Title: NOAAs Construction WorkInProgress CWIP
1NOAAsConstruction Work-In-Progress (CWIP)
- Presented by
- NOAAs Finance Office
- April 2008
2Purpose of Presentation
- To provide an overview of NOAAs CWIP process and
some current areas of concern in the CWIP process - To familiarize NOAA personnel who deal with
financial management on the - Concepts of CWIP so they can recognize likely
CWIP projects - Major steps and regular actions needed
- Reporting requirements for CWIP projects
- NOTE
- This does not fulfill requirement for annual
CWIP training
3Presentation Overview
- Underlying Concepts
- CWIP What is it?
- Why care about CWIP?
- Issues Obstacles
- Non-Compliance
- FY2007 Audit Findings
- Program Review
- CWIP Policy Procedures
- Next Steps
4Underlying Concepts
- Obligations (delivered obligations, not
undelivered) incurred by a program each FY are
either capitalized or expensed - Amounts capitalized relate to the acquisition of
a capital asset - Value of capital asset is consumed over a period
of 2 or more years remains a NOAA asset for
useful life of the asset - Amounts expensed are deemed to be consumed within
a period of one year or whose value is below the
capitalization threshold
5Underlying Concepts
- Assets purchased off the shelf are capitalized
upon delivery (if meet capitalization threshold) - Some assets require time to deliver/complete or
include costs associated with design, site
preparation, planning, installation, etc. - The constructed asset costs are not completed
depreciated until the project is completed
instead costs are tracked and recorded in asset
holding accounting, such as the CWIP account
6CWIP What is it?Definitions Criteria
- Temporary asset holding account used to track
cost during the design construction of PPE - Capital asset in NOAAs financial statements
- Eventually depreciated over assets useful life
in NOAAs financial statements upon completion of
the project - Criteria for CWIP (must meet all 4 conditions)
- Aggregate acquisition cost of 200K or more, and
- Estimated service life of 2 years or more, and
- Long-term economic benefit to the organization
which maintains or obtains control, and - Not intended for sale in the ordinary course of
operations
7CWIP What is it?Definitions Criteria
- Determinations must be made for capital
improvement projects to property projects that
extend the useful life or enlarges/improves the
capacity of the asset will be capitalized - MUST be treated as a CWIP project
- References to bulk purchase has been removed
from CWIP documentation - Not special to CWIP unless part of CWIP
- follows personal property requirements
- CWIP process must be followed even if a project,
which will result in the capitalization of the
asset, is expected to begin finish in the same
FY
8CWIP What is it?Categories/Groups
- 3 major groups of assets generally capitalized
may require the use of the CWIP process - Real Property
- Construction or significant improvement of a
facility - Personal Property
- Acquisition, development, construction or
installation of equipment or asset which is not
real property, or - Significant improvement or modification to the
original - Internal Use Software in Development
- Development or modification to software used
internally
9CWIP What is it?Categories/Groups
- Internal Use Software in Development (IUSD)
- MUST Follow CWIP Policy Procedures
- along with Internal Use Software Guidance found
in the NOAA Finance Handbook - Software developed for internal use falls within
the parameters of CWIP (even though CBS project
type is IUSD/IUSDC) - IUSD is a subset of CWIP
10CWIP What is it?Accounts
- CBS Treasurys USSGL reflects
- CWIP activity in Account 1720
- IUSD activity in Account 1832
- The costs remain in the CWIP/IUSD accounts until
the PPE has been delivered accepted by NOAA
(placed in service, commissioned, etc.)
11CWIP What is it?Still not sure its CWIP?
- If there is even the slightest possibility that
any activity may require CWIP handling, please
contact the OCAO PPMD /or PPMB for guidance to
verify before any obligations are incurred to
avoid considerable difficulties in getting the
data corrected in the accounting system
12Why care about CWIP?
- CFO Act of 1990
- Improve the government's financial management,
outlining standards of financial performance
disclosure - Ensure more effective general financial
management practices to the Federal government
through statutory provisions - FASABs Federal Financial Accounting Standards 6
Accounting for PPE - Support capitalized PPE and depreciation
components of NOAAs financial statements
13Why care about CWIP?
- CWIP is material to NOAA DoC Financial
Statements - As of 9/30/2007, NOAA CWIP totaled 3.2 billion
- CWIP (including IUSD) comprised of
- PPE 67 of NOAA (4.8 billion) / 56 of DoC
(5.7 billion) - Assets 35 of NOAA (9.2 billion) / 23 of DoC
(14.2 billion)
14Why care about CWIP?How Big is NOAA?Based on
September 30, 2007 Data
15Why care about CWIP?How Big is NOAA?Based on
September 30, 2007 Data
16Why care about CWIP?How Big is NOAA?Based on
September 30, 2007 Data
17Why care about CWIP?How Big is NOAA?Based on
September 30, 2007 Data
18Why care about CWIP?
- DoC will FAIL
- annual financial audit
- if NOAAs CWIP balances
- are not fairly stated
19Why care about CWIP?
