Title: UESC Project Implementation
1UESC Project Implementation
Engineering Design Package
Construction Installation
The Payment Period
- Issue TO for construction
- The pre-construction meeting
- Review/accept final construction package
- Commissioning
- Invoices
- Payments
- Periodic Performance Verification
- Follow-on projects
- CO issues TO
- Review ED Package
- CO negotiates final price proposal
Decision Go/ No go
Stop and
2Engineering and Design
- CO issues TO
- Review ED Package
- CO negotiates final price proposal
Decision Go/ No go
3Initiating the Engineering and Design Package
- Issue your task order for engineering and design
- Include agency and site specific requirements
- The utility will respond with a full set of plans
and detailed specifications
4When You Review the Package
- Look for consistency with the feasibility study
in engineering drawings and design specifications - This should be 100, you shouldnt see any new
design in the construction phase - Use FEMP for assistance
- They have specialized expertise in advanced
engineering technologies and can offer cautions
and advice in areas like photovoltaics, systems
controls and others
5Reviewing the ED Package
- The design package should include at least the
following for each ECM - Installation drawings
- 100 of plans and specs
- Commissioning, MV, OM (if required)
- Final price proposal
- Estimated construction schedule
- Planned service interruptions
- Environmental compliance
- Quality control
- ECM installation sequence
6Payments Performance Bonds
- Within a specified time frame after approval of
ECM installation plans, the utility shall submit - Acceptable payment and performance bonds or
- Letter of credit
7Start Planning for Installation
- Make sure that site inspection personnel are
available - Provide for a site individual to assist project
implementation
Youll want to have this set up so you can move
once you see the final construction schedule
8Commissioning and the Design Phase
- Develop design and operating intent
- Perform commissioning-focused design reviews
- Develop Commissioning Plan Specifications for
construction - Should include specifics on commissioning during
construction, acceptance and post acceptance
9Negotiating the Final Price Proposal
- Price proposal includes
- Construction cost
- Financing cost over the term of the loan
- Optional item cost (non-required costs)
- Project management costs
- Interest rate
10Structure the Interest
- Interest payments during the construction period
and the post-acceptance period - Option 1 Structure the financing so that the
cost of interest during the construction period
is added to the total project cost resulting in
one amount to be financed. - This is the most common option
- Option 2 Structure the financing to include
separate interest rates during construction
(short term) and post-acceptance (long term).
11Total Interest Rate
Base rate (SWAP rate) 6.00 Adder
1.40 Hedge 0.36 Total 7.76
Rates can be found at http//www.bloomberg.com/
12Components of the Interest Rate
- Base rate
- Historically based on the Treasury Note rate for
payment term of contract - Currently based on SWAP rate
13Adders
- Basis points added as a result of financiers
perception of projects risk - Basis point 1/100 or .01
- Contributing elements
- Utilitys credit rating
- Loan amount
- Loan term
- Projects technical risk
14Adder Example
- Given a major utility company with a good
balance sheet, a 1 million project with a 10
year term and proven relatively simple
technologies - Adder should be on the low side, 150-180 basis
points - A less appealing project would have a higher
adder
15Hedge
- Basis points that protect the financiers risk of
interest rate fluctuations during project
implementation - A typical hedge is 3-5 basis points per month
- 12 months _at_ 3 basis points per 36 basis points
or .36
16Sources of Financing
- Utility internal financing is not usually
competitive due to internal rate of return
requirement (gt10) - Consider some form of competition for third
part financiers
17Project Management
- Projects are partnerships but the utility is a
business and must make a profit for shareholders - Utility profit (IRR) is typically 10-14 on
services provided - You will be charged for project management and
overhead (OH) fees - OH fees are 15-20 on services portion
- Project management fee is 3-5 depending on
complexity
18Go or No Go?
- Will you continue the process?
- No? Pay for the EDS.
- Yes. CO finalizes the contract, move to
construction and installation
19Construction and Installation
- Issue TO
- The pre-construction meeting
- Final construction package
- Commissioning
20Initiate Project Construction and Installation
- CO issues Task order for Construction and
Installation Phase - Arrange a pre-construction meeting
21Pre-construction Meeting
- The COTR and other facilities or engineering
staff and utility reps must review and
coordinate the project schedule and installation
inspection - Approve the final construction schedule
- Bring in your designated inspection and
implementation site personnel (identified during
DE) - Check to see that appropriate permits have been
acquired
22Construction
- The agency monitors the utilitys and
subcontractors progress throughout the
installation period to assure work is proceeding
as planned
23Project Documents (Deliverables)
- OM manuals for installed ECMs
- Inventory of spare parts (lamps, ballasts)
- As-built drawings or revisions/updates to
existing as-builts - Training
- Warranties
24Commissioning and Acceptance
- Commission each ECM as you go
- The utility must notify the agency when the ECM
is ready for testing and performance verification - The government must verify that new equipment was
installed properly, then test equipment to ensure
that it is performing to spec.
25Commissioning and the Construction Phase
- Building systems including architectural,
structural, mechanical, electrical, and controls
are installed, undergo pre-functional performance
tests, and are placed into operation.
26Project Completion and Acceptance
- Per contract requirements, the utility notifies
the agency of project completion - Agency deems
- Substantial completion/beneficial occupancy
- Final completion and acceptance
- Completion of punchlist
- The agency notifies the utility of project
acceptance
27The Payment Period
- Invoices
- Payments
- Periodic Performance Verification
- Follow-on projects
28Invoices
- Invoices are only accepted and processed after
ECM installation and government signature on a
Certificate of Completion (or whatever is
required by the contract)
29Payments
- CO must notify the utility that the installation
has been accepted and that it complies with the
terms of the contract - Utility bill paid from funding account determined
during acquisition planning
30Post-Installation
- Conduct periodic performance verification
- Receive MV regular interval reports (if
required) - Verify and document the performance and actual
energy savings progressing in sequence, from
individual equipment through subsystem operation
to complete systems and finally whole building.
31Include Training
- Hands-on operation of the equipment including
start-up, operation in normal and emergency
modes, shutdown procedures, seasonal changeover,
and manual/automatic control - Requirements and schedules for routine
maintenance - Energy Management and Control System sequencing,
strategies, operation and programming - Health and safety issues and concerns
- When and how to re-commission
32Performance Acceptance Phase
- Operations are proven under partial and full
load, in all seasons, and under abnormal or
emergency conditions. - Some commissioning contracts require an effort to
fine-tune and optimize system operation, comfort
control, control parameters, sequences and energy
efficiency.
33Performance Acceptance
- Important in ensuring the effective, ongoing
functioning of a facilitys architectural,
structural and other systems. - As use and function of facilities change, the
building systems need to be adapted to the
changing requirements of occupancy and
utilization.
34Follow-on Projects
- Any additional ECMs or services proposed must be
within the contract scope - If desired, CO will issue a task order and
utility will submit a technical and price
proposal.
35Wrap UpQuestion and Answers