RiskBased Acquisition Management RBAM - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

RiskBased Acquisition Management RBAM

Description:

Surveillance methods are evolving (oversight to insight) ... Government emphasis on commercialization. Issues of recent special focus: ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 37
Provided by: kennethas
Category:

less

Transcript and Presenter's Notes

Title: RiskBased Acquisition Management RBAM


1
Risk-Based Acquisition Management(R-BAM)
  • Ken Sateriale
  • July 27, 2000
  • ksateria_at_pop200.gsfc.nasa.gov
  • http//gsfc-artemis.gsfc.nasa.gov/210/proclib.htm

2
Major Points
  • Risk Management is a Government-wide, OMB-driven
    initiative.
  • Risk Management will drive decision making.
  • The Office of Safety and Mission Assurance leads
    Risk Management at NASA.

3
Our Challenging Environment
  • NASA is a discretionary agency - safety and
    mission success are necessary for our survival!
  • Diminished Resources (human resources and
    funding)
  • Projects are generally smaller and faster
  • Acquisition rules have changed
  • Surveillance methods are evolving (oversight to
    insight)
  • Completion form contracts/PBC are becoming the
    norm
  • Government emphasis on commercialization
  • Issues of recent special focus
  • IT Security, Export Control, Health, Environment

4
Programmatic Risks
  • Safety
  • Security
  • Environmental
  • Technical
  • Export Control
  • Cost
  • Schedule

5
Project Considerations
  • What is currently important to the project,
    management, customer, or user?
  • Are there critical milestones the project is
    currently facing?
  • What limits and constraints do the project,
    organization, group, or manager have?
  • What milestones and limits are fixed? flexible?
  • What resources are available for mitigation?
  • How does this risk fit into the overall project
    issues and concerns? When is the best time to
    address or mitigate a risk?

6
Why Manage Risk?
  • Obtain early identification of potential problems
  • Acquire essential information needed to make
    tradeoffs based on priorities and quantified
    assessments
  • Enable more efficient use of resources
  • Increase probability of mission success
  • Risk Management Proactive Project Management

7
Risk Management Background
  • OMB Circular A-11, Capital Programming Guide
  • (Effectively supercedes OMB Circular A-109,
    dated 04/05/76, Major Systems Acquisitions)
  • NASA Administrator Safety and Risk
  • Chief Engineer NPG 7120.5, NASA Program and
    Project Management Processes and Requirements
  • Office of Safety and Mission Assurance
  • CRM/New Core Competencies/NPG Updates
  • Office of Procurement Strengthen PBC

8
OMBCapital Programming Guide
  • Risk management should be central to the
    planning, budgeting, and acquisition process.
    Failure to analyze and manage the inherent risk
    in all capital asset acquisitions may contribute
    to cost overruns, schedule shortfalls, and
    acquisitions that fail to perform as expected.
    For each major capital project a risk analysis
    that includes how risks will be isolated,
    minimized, monitored, and controlled may help
    prevent these problems.

9
OMB Circular A-11Capital Programming Guide
  • Elements of Risk Management
  • Risk Assessment
  • Risk Analysis
  • Risk Treatment
  • Lessons Learned

10
Risk Assessment
  • The first step in risk management is to identify
    and assess all potential risk areas.
  • A risk area is any part of a project where there
    is an uncertainty regarding future events that
    could have a detrimental effect on meeting the
    program goal.
  • Risk assessment continues throughout the life
    cycle of a program.
  • As the program progresses, previous uncertainties
    will become known and new uncertainties will
    arise.

11
Risk Analysis
  • Once risks are identified, each risk should be
    characterized as to the likelihood of its
    occurrence and the severity of potential
    consequences.
  • Risk analysis will result in a watch list of
    potential areas of risk. The watch list may
    identify early warning signs that a problem is
    going to arise.
  • As in risk assessment, risk analysis continues
    through the life cycle of the program the watch
    list should be updated as appropriate.

