Title: Contract Administration Issues


1
Contract Administration Issues
2
Daily Work Reports
  • More Detailed Information
  • Working Day Contracts (Include controlling
    operation)
  • Document any changes or decisions made in the
    field

3
Working Day Reports
  • Specifications require bi-weekly statements to be
    sent to Contractor (SiteManager Form)
  • Statement includes number of days charged for the
    period
  • Total days charged on the contract through the
    period
  • Number of working days remaining
  • Contractor has 14 calendar days from receipt to
    protest

4
When Is a Project Complete?
  • Complete Contractor has completed the
    corrective work required by project engineer
  • Completion Notice Submit to Central Office
    Contractor
  • Inspections 90 days from completion notice
  • Erosion, Landscaping, Striping Electrical
    Excluded
  • Importance of Notification

5
Inspections
  • Seeding/Erosion Control
  • 3 to 6 months after project completion
  • Striping
  • Paint (30 to 60 days after open to traffic)
  • Durable Markings (180 days after open to traffic)
  • Plantings
  • 1 growing season if not a major item
  • 3 growing seasons if major item (combination)
  • Inspections after September 15th (end of growing
    season)
  • Electrical Items (Signals/Lighting)
  • 90 days

6
Comprehensive Final Inspection Report
  • Project Engineer Issues to Contractor
  • Includes copies of all inspection reports
  • Excludes Erosion
  • Gives Contractor a Specific Date to complete
    corrective work
  • Liquidated Damages apply if work is not completed
    by the date
  • Usually 90 days unless seasonal limitations

7
Electrical Training
  • Offered by Div. of Traffic Operations
  • Who Should Attend?
  • Section Supervisor or Construction Engineer and
    one inspector per crew
  • One day training will be at 3 regional
    locations

8
Upcoming Electrical Changes
  • Shop Drawings submitted electronically directly
    to Traffic Operations by the Contractor
  • Copy to Project Engineer
  • On-site Pre-Electrical Meetings when traffic
    deems necessary
  • Electrical Questions/Issues
  • Project Engineer will be central contact.
    Project Engineer will contact Traffic Operations
    for guidance.
  • Notify Traffic Operations of all changes
    (Document)
  • ALL ITEMS HAVE BEEN ADDED TO THE PRE-CONSTRUCTION
    CHECKLIST

9
Electrical Changes
  • Contractor will be required to energize lighting
    as soon as it is fully functional and ready for
    final inspection
  • Lighting must remain operational from this point
  • Project Engineer will notify Traffic Operations
    when the electric portion of the project is
    complete
  • The Cabinet will take over the electrical service
    and maintenance of the lighting/signal after the
    electrical work has been accepted

10
Electrical Inspections
  • Traffic Operations will have 90 days to perform
    the final inspection after receiving the
    completion notification
  • Final Electrical Inspection will be sent
    electronically directly to the Project Engineer
    Electrical Contractor (No longer routed thru C.O.
    Construction)
  • Copies to District Central Office Construction
  • Section Office send copy to Prime Contractor
  • Contractor will have 90 days to complete any
    corrective work

11
Electrical Re-Inspection
  • Contractor has 90 days to complete all corrective
    work regardless of the number of re-inspections
    required
  • Once the corrective work is complete, Traffic
    Operations will be notified for a re-inspection
  • Traffic Operations will have 30 days to complete
    re-inspection
  • Time between complete and re-inspection will not
    count toward the 90 days

12
Failure to Complete Electrical Corrective Work
  • Failure to Complete the corrective work within
    the 90 days will lead to penalties being
    assessed.
  • Penalties will be equivalent to 1/2 of the
    liquidated damages rate for the contract
  • Div. of Traffic Operations will document all
    information from electrical completion to
    acceptance
  • Spreadsheet Provided with Dates

13
Key Dates in SiteManager
  • Section Office Responsibility
  • Work Begin
  • Work Complete
  • Open to Traffic
  • Corrective Work Complete
  • Striping/Reflectivity
  • Branch Manager Responsibility
  • Inspection Dates (Resurfacing,Guardrail)
  • Central Office Responsibility
  • Inspection Dates for any project they inspect

14
Final Inspections
  • Uniformity with Inspection Reports
  • Final Inspection reports should be completed
    using the SiteManager report
  • Project workbook report is outdated and reports
    are being sent out with Directors from years past
    listed
  • Concerns with open record requests

15
Special Note 9Y for Material Transfer Vehicle
  • MTV is incidental to the asphalt pavement
  • MTV to be used in driving lanes only
  • MTV to be used on all lifts of asphalt
  • Not just the top lift of base and surface

16
Asphalt Adjustment Special Note
  • Apply to projects let during the months of June
    2009-December 2009 and completed the same
    calendar year
  • Price must increase or decrease by 10 or more
    before the adjustment would be applied

17
Questions?Thank you