20Issues Obstacles
- 1 Issue is Non-Compliance with CWIP Policy and
Procedures - Lack of ownership for CWIP responsibilities
throughout NOAA community - Lack of understanding roles responsibilities
- Incomplete mandatory annual CWIP training
- New Repeat audit findings for CWIP
- CWIP Project Activity Managers are not familiar
with /or knowledgeable of CWIP policies
procedures
21Non-Compliance
- Incomplete CWIP training its mandatory
- Lack of supporting documentation or adequate
records kept by CWIP Activity Managers in CWIP
documentation files - Support of costs capitalized on NF 37-6 Report
of Property Constructed monthly CWIP
reconciliations - Incorrect capitalization of costs
- CWIP Activity Managers should know how to
differentiate between CWIP and non-CWIP costs
ensure all project costs are charged to
appropriate project codes capital vs. expense
22Non-Compliance
- CWIP CBS Project Codes
- Incorrect project code structure for CWIP
projects - Incorrect project type assignment for CWIP
projects - Incorrect accounting information assigned at
onset of projects classified as CWIP activities - Incorrect establishment/use of non-CWIP projects
(expensed costs) for valid CWIP activity - Incomplete inaccurate of monthly CWIP
reconciliations (adherence to instructions)
23FY2007 Audit Findings
FY 2007 Other consists of 3 Leases, 2 Real
Property, 1 Cost Allocation, 1 Payroll, 1
Accounts Payable, 1 CBS queries and 1 Journal
Entries.
24FY2007 Audit Findings
- 19 Property NFRs, 10 CWIP
- We did not concur with all NFRs
25FY2007 Audit Findings
- CWIP-specific NFRs, include
- Improper accounting of prepayments/advances for
CWIP/Property - Must ensure to identify amounts prepaid/advanced
vs. work completed report to FO quarterly - Timeliness of asset transfer from CWIP to asset
account from date placed into service - Must ensure NF37-6 is completed submitted
within same calendar quarter the activity reaches
BOD or substantial completion
26FY2007 Audit Findings
- CWIP-specific NFRs, include, continued
- Monthly CWIP reconciliations
- Unexplained differences identified resolved
- Must ensure differences are corrected within 4
weeks - CWIP Activity Managers should be able to provide
documented evidence for amounts reported in CWIP
Activity Managers Uncapitalized Cost column - Must ensure CWIP documentation file contains
documentation required to support costs - Incorrect amounts classified as CWIP, should be
expensed - Must allocate costs correctly between CWIP
(capital) non-CWIP (expense) codes
27Program Review
- Why is a program review being conducted?
- Significant increase in the number of audit
findings during FY 2007 Financial Statement
audit. - Objective of Review
- To determine whether there is adequate supporting
documentation for CWIP projects costs.
28Program Review
- Process
- Document processing reviewing of CWIP project
costs - Interview program finance staff to determine
- How CWIP costs are actually being processed
reviewed - Roles responsibilities for individuals involved
with processing CWIP project costs - Conduct direct testing of CWIP reconciliations
records from sample of CWIP projects - Issue report with recommendations
- Responsible LO/SOs will be required to develop
CAPs
29CWIP Policy Procedures
- Updates
- Roles Responsibilities
- Mandatory Annual CWIP Training
- CBS Project Code Assignments
- CWIP Costs
- CWIP Activities Funded by Reimbursables
- Documentation Requirements
- Transferring Assets from CWIP to PPE
- Incomplete/Impaired CWIP
- Advances/Prepayments for CWIP
- Internal Use Software In Development
- Appendices
- Figures
- NOAA CWIP Contacts
- Phase 2
30CWIP Policy ProceduresUpdates
- CWIP Policy and Procedures Updated April 08
- Effective May 1, 2008
- Updates included
- Revisions (including editorial)
- Clarifications
- Expansion of available information
- Additions (including new requirements)
31CWIP Policy ProceduresUpdates
- Clarification/Expansion of
- Roles responsibilities for the CWIP process,
including responsibilities for - OCAO OCFO
- CWIP Project Activity Managers
- CFOs and NOAA CAO (Deputy CAO)
- Mandatory CWIP Training
- Mandatory annual CWIP training (from FY2007)
- Expansion on training responsibilities
32CWIP Policy ProceduresUpdates
- New Requirements
- Formal analysis required to determine asset
impairment, if any - Must be completed annually
- CFO/CAO (Deputy CAO) certifications for all NF
37-6s - Prior to submission to FO-FSB
- Advance/prepaid amounts for CWIP activities
- Quarterly data call submission required
33CWIP Policy ProceduresUpdates
- Specific asset guidance added for assets involved
with CWIP activities - Spare parts, outfitting costs, PPE integral
non-integral to CWIP asset, etc. - Revised NF 37-6
- Consolidated Real Personal Property