12
Risk Treatment
  • After a risk has been assessed and analyzed, the
    agency should consider what to do about it.
    Alternatives include
  • Transfer
  • Avoidance
  • Reduction
  • Assumption
  • Sharing

13
NASA Administrator
  • ... accept risk, but only in an informed
    manner...consistent with our unwillingness to
    compromise the safety and health of people and
    property or do harm to the environment... I have
    designated safety and health as our highest core
    value...incorporate safety and health principles
    and practices into our daily decision-making
    processes and lives.
  • Daniel S. Goldin January 19, 1999

14
NASA Administrator
  • I request that all employees become familiar
    with failure modes and effects analysis, fault
    tree analysis, and probabilistic risk
    assessments.improved safety and mission success
    will result only from your complete, thorough,
    and across-the-board understanding and management
    of risk. Daniel S. Goldin June 1, 2000

15
Risk Management Technologies
  • Failure Modes and Effects Analysis (FMEA). The
    FMEA is a bottom-up analysis of component-level
    failures and their effects on higher-level
    systems.
  • Fault Tree Analysis (FTA). FTA is a top-down
    analysis used to evaluate specific undesired
    events. It is a deductive logic tree linking a
    top event to the combinations of sub-events that
    could cause it.
  • Probabilistic Risk Assessment (PRA). PRA is an
    analysis of the probability (or frequency) of
    occurrence of a top-level undesired event,
    including an assessment and display of our degree
    of uncertainty surrounding the probability.

16
Chief EngineerNPG 7120.5
  • Risk management is a continuous process that
    identifies risks analyzes their impact and
    prioritizes them develops and carries out plans
    for risk mitigation, acceptance, or other action
    tracks risks and the implementation of mitigation
    plans supports informed, timely, and effective
    decisions to control risks and mitigation plans
    and assures that risk information is communicated
    among all levels of a program/project. Risk
    management begins in the formulation phase with
    an initial risk identification and development of
    a Risk Management Plan and continues throughout
    the products life cycle through the disposition
    and tracking of existing and new risks.

17
Chief Engineer NPG 7120.5 Risk Management Plan
  • A Risk Management Plan (included in the NASA
  • Program/Project Plans) describes how the project
    will perform risk management, including
  • introduction
  • practice overview
  • project organization, roles, and responsibilities
  • practice details
  • risk management resources and milestones
  • risk information documentation

18
Office of Safety and Mission Assurance
  • Continuous Risk Management (CRM)
  • New Core Competencies
  • NPG Updates

19
Continuous Risk Management
  • Continuous Risk Management (CRM) is a process
    that searches for and identifies risks before
    they become problems and provides mitigation
    actions to reduce their likelihood and/or impact.
    The goal of CRM is to reduce the impact of
    issues and uncertainties on a project to an
    acceptable level.

20
Office of Safety and Mission Assurance NASAs
Continuous Risk Management Paradigm

21
Risk Management Steps
  • (1) Identify. State the risk in terms of
    condition and consequence(s) capture the context
    of the risk e.g., what, when, where, how, and
    why.
  • (2) Analyze. Evaluate risk probability,
    impact/severity, and time-frame (when action
    needs to be taken) classify/group with
    similar/related risks and prioritize.

22
Risk Management Steps
  • (3) Plan. Assign responsibility, determine
    approach (research, accept, mitigate, or
    monitor) if risk will be mitigated, define
    mitigation level (e.g., action item list or more
    detailed task plan) and goal execute plan.
  • (4) Track. Acquire/update, compile, analyze, and
    organize risk data report tracking results and
    verify and validate mitigation actions.

23
Risk Management Steps
  • (5) Control. Analyze tracking results, decide
    how to proceed (re-plan, close the risk, invoke
    contingency plans, continue tracking) execute
    the control decisions.
  • (6) Communication and documentation. These are
    present in all of the preceding functions and are
    essential for the management of risks. A system
    for documentation and tracking of risk decisions
    shall be implemented.

