UESC Project Implementation - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

UESC Project Implementation

Description:

Make sure that site inspection personnel are available ... Bring in your designated inspection and implementation site personnel (identified during D&E) ... – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 36
Provided by: Cam128
Category:

less

Transcript and Presenter's Notes

Title: UESC Project Implementation


1
UESC Project Implementation
Engineering Design Package
Construction Installation
The Payment Period
  • Issue TO for construction
  • The pre-construction meeting
  • Review/accept final construction package
  • Commissioning
  • Invoices
  • Payments
  • Periodic Performance Verification
  • Follow-on projects
  • CO issues TO
  • Review ED Package
  • CO negotiates final price proposal

Decision Go/ No go
Stop and
2
Engineering and Design
  • CO issues TO
  • Review ED Package
  • CO negotiates final price proposal

Decision Go/ No go
3
Initiating the Engineering and Design Package
  • Issue your task order for engineering and design
  • Include agency and site specific requirements
  • The utility will respond with a full set of plans
    and detailed specifications

4
When You Review the Package
  • Look for consistency with the feasibility study
    in engineering drawings and design specifications
  • This should be 100, you shouldnt see any new
    design in the construction phase
  • Use FEMP for assistance
  • They have specialized expertise in advanced
    engineering technologies and can offer cautions
    and advice in areas like photovoltaics, systems
    controls and others

5
Reviewing the ED Package
  • The design package should include at least the
    following for each ECM
  • Installation drawings
  • 100 of plans and specs
  • Commissioning, MV, OM (if required)
  • Final price proposal
  • Estimated construction schedule
  • Planned service interruptions
  • Environmental compliance
  • Quality control
  • ECM installation sequence

6
Payments Performance Bonds
  • Within a specified time frame after approval of
    ECM installation plans, the utility shall submit
  • Acceptable payment and performance bonds or
  • Letter of credit

7
Start Planning for Installation
  • Make sure that site inspection personnel are
    available
  • Provide for a site individual to assist project
    implementation

Youll want to have this set up so you can move
once you see the final construction schedule
8
Commissioning and the Design Phase
  • Develop design and operating intent
  • Perform commissioning-focused design reviews
  • Develop Commissioning Plan Specifications for
    construction
  • Should include specifics on commissioning during
    construction, acceptance and post acceptance

9
Negotiating the Final Price Proposal
  • Price proposal includes
  • Construction cost
  • Financing cost over the term of the loan
  • Optional item cost (non-required costs)
  • Project management costs
  • Interest rate

10
Structure the Interest
  • Interest payments during the construction period
    and the post-acceptance period
  • Option 1 Structure the financing so that the
    cost of interest during the construction period
    is added to the total project cost resulting in
    one amount to be financed.
  • This is the most common option
  • Option 2 Structure the financing to include
    separate interest rates during construction
    (short term) and post-acceptance (long term).

11
Total Interest Rate
Base rate (SWAP rate) 6.00 Adder
1.40 Hedge 0.36 Total 7.76
Rates can be found at http//www.bloomberg.com/
12
Components of the Interest Rate
  • Base rate
  • Historically based on the Treasury Note rate for
    payment term of contract
  • Currently based on SWAP rate

13
Adders
  • Basis points added as a result of financiers
    perception of projects risk
  • Basis point 1/100 or .01
  • Contributing elements
  • Utilitys credit rating
  • Loan amount
  • Loan term
  • Projects technical risk

14
Adder Example
  • Given a major utility company with a good
    balance sheet, a 1 million project with a 10
    year term and proven relatively simple
    technologies
  • Adder should be on the low side, 150-180 basis
    points
  • A less appealing project would have a higher
    adder

15
Hedge
  • Basis points that protect the financiers risk of
    interest rate fluctuations during project
    implementation
  • A typical hedge is 3-5 basis points per month
  • 12 months _at_ 3 basis points per 36 basis points
    or .36

16
Sources of Financing
  • Utility internal financing is not usually
    competitive due to internal rate of return
    requirement (gt10)
  • Consider some form of competition for third
    part financiers