- Prior versions will not be accepted
34CWIP Policy ProceduresUpdates
- New NF 37-6 checklists for review certification
- CWIP Activity Managers
- CFO/CAO (Deputy CAO)
- CWIP Policy Procedures Contact Information
within different NOAA Offices (OCAO, OCFO)
35CWIP Policy ProceduresUpdates
- Revised/New appendices, explaining in detail,
specific aspects of CWIP - Preparing reviewing the NF 37-6
- OMAO Ship Construction/Purchases, Upgrades
Modifications (not yet finalized) New - CWIP Documentation File (What should be included)
- Includes standard DW Discoverer Query to
standardize the CBS CWIP accounting charges that
need to be certified by the CWIP Activity Manager
(not yet finalized) - Must request access to Data Warehouse FMC
Business Area
36CWIP Policy ProceduresUpdates
- Revised/New appendices, explaining in detail,
specific aspects of CWIP, continued - Impairment analysis information New
- Memo from NOAA CFO (February 2008) for CWIP
Activity Manager Responsibilities - Understanding the CBS CWIP Report (CA500D) New
- Advanced/Prepaid Amounts for CWIP Activities
Template New - Frequently Asked Questions New
- CWIP Process Flowchart New
37CWIP Policy ProceduresRoles Responsibilities
Overall
- OCAOs Project Planning Management Division
(PPMD) Personal Property Management Branch
(PPMB) - Overall responsibility for oversight of NOAAs
CWIP activities, policies and procedures - Responsible for
- Providing guidance on NOAA CWIP Policy
Procedures - Reviewing providing guidance to the LO/SO in
determination as to whether an activity will
result in a CWIP activity and of the policies for
capitalization of personal and real property - Reviewing NF 37-6s CWIP documentation files to
ensure the accuracy of costs included in the CWIP
asset - Annual CWIP training program
38CWIP Policy ProceduresRoles Responsibilities
Overall
- OCFOs Finance Office (FO)
- Responsible for
- Providing guidance to ensure policies
procedures are consistent with external
accounting requirements (FASAB) - Issuing, interpreting, monitoring maintaining
CWIP ( IUSD) guidance - OCFOs Budget Execution Division (BEX)
- Responsible for maintaining CWIP Activity Listing
database -
- OCFOs BEXs role in the CWIP process is
currently under review TBD
39CWIP Policy ProceduresRoles Responsibilities
Overall
- OCAOs PPMB/OCIO/FO
- Responsible for the policies procedures for
capitalization of Internal Use Software
40CWIP Policy ProceduresRoles Responsibilities
Overall
- Line/Staff Offices Management Staff
- Responsible for
- Designating a CWIP Project Manager CWIP
Activity Manager for each activity - Ensuring CWIP requirements are established before
expending the funds - Ensuring compliance with policies procedures
- CWIP Project/Activity Managers
- Responsible for adhering to all CWIP policies
procedures ensuring compliance
41CWIP Policy ProceduresRoles Responsibilities
LO CFOs NOAA CAO
- LO CFOs NOAA CAO (Deputy CAO) responsible
for - Adhering to all CWIP policies procedures
- Ensuring all staff interacting with CWIP
activities adhere to all CWIP policies
procedures - Ensuring Managers (Project Activity) are
designated for each CWIP activity - Ensuring CWIP reconciliations are completed
submitted monthly by established due dates - Review certify the CWIP reconciliations (can be
delegated to MB Chiefs)
42CWIP Policy ProceduresRoles Responsibilities
LO CFOs NOAA CAO
- LO CFOs NOAA CAO (Deputy CAO) responsible
for - Ensuring mandatory CWIP training is completed
annually, or within established window of newly
designated CWIP Project/Activity Managers - Reviewing certifying the NF 37-6 (cannot be
delegated to MB Chiefs can be delegated to
Deputy CAO) - NEW Effective 5/1/2008
- Ensuring NF 37-6s are completed reported in the
calendar quarter the CWIP activity are placed
into service (accepted, delivered, occupied,
commissioned)
43CWIP Policy ProceduresRoles Responsibilities
LO Headquarters Offices
- LO Headquarters Office responsible for
- Adhering to all CWIP policies procedures
- Providing construction needs funding
- Establishing CBS Project Code for CWIP
activities, including - CWIP project codes
- Non-CWIP project codes
- Depreciation project codes
- Incidental administrative cost project codes
- Ensuring all CWIP project codes are set up
properly by utilizing the unique CBS CWIP project
code structure - Take corrective action immediately when project
codes set up incorrectly have been identified
44CWIP Policy ProceduresRoles Responsibilities
CWIP Project Managers
- CWIP Project Managers responsible for
- Adhering to all CWIP policies procedures
- Providing construction management support
- Providing CWIP documentation to CWIP Activity
Manager - CWIP Determination Letter estimated schedules,
including dates and costs award obligating
documents (prior to obtaining authorizations)