24
New SMA Core Competencies
  • Risk management
  • SMA plan development/surveillance plan
    development
  • System safety analysis/hazard analysis
  • Reliability analysis/modeling/testing and
    evaluation
  • Probabilistic risk assessment
  • Qualification/certification of products
  • Configuration management/process control
  • Failure/anomaly investigation/root cause analysis
  • Emergency preparedness planning

25
SMA Supporting Acquisition
  • SMA is your risk management consultant to the
    project throughout the acquisition process. SMA
  • Supports requirements development
  • Supports acquisition strategy planning
  • Supports risk management plan development
  • Supports up-front risk assessments and analyses
  • Provides risk management training as required
  • SMAs role in acquisition must be strengthened!

26
RM/CRM/R-BAM Implementation
  • OMB Circular A-11 Supplement CPG July
    1997
  • NPG 7120.5 April 1998
  • At a Glance Procurement Initiatives April
    1999
  • Procurement Information Circular April 1999
  • Procurement Notice (NFS) Proposed Rule July
    1999
  • Procurement Notice (NFS) Interim Rule June
    2000
  • NPG 8715.3, NASA Safety Program Manual January
    2000
  • NPG 8621.1, Mishap Reporting June 2000
  • NPG 8735, SMA Surveillance ... Contracts August
    2000
  • NPG 8705 Risk Management Sep 2000
  • Outreach Procurement and Technical Ongoing

27
http//satc.gsfc.nasa.gov/crm/
28
Office of Procurement Strengthen PBC Framework
  • Agency goal of 80 is being met!
  • Butsome application of PBC is nominal.
  • Since program and project management
    accountability still resides with NASA, there is
    a tendency to exercise pervasive control.
  • Risk management provides a framework for
    determining the appropriate level of
    NASA-Contractor engagement.

29
Incorporating Risk Management into the
Acquisition Process
30
Procurement Notice 97-46 Interim Changes to the
NASA FAR Supplement Applicable to solicitations
issued on or after July 13, 2000
31
Interim Rule - 1 of 3
  • Acquisition plan must discuss risk.
  • Acquisition planning must include input from
    safety, health, information technology, export
    control, security, and environment.
  • Draft RFP must invite industry comment on safety,
    security, health, and environmental concerns.
  • RFPs shall require offerors to identify/discuss
    risk issues throughout the proposal, where
    relevant.

32
Interim Rule - 2 of 3
  • Source Selection
  • Mission suitability must include consideration of
    safety and health, when that plan is required.
    For acquisitions or gt10M or, or gt25M
    Commercial, a sub-factor for safety and health
    must be used.
  • Past performance evaluation must include
    security, safety, and environmental damage, where
    germane.

33
Interim Rule - 3 of 3
  • Pre-Negotiation Position Memorandum must address
    any safety and risk issues.
  • Risk Management must be considered under the
    technical award fee factor.
  • No award fee for periods with fatality, mission
    failure, 1M damage, or willful or repeat OSHA
    violations.
  • New clause, Major Breach of Safety or Security
    allows for Termination for Default. Required for
    contracts gt500K.

34
Implementation IssuesThe Devils In the
Details
  • Agency Procurement Working Group
  • Section L and M language?
  • Mid-Range applicability?
  • Resolution of liability issues may delay
    close-out?
  • Identifying Known Risks to Offerors?

35
(No Transcript)
36
SUMMARY RBAM Enables Key Decisions
Surveillance Mode Insight/Oversight
Evaluation Criteria Selection of Contractor
Contract Type and Fee Structure
Contracting Technique
Mode of Implementation In-house, Grant,
Cooperative Agreement, Contract
Development of Work Statement/Requirements
Feasibility Program Go/No Go
Write a Comment
User Comments (0)
About PowerShow.com