Title: WHAT THE SPECIFICATIONS ASK WHEN TESTING CONTROL SYSTEM
1WHAT THE SPECIFICATIONS ASK WHEN TESTING CONTROL
SYSTEM
- Gaylon Richardson
- Engineered Air Balance Co., Inc.
2SPECIFICATIONS
- Does the specification cover what is required to
test the control system? - What is required for testing the terminal boxes?
- What is required for verifying calibration of all
sensors and that the correct sensors control the
proper devices?
3SPECIFICATIONS
- How will each sequence be verified and how should
the test be written? Should all interlocks,
alarms and safeties be identified? - Should the specification cover testing each point
for its proper name and the point responds to a
change in value at the main graphics?
4SPECIFICATIONS
- BOTTOM LINE THE AIR FLOWS CAN BE SET, THE WATER
FLOWS CAN BE SET, BUT IF THE CONTROL SYSTEM IS
NOT VERIFIED TO BE CALIBRATED AND ALL SEQUENCES
OPERATING IT ISNT WORKING.
5What Should Be In The Specification?
- Verify all control devices are properly connected
and operated by the intended controller. - Observe all valves are properly installed in the
piping system in relation to direction of flow. - Verify the proper application of all normally
opened and normally closed valves and dampers.
6What Should Be In The Specification?
- Observe the location of all sensors to determine
whether their position will allow them to sense
only the intended temperatures or pressures. If
the sensor is in the wrong location the Control
Contractor must be required to relocate the
sensor. - Observe the calibration of all controllers.
7What Should Be In The Specification?
- Verify the sequence of operation for all control
modes, that each is in accordance with the
specifications and that the approved shop
drawings are correct. - Verify the operation of all interlock systems.
- Verify all safeties and alarms.
8What Should Be In The Specification?
- Verify on single zone systems there is a dead
band between cooling and heating. - Verify the pressure set points in variable flow
systems track from a full flow condition to a
minimum flow condition. - Document all the above observations and
verifications.
9How Can Everything Be Documented?
- Start with the terminal box controls.
- The flows must be established which involves
testing all flows at maximum and minimum values
and adjusting the terminal box software to
provide the correct airflows.
10How Can Everything Be Documented?
- The terminal box verification should list a
controller number which identifies the
application, the room number, DDC address, type
of terminal, terminal size, cooling and heating
primary maximum settings,
11How Can Everything Be Documented?
- show the calibration of each control sensor (note
some devices can not be calibrated and the
control contractor will replace any device not
within the specified tolerances). - Show control sequence verification.
12How Can Everything Be Documented?
- Show trend logs for room sensors.
- If specified verify all points back to the
central data acquisition system by causing a
change in value and seeing the correct point name
have a change in value at the remote monitoring
point.
13Terminal Box Verification
14Terminal Box Verification
15Sensor Calibration
16Control Sequence Verification
- SYSTEM DESCRIPTION The AHU is designed as a
heating/cooling, dual duct, variable volume air
handling system. The AHU consists of a single
fan with coils located in the blow through
configuration. The AHU has ducted return, 30
pleated pre-filters and 90 final filters. The
cold deck has a reheat coil to avoid saturating
the final filters with moisture. The AHU has a
pressure independent terminal unit providing
pre-treated outside air from AHU-AC-PH-01 and 02.
The AHU unit serves dual duct air terminal units
SAT 1 through SAT 80. High static control dampers
have been added to the cold deck discharge and
the inlet of the hot deck heating coil to
prevent static pressure in either deck from
exceeding 3.75. The VFD serving the AHU has a
bypass switch to allow the motor to operate when
the VFD fails. A pressure relief damper has been
installed to reduce the pressure in the discharge
plenum when in bypass.
17Control Sequence Verification
- PREREQUISITE TEST PRIOR TO CONTROL SEQUENCE
VERIFICATION All return, supply terminals and
OSA terminals must be balanced. The Terminal Box
Control Verification Forms must be complete.
The AHU will be traversed with all terminal boxes
set for maximum cooling, maximum heating, and
total submittal airflow (if the AHU does not
have a connected airflow to equal the submitted
airflow the cold deck terminal boxes in the
flexible zone will be set to 2000 fpm inlet
velocity to verify the maximum airflow of the
AHU). All water flows must be balanced and coil
capacities established.
