Overview and Guidelines for''' - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Overview and Guidelines for'''

Description:

vertical services not included, only tested as agreed between providers 'black box' testing approach. only concerned with LNP compliance ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 19
Provided by: WOO82
Category:

less

Transcript and Presenter's Notes

Title: Overview and Guidelines for'''


1
Overview and Guidelines for...
  • SOA/NPAC, Internal and Inter-carrier testing

2
SOA Testing
  • May 1, 2001 to September 30, 2001
  • Must be coordinated through Neustar
  • Not a topic for discussion in this forum

3
Internal (intra-company) testing
  • Timeframe
  • Now to September 30, 2001
  • Guidelines on Section 1.0.1 of industry test plan
  • Once the intra-company testing of affected nodes
    and network, and the certification testing with
    the Number Portability Administration Center
    (NPAC) is successfully completed, the Test
    Coordinator will schedule inter-company testing.
    Prior to initiating the inter-company testing,
    all intra-company testing must be completed by
    the individual Service Providers.

4
Inter-carrier testing
  • Excerpt from Industy test document Section 1.0.3
  • Each Service Provider will conduct a set of test
    scripts between itself and another service
    provider. Specific combinations of participants
    will be determined by the participants
    themselves, using the recommended list defined
    in Section 3. Participants may choose to run
    additional tests developed by individual Service
    Provider combinations that address any specific
    needs, architectures or business arrangements of
    the testing partners.
  • Service Providers participating in a particular
    location will negotiate for test partners and
    test selections. Their Test Coordinators will
    manage this process by developing a master test
    schedule and track the testing done in each
    location by each Service Provider

5
Wireless/Wireline porting
  • Any porting between wireless and wireline will
    default to wireline long timers

6
Wireless/wireline porting
  • SHORT
  • WPR form
  • Hours of operation - will be discussed later
  • ICC time
  • 30 minutes
  • NPAC T1/T2 timer-
  • 1 hr each
  • LONG
  • LSR form
  • Hours of operation-
  • will be discussed later
  • ICC time
  • 24 hour
  • NPAC T1/T2 Timer
  • 9 hours each

7
Reseller porting
  • Facility based provider is responsible for NPAC
    communication for its reseller
  • FB providers SPID will be on the NPAC record
  • Responsibility for ICC process is determined by
    each carrier

8
Reseller/Facility based provider porting
Wireless to Wireless
Assumption For a complex port it is assumed
that coordination is complete before step 1.
9
Reseller/Facility based provider porting
Wireless to Wireless
Assumption For a complex port it is assumed
that coordination is complete before step 1.
10
WNP Industry Test Plan
  • CTIA Number Advisory Working Group Intercarrier
    test plan (Version 1.0)
  • Section 1 - Scope/Purpose, Assumptions
  • vertical services not included, only tested as
    agreed between providers
  • black box testing approach
  • only concerned with LNP compliance
  • after porting business as usual, no degradation
    to system
  • no vendors mentioned in test plan

11
WNP Industry Test Plan
  • Impacts to system by LNP
  • Porting Order Exchange
  • Service Provisioning
  • Exception Processing Order Cancellation
  • Disconnected TN Snapback
  • Call Flows
  • 911 Record Changes
  • Operator Services
  • Inter-service provider billing

12
WNP Industry test plan
  • Section 2 - Network configuration
    requirements/consideration
  • STP, SCP, SSP, SOA/LSMS requirements
  • Section 3 - Test Planning
  • Test coordinator, manager roles/resp
  • Documenting results
  • Test matrix (Appx. A)

13
WNP Industry test plan
  • Section 4 - Test cases
  • 4.0 Provisioning cases (9 tests)
  • 4.1 Wireless/Wireless test cases (36 tests)
  • 4.2 Wireless/Wireline test cases (16 tests)
  • 4.3 Wireline/Wireless test cases (16 tests)
  • 4.4 Enhanced services (4 tests)
  • TOTAL 81 possible tests
  • Description, procedure, results for each case

14
WNP Industry test plan
  • Appendices
  • Appendix A Test matrix
  • Appendix B Support drawings
  • Appendix C Entry checklist
  • Appendix D Exit checklist
  • Appendix E Sample forms
  • Appendix F Test successful criteria
  • Appendix G Related documents
  • Appendix H Glossary of terms

15
Test coordination
  • MSA
  • Test coordinators from each SP will schedule
    inter-carrier testing dates from this info
  • Company Date ready for testing
  • Company A (11/15/01)
  • Company B (12/12/01)
  • Company C (10/01/01)

16
Future Meetings
  • 1 year until testing should be complete
  • June 2001 to May 2002
  • propose 12 monthly face to face meetings the week
    before WNPO (2 day meetings)
  • 12 monthly conference calls (1/2 day meetings)
  • other ad-hoc meetings can be scheduled as needed

17
Next Meeting Dates
  • Face to Face (2001)
  • Tues Wed week before WNPO
  • June 5,6 Arlington, VA (Telecorp)
  • July 5 (no face-to-face, conf call)
  • Aug 7,8 Denver, CO (Qwest Wireless)
  • Sep 4,5 Seattle, WA (Voicestream or Triton PCS)
  • Oct 2,3 Dallas,TX (Cingular)
  • Nov 6,7 Atlanta, GA (Cingular)
  • Dec 4,5 Sprint PCS or
  • Telcordia
  • WNPO
  • June 11-12 Kansas City, MO
  • July 9-10 Ottawa
  • Aug 13-14 Seattle, WA
  • Sept 10-11 Baltimore, MD
  • Oct 8-9 San Antonio, TX
  • Nov 12-13 New Orleans, LA
  • Dec 10-11 Phoenix, AZ

18
Next Meeting Dates
  • Conf Calls (2 weeks after face-to-face)
  • TIME 12 PM - 4 PM (Eastern)
  • May 24, 2001
  • June 21, 2001
  • July 5, 2001 (due to holiday)
  • July 19, 2001
  • August 23, 2001
  • September 20, 2001
  • October 18, 2001
  • November 29, 2001
  • December - cancelled