways to Inform and Involve You
- Web site _at_ www.epa.gov/region02/npl/diamondalkali
- Email
- Listserv (electronic group notices)
- Public meetings information sessions
- Fact Sheets
- Workshops on special topics
49Some of the Ways to Inform and Involve You
(Continued)
- Coordination with environmental community
groups - Project update meetings with agencies and
stakeholders - Technical assistance (grants and contracts)
- Media updates, tours, events
- Tollfree hotline _at_ 1-800-346-5009
50Some of the Ways to Inform and Involve You
(Continued)
- Updating federal, state and local officials
- Information repository (Newark Public Library
New Jersey reference section) - Public comment on selection of cleanup plans
- Educational outreach with schools
51Technical Assistance Support
- Passaic River Coalition received a grant from EPA
to fund technical assistance support for
communities - Passaic River Coalition can be contacted at (908)
222-0315 and at www.passaicriver.org - Technical Assistance Support for Communities
(TASC) an EPA-funded contract for hiring experts
to assist on discrete products/issues
52Community Health Safety Plan
- A plan specifically devoted to protecting the
local community during cleanup - Developed during design with community input
- Anticipated timeframe for developing a draft plan
is mid-2009
53Getting to Cleanup
- After public comment on Phase 1 cleanup proposal,
EPA selects cleanup plan through Action Memo - Tierra submits Removal Design Work Plan and
schedule for work to EPA for review approval
54Removal Design Work Plan
- Describes the process and schedule for developing
detailed design plans such as - Sampling plans
- Health and safety plans
- Sediment excavation and enclosure plans
- Transportation plans for disposal out-of-state
- Water treatment plans
55Your Input is Crucial
- The Design Phase will answer many questions
- How the work will be done to minimize impacts to
the local community - How the sediments will be transported out of the
region - Where and how the sediments will be treated and
disposed
56Anticipated Phase 1 Timeline
Oct. 2008Phase 1 EE/CA submitted to USEPA
Phase 1 Action Memo issued by USEPA (Anticipated)
2008
2011
2010
2009
Phase 1 Design (Anticipated) With Public
Involvement
Phase 1 Work (Anticipated)
Sept. 2008 Phase 1 EE/CA Work Plan Finalized
USEPA review and Public comment on Phase 1 EE/CA
(Anticipated)
57Questions?