18Control Sequence Verification
- Des Max Cooling CFM 36920 Act Max CFM 38455
- Des Max Heating CFM 14660 Act Max CFM15625
- Heating Max CFM 20920 Act Cool CFM 21570
- Sub Max Cool CFM 42000 Act Cool Max 40210
- Des RA CFM 28655 Act RA CFM 30545
- Des OSA CFM 8255 Act OSA CFM 8255
- Minimum Speed Set point 20HZ
19Control Sequence Verification
- AHU SEQUENCE START The fan will be enabled
through a signal from the BAS with the VFD in the
auto position. Upon a fan start command the
variable frequency drive (VFD) will operate at a
preset minimum speed. The BAS will monitor the
discharge static pressure sensors. The
pretreated outside air terminals will open to
their airflow setpoint. - Minimum Speed Set point 20HZ
20Control Sequence Verification
- STATIC PRESSURE CONTROL The hot and cold
decks are monitored with static pressure sensors
located 2/3 down the ductwork. The static
pressure control loops senses the static pressure
in the hot and cold decks and sends a signal to
the VFD to modulate the fan speed to satisfy the
lower of the two static pressure signals being
monitored. - Full Cooling Cold Deck SP 1.40 _at_ 58.8 HZ
- Full Heating Hot Deck SP 1.40 _at_ 46.3 HZ
21Control Sequence Verification
- With the terminal boxes in control the static
pressure set point will be raised 0.20 above set
point and lowered 0.40 below set point. The VFD
response to change will be shown by recording the
static pressure maintained and the operating
hertz. After all adjustments are made the system
will be returned to its original operating
conditions. - Raise SP 1.60 _at_ 43.5 HZ
- Lower SP 1.00 _at_ 39.1 HZ
22Control Sequence Verification
- The hot and cold deck static pressure sensors
located 2/3 down the ductwork are also used to
control the discharge static pressure loops that
will modulate the discharge damper in the hot or
cold duct. The duct having the highest static
pressure of the two will be controlled at 2.0.
The static pressure control will be tested from
full cooling to full heating by placing terminal
boxes to full heating two at a time. The static
pressure sensors located 2/3 down the duct and at
the fan discharge will be observed after each box
is set for heating until all terminal boxes are
at full heating.
23Control Sequence Verification
- The same test will be performed by returning
each terminal box to full cooling until all
boxes are at full cooling. The static pressures
and VFD HZ will be recorded with terminal boxes
set for 100, 75, 50, 25 of maximum cooling
airflow and 100, 75, 50, 25 maximum heating
airflow. - 100 Cooling Discharge 1.40 CD 3.67 HD 58.8 HZ
- 75 Cooling Discharge 1.40 CD 2.61 HD 49.1 HZ
- 50 Cooling Discharge 1.40 CD 1.64 HD 40.0 HZ
- 25 Cooling Discharge 1.40 CD 2.01 HD 42.3 HZ
- 100 Heating Discharge 2.22 CD 1.40 HD 46.3 HZ
- 75 Heating Discharge 2.18 CD 1.41 HD 43.0 HZ
- 50 Heating Discharge 1.99 CD 1.40 HD 39.1 HZ
- 25 Heating Discharge 1.39 CD 1.64HD 36.0 HZ
24Control Sequence Verification
- HOT DECK TEMPERATURE CONTROL The hot deck
temperature control loop is enabled by the fan
status proof through the BAS. The control loop
will modulate the hot water control valve to
maintain a discharge air temperature set point at
the temperature sensor. The hot deck temperature
set point is reset through the BAS. - Heating Valve Control Verification
- Heating Coil Discharge Air gt Set point Hot
Water Valve Will Modulate Closed - Heating Coil Discharge Air lt Set point Hot Water
Valve Will Modulate Open - Heating Coil Valve will close when the AHU is
disabled from the BAS
25Control Sequence Verification
- Hot Deck Reset As the Outside Temperature falls
below 70?F the hot deck temperature will increase
0.3?F for every 1?F drop in outside temperature.
At 30?F the hot deck temperature will be 95?F.