17
Project Management
  • Projects are partnerships but the utility is a
    business and must make a profit for shareholders
  • Utility profit (IRR) is typically 10-14 on
    services provided
  • You will be charged for project management and
    overhead (OH) fees
  • OH fees are 15-20 on services portion
  • Project management fee is 3-5 depending on
    complexity

18
Go or No Go?
  • Will you continue the process?
  • No? Pay for the EDS.
  • Yes. CO finalizes the contract, move to
    construction and installation

19
Construction and Installation
  • Issue TO
  • The pre-construction meeting
  • Final construction package
  • Commissioning

20
Initiate Project Construction and Installation
  • CO issues Task order for Construction and
    Installation Phase
  • Arrange a pre-construction meeting

21
Pre-construction Meeting
  • The COTR and other facilities or engineering
    staff and utility reps must review and
    coordinate the project schedule and installation
    inspection
  • Approve the final construction schedule
  • Bring in your designated inspection and
    implementation site personnel (identified during
    DE)
  • Check to see that appropriate permits have been
    acquired

22
Construction
  • The agency monitors the utilitys and
    subcontractors progress throughout the
    installation period to assure work is proceeding
    as planned

23
Project Documents (Deliverables)
  • OM manuals for installed ECMs
  • Inventory of spare parts (lamps, ballasts)
  • As-built drawings or revisions/updates to
    existing as-builts
  • Training
  • Warranties

24
Commissioning and Acceptance
  • Commission each ECM as you go
  • The utility must notify the agency when the ECM
    is ready for testing and performance verification
  • The government must verify that new equipment was
    installed properly, then test equipment to ensure
    that it is performing to spec.

25
Commissioning and the Construction Phase
  • Building systems including architectural,
    structural, mechanical, electrical, and controls
    are installed, undergo pre-functional performance
    tests, and are placed into operation.

26
Project Completion and Acceptance
  • Per contract requirements, the utility notifies
    the agency of project completion
  • Agency deems
  • Substantial completion/beneficial occupancy
  • Final completion and acceptance
  • Completion of punchlist
  • The agency notifies the utility of project
    acceptance

27
The Payment Period
  • Invoices
  • Payments
  • Periodic Performance Verification
  • Follow-on projects

28
Invoices
  • Invoices are only accepted and processed after
    ECM installation and government signature on a
    Certificate of Completion (or whatever is
    required by the contract)

29
Payments
  • CO must notify the utility that the installation
    has been accepted and that it complies with the
    terms of the contract
  • Utility bill paid from funding account determined
    during acquisition planning

30
Post-Installation
  • Conduct periodic performance verification
  • Receive MV regular interval reports (if
    required)
  • Verify and document the performance and actual
    energy savings progressing in sequence, from
    individual equipment through subsystem operation
    to complete systems and finally whole building.

31
Include Training
  • Hands-on operation of the equipment including
    start-up, operation in normal and emergency
    modes, shutdown procedures, seasonal changeover,
    and manual/automatic control
  • Requirements and schedules for routine
    maintenance
  • Energy Management and Control System sequencing,
    strategies, operation and programming
  • Health and safety issues and concerns
  • When and how to re-commission

32
Performance Acceptance Phase
  • Operations are proven under partial and full
    load, in all seasons, and under abnormal or
    emergency conditions.
  • Some commissioning contracts require an effort to
    fine-tune and optimize system operation, comfort
    control, control parameters, sequences and energy
    efficiency.

33
Performance Acceptance
  • Important in ensuring the effective, ongoing
    functioning of a facilitys architectural,
    structural and other systems.
  • As use and function of facilities change, the
    building systems need to be adapted to the
    changing requirements of occupancy and
    utilization.

34
Follow-on Projects
  • Any additional ECMs or services proposed must be
    within the contract scope
  • If desired, CO will issue a task order and
    utility will submit a technical and price
    proposal.

35
Wrap UpQuestion and Answers
Write a Comment
User Comments (0)
About PowerShow.com