related invoices - Completing mandatory CWIP training annually (or
within 30 days of CWIP Project Manager
designation) - Ensuring correct accounting codes are used on
transactions
45CWIP Policy ProceduresRoles Responsibilities
CWIP Activity Managers
- CWIP Activity Managers
- Defined as the individual who maintains
obligating documents for a CWIP activity
collect, record verify all costs, including
direct incidental labor associated with the
CWIP activity - Overall responsibility for the financial
budgetary activities accuracy of the valuation
of the CWIP asset
46CWIP Policy ProceduresRoles Responsibilities
CWIP Activity Managers
- CWIP Activity Managers responsible for
- Adhering to all CWIP policies procedures
- It is imperative that all designated CWIP
Activity Managers have a thorough understanding
of the CWIP policies procedures - Maintaining quantitative financial control over
each CWIP activity - Completing mandatory CWIP training annually (or
within 30 days of CWIP Activity Manager
designation) - Ensuring all CWIP projects are set up correctly
at the onset of the project - Take corrective action immediately when project
codes set up incorrectly have been identified
47CWIP Policy ProceduresRoles Responsibilities
CWIP Activity Managers
- CWIP Activity Managers responsible for,
continued - Preparing forwarding necessary information to
appropriate personnel (cost estimates, schedules
of completion, etc.) - Ensuring all CWIP project codes are set up
properly by utilizing the unique CBS CWIP project
code structure - Take corrective action immediately when project
codes set up incorrectly have been identified - Ensuring correct accounting codes are used on
transactions - Reviewing all obligating documents for CWIP
compliance - Take corrective action immediately when project
codes set up incorrectly have been identified - Capturing allocating all costs correctly, both
capital expense
48CWIP Policy ProceduresRoles Responsibilities
CWIP Activity Managers
- CWIP Activity Managers responsible for,
continued - Monthly CWIP Reconciliations
- Performing monthly reviews of the accuracy of CBS
balances for all costs in CWIP accounts - Preparing monthly reconciliations (CWIP
Reconciliation Template) for all costs in CWIP
documentation file CBS balances - Must ensure completeness accuracy for all CWIP
costs - Identifying properly all differences
adjustments necessary - Must provide explanations with adequate detail
- Must resolve all differences within 4 weeks of
noted difference - Ensuring CFO/MB Chiefs/CAO (Deputy CAO) review
certify accuracy completion of monthly CWIP
reconciliations - Ensuring timely submission of monthly CWIP
reconciliations, approved by CFO/MB Chiefs/CAO
(Deputy CAO)
49CWIP Policy ProceduresRoles Responsibilities
CWIP Activity Managers
- CWIP Activity Managers responsible for,
continued - NF 37-6 Report of Property Constructed
- Ensuring CFO/CAO (Deputy CAO) review certify
the accuracy completion of all NF 37-6s for
completed CWIP activities - Ensuring timely submission of CFO/CAO approved NF
37-6s to transfer costs of CWIP activities
immediately once a constructed property item is
placed into service or accepted - Submitting amended NF 37-6 for review
certification, if necessary - If total capitalized amount differs from amount
recorded earlier - Ensuring CWIP project type changed from
CWIP/IUSD to CWIPC/IUSDC for completed CWIP
activities to allow purge from CBS CWIP Report
(CA500D)
50CWIP Policy ProceduresRoles Responsibilities
CWIP Activity Managers
- CWIP Activity Managers responsible for
- Maintaining a CWIP documentation file, including
copies of invoices CBS reports - Ensuring files are complete accurate support
full CWIP costs of the activity support CWIP
amounts on CBS CWIP Report (CA500D) support
costs on NF 37-6 - Ensuring formal impairment analysis is performed
annually, at a minimum, on all open CWIP projects
(both real personal property) provided to FO - By Q3 Financial Statement Data Call
- Identifying amounts prepaid/advanced for CWIP
activities vs. work actually completed
51CWIP Policy ProceduresRoles Responsibilities
Designated Financial Representatives
- Designated Financial Representatives
- Identified as other individuals who can also be
listed on the CWIP Activity Listing as the person
designated to assist the CWIP Activity Manager
for - Preparation accuracy of the reconciliations
- Maintenance of documentation for program costs
- CWIP Activity Managers still have the
ultimate responsibility for the overall CWIP
activity must ensure CWIP policies procedures
are properly carried out
52CWIP Policy ProceduresMandatory Annual CWIP
Training
- ALL
- CWIP Project Managers
- CWIP Activity Managers
- must complete mandatory
- CWIP training,
- on an annual basis!