Adjust the virtual outside air point to
85?F,50?F,30?F and verify the hot deck
temperature. The reset schedule is as follows - Outside Air Temperature Hot Deck
Temperature
30?F
95?F - 70?F
80?F - Test 1 85?F OSA 80?F HDT
- Test 2 50?F OSA 87.5?F HDT
- Test 3 30?F OSA 95?F HDT
26Control Sequence Verification
- COLD DECK TEMPERATURE CONTROL The cold deck
temperature control loop is enabled by the fan
status proof through the BAS. The control loop
will modulate the cold water control valve to
maintain a discharge air temperature set point at
the cooling coil discharge air temperature
sensor. The control loop will also modulate the
hot water control valve serving the reheat coil
to maintain a discharge air temperature at
the reheat discharge air sensor. - Cold deck Discharge Set point 52?F
- Reheat Discharge Set point 54?F
27Control Sequence Verification
- Cooling Valve Control Verification
- Cooling Coil Discharge Air gt Set point Chilled
Water Valve Modulate. Open - Cooling Coil Discharge Air. lt Set point Chilled
Water Valve Will Modulate Closed - Cooling Coil Valve will close when the AHU is
disabled from the BAS - Set point 52?F
28Control Sequence Verification
- Re-heat Valve Control Verification
- Re-heat Coil Discharge Air gt Set point Hot Water
Valve Will Modulate Closed - Re-heat Coil Discharge Air lt Set point Hot Water
Valve Will Modulate Open - Re-heat Coil Valve will close when the AHU is
disabled from the BAS - Set point 54?F
29Control Sequence Verification
- Dehumidification Control The BAS will
monitor the relative humidity in the return air
duct. If the return air relative humidity exceeds
60 the cold deck discharge air temperature will
be lowered 1?F per 5 humidity above 50. The
cold deck will be proportionally lowered
from 52?F to 50?F. When 50 relative humidity is
obtained the cold deck temperature set point will
return to 52. Return relative humidity gt 60
cold deck temperature 50?F. Return relative
humidity lt 50 cold deck temperature 52?F. - Set point 60
- Set point 50?F
30Control Sequence Verification
- SAFTIES
- A high static pressure sensor is located in the
hot deck and the cold deck. If the set point of
either sensor is exceeded the VFD will stop the
fan. - Set point 3.75
- Fire smoke detector (FSD-1) located in the
return duct will signal the VFD to stop the fan - Fire smoke detector (FSD-2) located in the hot
duct will signal the VFD to stop the fan - Fire smoke detector (FSD-3) located in the cold
duct will signal the VFD to stop the fan.
31Control Sequence Verification
- ALARMS
- Discharge Air Temperature- If the discharge air
temperature in the cold deck is below 45 F or
above 65 F for more than 5 minutes an alarm will
be initiated at the BAS workstation. - If the final filter in either the hot deck or
cold deck differential pressure exceeds 1.20 WG
for more than 10 minutes an alarm will be
initiated at the BAS workstation. - If the pre-filter differential pressure exceeds
0.5WG for more than 10 minutes an alarm will be
initiated at the BAS workstation. - If the VFD is not in the auto position an alarm
will be initiated at the BAS workstation. - If the fan commanded value does not match the
status proof condition an alarm will be initiated.
32Control Sequence Verification
- Alarm when cold deck lt 45 F for 5 minutes
- Alarm when cold deck gt 65F for 5 minutes
- Alarm when CDl filter ?P gt 1.2 WG for 10min
- Alarm when HDl filter ?Pgt 1.2 WG for 10 min
- Alarm when pre- filter ?Pgt 0.5 WG for 10 min
- Alarm when VFD not in auto position
- Alarm when fan commanded value does not match the
status proof condition
33Control Sequence Verification
- STOP BMS DISABLED (VFD IN AUTO)
- Unit Disabled
- Fan Stop - AHU status off
- OA terminal disabled
- Controls disabled
34Control Sequence Verification
- VFD FAILS-ENABLE AHU WITH THE BYPASS SWITCH
- When the bypass switch enables the AHU fan
the relief damper will be driven open to a pre
set position and remain in place for three
minutes. The damper will be released to control
the discharge plenum to 5.0 WG. The control
system will function as described above.
35Control Sequence Verification
- Test the relief damper with all dual duct
terminal boxes set for full cooling and the VFD
in bypass. Test the relief damper with all dual
duct terminal boxes set for full heating and the
VFD in bypass. Measure the SP in the discharge
plenum and downstream of the discharge dampers
during both tests. - Full Cooling Static Pr Discharge 2.01 CD 2.68 HD
- Full Heating Static Pr Discharge 1.98 CD 1.65 HD
36Point to Point
37Point to Point
38Conclusion
- When writing control sequence verifications the
main source should be the specifications. - As changes are made to the system because of job
conditions the specification must be changed to
reflect the change.
39Conclusion
- As changes are made the shop drawings, control
sequence verification and commissioning plan
must be updated. - All systems have some differences and a
verification used on the last system probably
will not work on the next.