53CWIP Policy ProceduresMandatory Annual CWIP
Training
- Newly appointed CWIP Project/Activity Managers
have one month of appointment to complete the
mandatory CWIP training - OCAOs PPMD PPMB are responsible for the annual
CWIP training program (coordinating, publishing,
tracking, etc.) - CWIP Project Managers CWIP Activity Managers,
who do not complete the mandatory CWIP training
within established time frames, will be reported
to appropriate senior management of LO/SO
54CWIP Policy ProceduresCBS Project Code
Assignments
- A CWIP activity must have, at a minimum, two
unique CBS project codes assigned - CWIP project code to capture all costs
associated with that activity to be capitalized
(will have a CBS project type of CWIP or IUSD)
- Non-CWIP project code to capture costs
associated with the CWIP activity not to be
capitalized as part of the CWIP project, but
instead, expensed (will have a CBS project type
of something other than CWIP or IUSD) - Separate distinct set of CBS project codes must
also be established for annual cost adjustments
of incidental administrative costs from a
funded non-CWIP related project code to a CWIP
project code - See slide on Project TYPES
55CWIP Policy ProceduresCBS Project Code
Assignments
- It is imperative the appropriate unique CWIP
project code structure is followed when assigning
project codes to CWIP activities (CWIP Report,
UPR, Policy, Auditors) - The CWIP Activity Manager will be required to
make corrections when non-compliant project codes
are identified - Reimbursable project codes for CWIP activities
funded by an outside source, through reimbursable
funding, will not follow the same CWIP project
code structure, nor will they be reported in the
same CBS Fund Code as other CWIP project codes
56CWIP Policy ProceduresCBS Project Code
Assignments
- CBS Project Code TYPES each CBS project code
is assigned a project TYPE. - For capital (not expensed) CWIP project codes,
project TYPE must be CWIP (or IUSD) during the
construction or development of the activity - For completed activities, the CWIP Activity
Manager should notify FO-FSB to change project
type in CBS to CWIPC (or IUSDC) - Required for CBS CWIP Report (CA500D) PURGE
(Appendix N)
57CWIP Policy ProceduresCBS Project Code
Assignments
- ORF Direct Funded CBS CWIP Project Code Structure
(13_1450 Treasury symbols) - 2nd position of CBS project code should be a 4
(i.e., x4xxxxx) - PAC Direct Funded CBS CWIP Project Code Structure
(13_1460 Treasury symbols) - 2nd position of CBS project code should be a 2
AND 4th position should be F (i.e., x2xFxxx) - Both conditions must exist in PAC project codes
58CWIP Policy ProceduresCWIP Costs
- CWIP Activity Managers are responsible for
reviewing all obligating documents determining
that each cost charged to the CWIP activity is
correctly - Capitalized as CWIP assigned to the CBS CWIP
project code - OR
- Expensed as non-CWIP assigned to the CBS
non-CWIP project code - It is the CWIP Activity Managers responsibility
to ensure that all costs, both capital expense,
are captured allocated correctly
59CWIP Policy ProceduresCWIP Costs Capital
Costs
- Specific examples of costs the CWIP Activity
Manager should include in CWIP for capitalization
are (not limited to) - Labor cost for design engineering
- Actual contract costs with modifications for
architectural engineering contract design - Storage costs of Government Funded Equipment
(GFE) delivered prior to installation date - Construction contract all modifications
- Materials all actual labor associated with
construction
60CWIP Policy ProceduresCWIP Costs Capital
Costs
- CWIP Activity Manager should include in CWIP for
capitalization (not limited to), continued - Incidental administrative costs representing
labor for procurement, finance, supervisory,
clerical and all other non-labor administrative
costs (Rates used are 3 5) - Direct labor, leave, benefits indirect costs
- Construction installation costs and generally
all ancillary costs associated with design,
delivery, project management, and testing
implementing the equipment or facility
61CWIP Policy ProceduresCWIP Costs Capital
Costs
- FASABs SFFAS 6 (Accounting for PPE) states
that costs captured shall include all costs
incurred to bring the PPE to a form location
suitable for its intended use would include
(not limited to) - Amounts paid to vendors
- Transportation charges to the point of initial
use - Labor other direct or incidental production
costs (for assets produced or constructed) - Engineering, architectural other outside
services for designs, plans, specifications
surveys - Acquisition preparation costs of buildings
other facilities
62CWIP Policy ProceduresCWIP Costs Capital
Costs
- CWIP costs should include (not limited to),
continued - An appropriate share of the cost of the equipment
facilities used in construction work - Fixed equipment related installation costs
required for activities, a building or facility - Direct costs of inspection, supervision
administration of construction contracts
construction work - Legal recording fees damage claims
- Handling storage costs
- Demolition of an existing building/structure to
prepare a site for construction of a new
building, structure or addition
63CWIP Policy ProceduresCWIP Costs Capital
Costs
- CWIP costs should include (not limited to),
continued - Fair value of facilities equipment donated to
the government by non-Federal agency - Fair value of facilities equipment
transferred to NOAA by another Federal agency
(includes amounts funded through reimbursable
funding, if ownership transfers from sponsor to
NOAA at project completion) - Material amounts of interest costs paid
- Interest costs refers to any interest paid by the
reporting entity directly to providers of goods
or services related to the acquisition or
construction of PPE - PPE integral to the CWIP asset
64CWIP Policy ProceduresCWIP Costs Capital
Costs
- PPE integral to the CWIP asset should be
included in the cost of the CWIP asset when it
meets both of the following 2 conditions - PPE is built into the CWIP asset such that its
removal would damage the asset or the PPE or
impair the intended use of the asset or the PPE - and
- PPE is immaterial relative to the related CWIP
asset. In determining materiality, both cost
useful life should be considered
65CWIP Policy ProceduresCWIP Costs Capital
Costs
- Costs of additions, alterations, betterments,
rehabilitations, replacements or upgrades that
meet the criteria for capitalization, and extend
the useful life of the asset, or
enlarges/improves its service capacity, shall be
treated as a CWIP activity
66CWIP Policy ProceduresCWIP Costs Expensed
Costs
- Specific examples of costs the CWIP Activity
Manager should not include in CWIP for
capitalization, but instead should expense, are
(not limited to) - Planning activities not resulting in final design
- Ordinary administrative supplies (i.e., copy
paper, office equipment, etc.) - PPE constructed for Research Development
intended as experimental, changing product rather
than as a finished product - Personal property equipment used for
administrative support - Non-integral PPE not meeting capitalization
threshold
67CWIP Policy ProceduresCWIP Costs Expensed
Costs
- CWIP costs should not include (not limited to),
continued - Spare parts
- Depending on overall value of spare parts,
consideration should be given to capitalizing the
parts as OMS expensing them as they are used
(By quarterly Financial Statement Data Call) - Outfitting costs not meeting capitalization
threshold - Outfitting costs meeting capitalization
threshold, with a useful life of 2 years or more,
should be capitalized separately from the CWIP
asset depreciated over the appropriate useful
life
68CWIP Policy ProceduresCWIP Costs Other
Related Capital Costs
- Other related capital costs, which should be
capitalized separately from the CWIP asset
depreciated over the appropriate useful life
include (not limited to) - Outfitting costs not meeting capitalization
threshold with a useful life of 2 years or more - Material components of a CWIP asset that meet
capitalization threshold, but expected to have a
useful life less than that of the asset - Non-integral PPE meeting capitalization threshold
69CWIP Policy ProceduresCWIP Activities Funded
by Reimbursables
- Project code structure will not follow the unique
CWIP structure for CWIP-related activity in
reimbursable funds - Project codes should be setup accounted for as
reimbursables to accurately reflect reimbursable
activity in financial reports - Costs will be included in the total value of the
CWIP activity only if the MOU transfers or
identifies the asset as belonging to NOAA at the
end of the construction project - End of CWIP activity, if NOAA plans to own the
constructed asset, the portion of the CWIP asset
funded by the reimbursable sponsor (i.e.,
Airforce, Navy, NASA, etc.) should be
"transferred" to NOAA
70CWIP Policy ProceduresCWIP Activities Funded
by Reimbursables
- At start of agreement, LO responsible for
informing the sponsor (financial reporting area)
they should be recording the funds, contributed
to NOAA through reimbursable funding, as CWIP
(SGL account 1720) on their CFO-Act financial
statements until the asset is constructed
transferred to NOAA - SLTs should not be used to adjust CWIP-related
activity from reimbursable funds into a
NOAA-appropriated fund - CWIP Activity Managers must track the CWIP costs
funded by reimbursable money on monthly CWIP
reconciliations (separate spreadsheet) to ensure
full cost accounting once the activity has been
completed
71CWIP Policy ProceduresCWIP Activities Funded
by Reimbursables
- NF 37-6s must include the NOAA-appropriated
portion (the CWIP project codes) AND the
"transferred-in" portion from the reimbursable
sponsor - Must list funding contributed by each agency
separately for appropriate intragovernmental
eliminations - FO will enter NF37-6 showing CWIP amounts
transferred-in then moving them out
capitalizing them with the remaining cost of the
CWIP asset - Property Offices must enter the total cost amount
of the asset, if NOAA owns the constructed asset,
which includes the NOAA-appropriated portion plus
the reimbursable portion, into the property
system depreciate the total amount
72CWIP Policy ProceduresDocumentation
Requirements
- It is the responsibility of the CWIP Activity
Manager to - Maintain adequate supporting documentation for
all costs included in the CWIP activities for
proper cost valuation of the asset - CWIP Activity Managers must obtain copies of, or
have access to the source documents, for any
costs included on the monthly CWIP
reconciliations on the NF 37-6 - Forward copies of supporting documentation
(reports, etc.) to the appropriate property
office for review, along with NF 37-6 for entry
into the appropriate property system
73CWIP Policy ProceduresDocumentation
Requirements
- CWIP documentation file should include minimum
requirements - Standard DW Discoverer query (FMC Business Area)
results for CWIP activities, including charges
for administrative costs (travel, training,
labor, security, etc.), by project code - Obligating documents (contract, etc.), including
Statement of Work copies of - construction or production contract all
modifications related invoices - architectural engineering contract task orders
related invoices - contracts for construction management services
related invoices - Memorandum of Understanding (MOUs)
- CWIP Determination Letter
74CWIP Policy ProceduresDocumentation
Requirements
- CWIP documentation file should include minimum
requirements - CWIP spreadsheet or planning document as a cost
documentation checklist - CD-509 Property Transaction Report for personal
property construction signed by the property
custodian - BOD Letter
- Hard copies of invoices to support the dollar
amounts reported on the NF 37-6, including IPAC
billings from other Federal agencies - Required annual calculations SLTs for
incidental administrative costs
75CWIP Policy ProceduresDocumentation
Requirements
- CWIP documentation file should include minimum
requirements, continued - CBS CWIP Report (CA500D) other related CBS
accounting reports, organized by project code
agreeing to the dollar amounts by project code
reported on the NF 37-6 - Reviewed/Verified/Certified CBS labor reports
documenting direct labor costs other CBS cost
reports - Documentation related to CWIP activities
transferred to NOAA through reimbursable funding
or outright transfers/donations - Details in Appendix K of CWIP Policy Procedures
76CWIP Policy ProceduresDocumentation
Requirements
- Documentation will be reviewed/requested for the
following reasons (not limited to) - Property office NF 37-6 review of source
documents for proper cost valuation - FO Program Review of CWIP activities
- Management Control Reviews
- Annual financial audit review of sampled CWIP
activities by contract auditors
77CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- FASABs SFFAS 6 (Accounting for PPE) states
that - PPE should be recognized when title passes to
the acquiring entity or when the PPE is
delivered to the entity or to an agent of the
entity - Completed CWIP activities must be reported on the
NF 37-6 in the calendar quarter in which the
assets are delivered or placed into service
(accepted, occupied, commissioned or operational) - Acceptance means that NOAA has agreed that the
project is substantially completed according to
specifications
78CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- PPE shall be recorded as CWIP until
- Real property Beneficial Occupancy (the
Beneficial Occupancy Date (BOD)) - BOD shall be used as the acquisition date for
purposes of depreciation - Personal property when ready for its intended
purpose placed into service - CWIP Activity Managers must initiate the NF 37-6
process to transfer assets from CWIP to PPE - Complete the NF 37-6 form
- Obtain necessary certification signatures prior
to forwarding to FO for review/certification - CWIP Activity Managers
- LO CFO or CAO (Deputy CAO)
79CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
-
- NEW
- Starting May 1, 2008, NF 37-6s received in FO
without CFO or CAO (Deputy CAO) certifications
will not be accepted
80CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- CWIP Activity Managers must initiate the NF 37-6
process to transfer assets from CWIP to PPE,
continued - FO will review the NF 37-6 to certify the
- Depreciation project code is valid active
- CWIP costs on NF 37-6 to transfer from CWIP to
PPE do not exceed current CBS CWIP Report
(CA500D) for Uncapitalized Costs
81CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- NOTE FO is not
- 1) Reviewing CWIP documentation file
- 2) Certifying accuracy of costs charged to
included in CWIP activity -
- This is the responsibility certification
of the OCAO Real/Personal Property Offices during
their review of the NF 37-6 CWIP Documentation
File prior to entering the CWIP asset into the
property systems
82CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- CWIP Activity Managers must initiate the NF 37-6
process to transfer assets from CWIP to PPE,
continued - Once NF 37-6 is accepted/certified by FO signed
copy is received, the CWIP Activity Manager must
forward NF 37-6 CWIP documentation file
supporting the costs on the NF 37-6 to the
appropriate Real/Personal Property Office for
review/certification - Once NF 37-6 is reviewed/accepted/certified by
the Property Office, the asset is entered in the
appropriate property system depreciation begins
83CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- CWIP Activity Managers must initiate the NF 37-6
process to transfer assets from CWIP to PPE,
continued - Once NF 37-6 is received back in the FO (with all
required certifications), an adjusting entry is
entered into CBS moving the amounts from CWIP to
PPE, along with associated depreciation amounts - NOTE no adjustments will be made for NF 37-6s
that do not have all the required certifications
84CWIP Policy ProceduresTransferring Assets from
CWIP to PPE
- Entire process must occur in the calendar quarter
in which the assets are delivered or placed into
service (accepted, occupied, commissioned or
operational) - Details in Appendix I of CWIP Policy Procedures
85CWIP Policy ProceduresIncomplete/Impaired CWIP
- FASB FAS 144 Accounting for the Impairment or
Disposal of Long-Lived Assets defines impairment
as the condition that exists when the carrying
amount of a long-lived asset (asset group)
exceeds its fair value. - If an impairment loss is recognized, the adjusted
net book value of the long-lived asset shall be
its new cost basis. - Require annually formal analysis to determine
permanent loss during construction or development
of real personal property CWIP assets
86CWIP Policy ProceduresIncomplete/Impaired CWIP
- CWIP Activity Managers must ensure an impairment
analysis is performed, annually, on all open real
personal property CWIP activities provide the
information to FO - Must determine if an impairment situation has
occurred determine if CWIP activity is viable or
likely to be completed - Notification required as part of the quarterly
Financial Statement Stewardship Data Call - Details in Appendix L of CWIP Policy Procedures
87CWIP Policy ProceduresAdvances/Prepayments for
CWIP
- Includes advances prepaid amounts to other
government agencies for CWIP activities (i.e.,
Navy, etc.) - CWIP Activity Manager is responsible for
- Ensuring amounts are allocated correctly
charged using the correct CWIP or related
non-CWIP project codes - Quarterly, as part of the quarterly Financial
Statement Stewardship Data Call - Identifying the amount of funds advanced/prepaid
vs. the amount of work completed to date - Preparing standard spreadsheet identifying each
project code with advanced/prepaid funds for CWIP
activities the amount of advanced/prepaid funds
completed, identified by CWIP and related
non-CWIP project codes - Format in Appendix P of CWIP Policy Procedures
88CWIP Policy ProceduresAdvances/Prepayments for
CWIP
89CWIP Policy ProceduresInternal Use Software
In Development
- Internal Use Software In Development is a
sub-set of CWIP - IUSD is the CBS project code
- Temporary holding account (SGL Account 1832) for
collecting costs during activities related to the
design development of internal use software - Any developed software, including enhancements,
which will be capitalized used internally - Must follow the CWIP policy and procedures
documentation - In order to be considered an IUSD activity, a
development project must meet all of the criteria
for CWIP activities.
90CWIP Policy ProceduresAppendices
- Appendix A Glossary of Terms
- Appendix B References (i.e., CFO Act of 1990)
- Appendix C Acronyms
- Appendix D Policy Procedures for Reporting
Construction Work-In-Progress And Capitalization
of GOES POES Satellites, Their Component
Sensors, and Related Assets - Appendix E Policy Procedures for Reporting
Construction Work-In-Progress And Capitalization
of NPOESS Satellites, Their Component Sensors and
Related Assets
91CWIP Policy ProceduresAppendices
- Appendix F CWIP Processing Flow
Responsibilities (for Real Personal Property) - Flow of the CWIP process, including different
phases of a CWIP activity required actions of
involved parties - Appendix G Example of CBS CWIP Report (CA500D)
- Appendix H Summary Level Transfer (SLT) CBS
Cost Adjustment - Appendix I Preparing Reviewing the NF 37-6
- Review Checklists
- CWIP Activity Manager
- LO CFO or NOAA CAO (Deputy CAO)
- Revised NF 37-6 FORM (for Real Personal
Property)
92CWIP Policy ProceduresAppendices
- Appendix J OMAO Ship Construction/Purchases,
Upgrades Modifications - Appendix K CWIP Documentation File (What should
be included) - Includes minimum requirements suggested file
formats - Appendix L Impairment Analysis Information
- Appendix M NOAA CFO February 2008 Memo on
Responsibilities of all CWIP Activity Managers - Appendix N Understanding the CBS CWIP Report
(CA500D) - Includes report layout columns, purge criteria,
display examples for assets transferred-in to NOAA
93CWIP Policy ProceduresAppendices
- Appendix O CWIP Reconciliation Template
Instructions - CWIP Reconciliation Template
- Review Checklists
- CWIP Activity Manager
- CFO/MB Chief/CAO (Deputy CAO)
- Appendix P Advanced/Prepaid Amounts for CWIP
Activities - Appendix Q Frequently Asked Questions
94CWIP Policy ProceduresFigures
- Figure 1 CWIP Process Flowchart
- Budget Approvals
- Project
- Planning
- Determination
- Documentation
- Reconciliation
- Capitalization
95CWIP Policy ProceduresNOAA CWIP Contacts
- OCAOs Real Property Management Division (RPMD)
- Andy Duran, Chief
- Mary Ann Whitmeyer
-
- OCAOs Project Planning Management Division
(PPMD) - Chien Le, Chief
- Bev Mooneyham
- OCAOs Personal Property Management Branch (PPMB)
- Ezekiel Dennison, Chief
- Jon Pinner
- Steven Creeger
- OCFOs Budget Execution Division (BEX)
- Jim LeDuc, Chief
- Lisa Conley
- OCFOs FO Financial Reporting Division (FRD),
Financial Statements Branch (FSB) - Mark P. Miller, Chief
- Jones Harbor
- Melvin Spencer
96CWIP Policy ProceduresPhase 2
- Finalize OMAO Ship-Specific Appendix
- Finalize standard CWIP Discoverer Query for CWIP
Documentation File (DW-FMC Business Area) - Review of Internal Use Software policy in NOAA
Finance Handbook ensure consistency
appropriate references to CWIP Policy
Procedures for developed software used internally - CWIP Activity Listing Database determine where
database maintenance belongs
97CWIP Policy ProceduresPhase 2
- Revised NF 37-6 easier to use complete
- CBS CWIP Project Code setup should approvals be
required, along w/ determination letters - Process for suggested revisions/changes to CWIP
Policy Procedures - CWIP workgroup to discuss CWIP issues potential
revisions to CWIP Policy Procedures
98Next Steps
- Phase 2 of CWIP Policy Procedure Updates
- Continued activities efforts implementing
Corrective Action Plans (CAPs) to address audit
findings - Continued communication with NOAA senior
management on progress in area of CWIP activities - Gain understanding of CWIP policies procedures,
including roles responsibilities
99Next Steps
- Complete annual CWIP training
- Compliance with CWIP policies procedures
- Proactive, not reactive
- Cooperation vs. resistance staff only trying to
help prevent future audit findings
100CWIP Website
- On OCFO-Finance Office website
- Under CWIP (left side of page)
- http//www.corporateservices.noaa.gov/finance/CWI
P.html - Policy Documentation
- Related Accounting Standards
- Forms Checklists
- Contact Information
101Questions?